Wuhan–Guangzhou high-speed railway


The Wuhan–Guangzhou high-speed railway, also called the Wuguang high-speed railway and short for Beijing–Guangzhou–Shenzhen–Hong Kong high-speed railway, Wuhan–Guangzhou section, is a high-speed rail line, operated by China Railway High-speed, connecting Wuhan and Guangzhou, the provincial capitals of Hubei and Guangdong, respectively. It was the world's fastest train service, initially using coupled CRH2C and CRH3C trains which averages in non-stop commercial service.
The line is part of the 2230-km long Beijing–Guangzhou–Shenzhen–Hong Kong high-speed railway. Since the railway line opened ten years ago, it has transported 500 million passengers and provided over 500000 train services.

Rolling stock

When the line opened, the trains had a maximum in-service speed of according to Chinese sources. Each train consists of two eight-car electric multiple units coupled together to make a 16-car train. The passenger capacity of the train is about 1114 or 1220. The trains are based on technology developed by Siemens and Kawasaki modified to the standards of China Railway High-speed. The trains used on the line are manufactured in China.
On December 3, 2010, the new China Railways CRH380A trainset started serving this line.

Commercial service

The first commercial trains left Wuhan and Guangzhou North at 9:00 am on December 26, 2009, and reached their destinations in three hours, compared with ten and a half hours for the previous service.
From December 28, 2009, until Guangzhou South Station was opened on January 30, 2010, 28 passenger train services run on the line daily each way. Of these 28 trains, two run between Wuhan and Changsha South, five run between Changsha South and Guangzhou North, and 21 run between Wuhan and Guangzhou North.
Nonstop trains, now cancelled, covered the 922-km long journey in a scheduled 02h57m or 02h58m. This is an average speed of between stations. Before this line was opened, the fastest commercial train service between stations was the train run between Lorraine TGV and Champagne TGV in France, averaging.
Guangzhou South Railway Station was opened on January 30, 2010, just before the Chinese New Year. Trains arrive at or depart from Guangzhou South instead of Guangzhou North since then. During the first 56 days in 2010, the railway transported 1.108 million people, or 43 thousand per day. The total ticket income was about ¥700 million, exceeding earlier predictions.
More trains have been added to the route since March 3, 2010.
On July 1, 2010, coupled trains were replaced by single trains, and service frequency was doubled - from two daily non-stop 03h08m-long services between Wuhan and Guangzhou to six daily 03h16m-long services with one stop in Changsha South - these services departed on the hour.
On September 20, 2010, even more trains were added. There were then 75 trains in each direction on weekdays and 80 trains in each direction on weekends. The average train interval had been cut to 11 minutes. On October 1, 2010 during the National holidays, the railway line transported 118 thousand people in a single day.
In August 2011 the maximum speed of Chinese high-speed trains was reduced to following the Wenzhou train collision but was restored to 350km/h in late 2017. In August 2011 the fastest trains between Wuhan and Guangzhou South, with one stop at Changsha South, had a scheduled trip time of 3 hours and 33 minutes.
From April 1, 2012, the service was extended with through trains running between Wuhan and Shenzhen North station. Initially there are 10 services each day in each direction with the fastest train taking 4 hours, 11 minutes.
Since the railway line opened ten years ago, it has transported 500 million passengers and provided over 500000 train services.
On January 23, 2020, due to the COVID-19 pandemic and as part of the efforts to contain it, the Chinese authorities and city government announced that all services were suspended until further notice.

Line

Construction work began on June 23, 2005. The line cost approximately CN¥116.6 billion. Xu Fangliang was the general engineer in charge of designing the line.
of the railway line is laid on bridges, and is in tunnels, totaling 2/3 of the entire length. There are 684 bridges and 226 tunnels along the line. The signalling system deployed on the line is CTCS-3.
There are eighteen stations on the line. Fourteen of them are opened for passenger service. The northern terminal, Wuhan Railway Station was opened simultaneously with the railway line. Guangzhou South station was opened later on January 30, 2010. Lechang East and Yingde West stations are under construction. Wulongquan East is an overtaking station which is not open for service.
On December 9, 2009, a train achieved a top speed of and took 02h55m to travel from Guangzhou South to Wuhan during a test run.

Fare

The second class fare is about ¥0.465 per kilometer between 0–500 km, ¥0.415 per kilometer between 500–1000 and ¥0.365 per kilometer after 1000 km. The first class fare is 60% higher. Deluxe class is also available on CRH3 trains, which is about 80% higher than second class. Like other train services in China, insurance of ¥0.0011722 per kilometer is included for every ticket. The ratemaking distance is based on the existing Jingguang Railway, not the actual rail distance of the new railway. Hence, though the actual rail distance between Wuhan and Guangzhou South is, is charged. The ticket price between the two terminal stations is ¥490 and ¥780.

Criticisms

Reaction from existing passengers

With an average speed 4 times faster, the fare for the high-speed railway is also about 4 times expensive than the ordinary railway fare. Some believe this is too high for the public. RMB490 is about 15% of the average monthly income of workers in Guangzhou. After opening of the high-speed railway, 13 out of 45 ordinary trains were canceled, a decision criticized to have harmed the welfare of low-income workers. Hence, the existing passengers complain that they are "forced to travel high-speed".
Many passengers also disliked the cancellation of many of the "conventional" trains that used to provide overnight service between Wuhan and Guangzhou. While they were much slower than the new high-speed train, overnight service provided the convenience of traveling while sleeping.
There has also been some vocal criticism of a lack of group discounts, so organised tour operators have to pay full fares for every tourist, when airlines will offer special discounts. With airlines reducing services on the high-speed routes, high-speed rail is the only effective time saving option during the short holiday breaks, such as Mid-Autumn Festival, May Day and Qing Ming Festival, making such trips more expensive.

Reaction from airlines

, a national airline with one of two hubs in Guangzhou, spoke of concern over eroding market share from competition. Thirty-eight of 160 plus China Southern domestic routes will compete with the rail line. The airline has aggressively cut fares, slashing the advance purchase price of flights between Wuhan and Guangzhou by almost half.
Tan Wangeng, president of China Southern Airlines, said, "In the long run, the coming of high-speed railway age is an opportunity rather than challenge to our airline company. China Southern is expecting cooperation with the railway company to extend the market and develop more packaged travel products for the passengers."