Bratsk Hydroelectric Power Station


The Bratsk Hydroelectric Power Station is a concrete gravity dam on the Angara River and adjacent hydroelectric power station. It is the second level of the Angara River hydroelectric station cascade in Irkutsk Oblast, Russia. From its commissioning in 1966, the station was the world’s single biggest power producer until Krasnoyarsk Hydroelectric Power Station reached 5,000 MW in 1971. Annually the station produces 22.6 TWh. Currently, the Bratsk Power Station operates 18 hydro-turbines, each with capacity of 250 MW, produced by the Leningrad Metal Works in the 1960s.

Design and specifications

Dam

Components:
On the top of the dam are the track of the Taishet-Lena railway line and a vehicle road.
There are no navigational channels, because the Angara has no through ship routes. Nevertheless, the construction project includes the possibility to build a ship elevator.

Power plant

The Turbine Hall contains 18 Francis hydroturbine units, 250 MW each, with 106 m of operating head. A 5,140 m-long penstock forms the Bratsk Reservoir. With a 4,500 MW capacity, and 22.6 TWh of annual output, it is Russia's second largest single producer of hydroelectricity. Output is distributed into five 500 kV power lines and twenty 220 kV lines.
The plant was designed by the Moscow-based Hydroproject institute, and is operated by the joint-stock company Irkutskenergo, although all the buildings themselves belong to Russia's federal government. A reconstruction project includes increasing the output towards 5,000 MW. At present, Irkutskenergo together with JSC Silovii Mashini is modernizing the aging turbines.

Economics

The plan to build the hydroelectric plant was approved in September 1954 and later that year the first workers and machines arrived at Bratsk. On December 21, 1954 preparation works were initiated by the Nizhneangargasstroy departament, later renamed to Bratskgasstroy. Concurrently, the city of Bratsk was founded. On December 12, 1955 Bratsk was officially converted from a workers settlement into a city by the decree of the Presidium of the Supreme Soviet of the RSFSR.
Construction was declared as the Komsomol's high-tempo priority goal and was in the center of public attention. Eventually, a lot of the workers were awarded state prizes and the plant became a symbol of the industrial development of Siberia.
From July 1955 to October 1957 the 220 kV power line to Irkutsk was constructed. On November 6, 1957 the Bratsk substation received the first current from the newly constructed plant and later that year this current was transmitted to Irkutsk for the first time via the newly created power line. In 1961 the second 500 kV power line was added.
On July 18, 1961 the Bratsk Reservoir started filling. First stationary 225 MW generator became operational on November 28, 1961 at 10:15 local time. After 7 days on December 5 the second unit No. 17 started to operate and on December 12, 1963, units No. 16 and No. 15 were included into the Unified Energy System of Siberia. On May 9, 1964, operators began to control the plant as the central control post was put into service. On September 30, 1964, the last cubic meter of concrete was poured into the dam wall.
Construction of a railway track over the dam began on March 3, 1965 and it started to operate on June 16. A vehicular road opened on July 28.
On December 14, 1966 the last unit, No. 1 was operational and on September 8, 1967, the State Commission accepted the inclusion of Bratsk into constant use.