Sha Tin to Central Link


DateEvent
1960sPredecessor East Kowloon Line was proposed by British consultant Freeman, Fox, Wilbur Smith & Associates
2000Sha Tin to Central Link first appeared in the government document Railway Development Strategy 2000
2002KCRC won its bid to build SCL, building an independent line from Tai Wai to Central West
2005KCRC modified its 2002 plan, making East Kowloon portion of the line join Ma On Shan Rail at Tai Wai and West Rail at Hung Hom. The East Rail would extend to Central West
MTRC submitted a new proposal: extending Kwun Tong Line to Whampoa, and building a new independent line from Tai Wai to Central West
2006MTR–KCR merge was confirmed. Non-binding memorandum of understanding signed by government and MTRC. Yet, SCL would be built in accordance to KCRC 2005 plan, while Kwun Tong line extension would also be constructed
2007MTR–KCR merge
2008MTRC announced a revised proposal, fully funded by government
2012Executive Council approved and construction began
2015First rolling stock for East West line arrived in Hong Kong
2016Kwun Tong line extension commence
11-kilometre tunnel of East West line was fully broken through
2018Whistleblowing on poor construction quality at the Hung Hom station
A Commission of Inquiry is appointed by Chief Executive of HKSAR government
2019Commencement of whole SCL postponed
SCL split into Tuen Ma line First Phase and Second Phase due to construction quality of Hung Hom station

The Sha Tin to Central Link is an expansion of the MTR rapid transit network currently under construction in Hong Kong. It is divided into two sections.
The first section, codenamed “Tuen Ma Line”, runs from Tai Wai station in the New Territories to Hung Hom station in Kowloon. The Tai Wai–Hung Hom segment will connect the Ma On Shan line and West Rail line, forming the new Tuen Ma line. Operation of the Tai Wai to Kai Tak section began on 14 February 2020. The opening of the section from Kai Tak to Hung Hom has been delayed to the first quarter of 2021.
In anticipation of the Tuen Ma Line, the existing Kwun Tong line was extended from its previous terminus at Yau Ma Tei to Whampoa station. This extension includes the new Ho Man Tin station to provide interchange with the Tuen Ma Line. The Kwun Tong line extension was opened on 23 October 2016.
The second section, codenamed the “East Rail Line”, runs from Hung Hom to Admiralty on Hong Kong Island. The Hung Hom–Admiralty segment will be an extension of the East Rail Line. This cross-harbour extension is scheduled to be completed in the first quarter of 2022.

History

The proposed route of the Sha Tin to Central Link roughly follows the scheme of the original East Kowloon line, which was proposed in the late 1960s but was not constructed. The Shatin to Central Link was included as one of the Priority Railway Schemes in the Hong Kong government's Railway Development Strategy 2000.
On 25 June 2002, the government announced that the Kowloon–Canton Railway Corporation had won its bid against the MTR Corporation to build and operate the Shatin to Central Link. The route was originally planned to go from Tai Wai station to Central West station, as an extension of the then-under-construction KCR Ma On Shan Rail.
The KCRC announced modifications to the proposal in 2005, with the East Kowloon portion of the line joining KCR Ma On Shan Rail at Tai Wai and KCR West Rail at Hung Hom, with the cross-harbour portion joining KCR East Rail at Hung Hom. Mong Kok Station would have been relocated, joining a new tunnel to a deeper Hung Hom station platform connecting to the cross-harbour section. Additionally, stations at Tsz Wan Shan and Whampoa Garden were removed from the proposal; the areas would instead have been served by people movers from other stations. However, the KCRC's proposal had not yet been finalised.
At the same time, the MTRC submitted a new proposal to the government. According to the proposal, the Kwun Tong line would be extended from Yau Ma Tei station to Whampoa station, and the route of the SCL would follow the KCRC's original proposal instead of the 2005 modified proposal. An underground train depot would have been built beneath the passenger terminal of the former Kai Tak International Airport, adjacent to Prince Edward Road East in Kowloon City; however, under the Kai Tak redevelopment plan released by the government in October 2006, the depot would have to be constructed somewhere else.

MTR–KCR merge plan

On 11 April 2006, MTRC signed a non-binding memorandum of understanding with the government of Hong Kong, the owner of KCRC, to merge the operations of the territory's two railway networks. According to the memorandum, the MTRC-owned MTR lines will be fully integrated with the Shatin to Central Link, which will be part of the MTR system. The government also intended to choose the KCRC's modified proposal to build the railway, that is, extending the current East Rail line to Hong Kong Island. However, final decisions were not made before conducting further studies on the proposal with the MTRC.
The new proposal was announced jointly by both companies on 12 July 2007, before the merger of the two rail networks on 2 December that year. Under this proposal, the depot for the Sha Tin to Central Link would have been built underneath the former Tai Hom Village site between Kai Tak and Diamond Hill stations. The people movers were omitted; Causeway Bay North station was also removed from the proposal due to potential adverse effects on road traffic during construction.
The MTRC announced a revised proposal on 11 March 2008. The government would fund all of the required for construction. The Executive Council approved the construction cost of HK$79.8 billion in March 2012 and construction began on 22 June 2012. Under the final proposal, the former Hung Hom Freight Yard adjacent to Hung Hom station will be converted into stabling sidings for Sha Tin to Central Link trains, and new access tracks will be constructed to link the Sha Tin to Central Link with the former Hung Hom Freight Yard. Central South station was excluded in the modified plan, as no suitable sites had been found. One station at Hin Keng was added to the proposal afterwards, to alleviate congestion at Tai Wai station.

Expected commencement

The original commencement date of Phase 1 was 2018; Phase 2 was expected to be completed in 2020 or 2021. Some of the construction work of Phase 2 will follow the completion of Wan Chai Reclamation Phase 2 and Central–Wan Chai Bypass, as there are overlaps between station and tunnels. On November 2014, Secretary for Transport and Housing Anthony Cheung revealed that the project would be delayed by at least another 11 months, caused by archaeological Work at To Kwa Wan station, and extra enabling works at Exhibition Centre station for topside development. At that time, the authority submitted a document to the Legislative Council, stating Phases 1 and 2 would be completed in 2019 and 2021 respectively.
However, the opening was delayed again due to construction quality problems at Hung Hom station. In January 2020, Secretary for Transport & Housing Frank Chan announced the "Tuen Ma line first Phase" would be open in 14 February 2020, the rest of the Tuen Ma line would open in late 2020 or early 2021, and the MTR expects the opening of the East Rail line extensions in the first quarter of 2022, but is subject to change.

Hung Hom station scandal

In 2018, a whistleblower leaked information to the Hong Kong media stating that the construction quality at the Hung Hom station was substandard. Namely, the threaded steel bars that were supposed to link to each other were cut so that they would fit into couplers without actually connecting to the full extent
This raised concerns that the platform is not as strong as it was designed to be. Although initially denying the allegations, the MTR and the contractor later confirmed them, and proposed a plan to open up the concrete at some areas of the stations to inspect the construction quality.
The investigation also revealed further incidents of substandard work and missing construction records. For example, 40% of Request for Inspection and Survey Checks forms for the northern approach tunnels are missing.

Construction and facility enhancement

New railway lines and track

The 11-kilometre tunnel of the East-West Corridor was fully broken through in August 2016.
As of February 2017, construction and tunnel boring is underway for the sections between the Exhibition Centre station and Causeway Bay, and between Causeway Bay and Kowloon. MTRC has set up an Immersed Tube Tunnel Casting Yard at the site of the former Shek O Quarry at the south side of the Hong Kong Island to pre-assemble sections of the tunnel tubes, which will be then transported by sea and immersed in place. As June 2017, the first Immersed Tube Tunnel units was installed in Victoria Harbour, marking the beginning of constructing the fourth harbour-crossing railway tunnel in Hong Kong. 11 tube tunnel units in total will be constructed and placed for the harbour crossing section.

New signalling systems and station facilities

Both of the new corridors will receive new signalling systems as part of the Sha Tin to Central Link project. The technology, known as communications-based train control, will minimise train intervals while complying with existing and future infrastructure, such as platform doors/gates.
The East West Corridor will use SelTrac CBTC supplied by Thales. This is an updated, more modern version of the Seltrac IS technology already installed on the West Rail line, Ma On Shan line, and Kowloon Southern Link. New on-board computers are being retrofitted to the existing SP1900 trains as part of their modifications to form 8-car trains, supplemented with newly acquired 8-car trains delivered with the new computer already installed. All stations on the Ma On Shan Line have also received half-height platform gates in conjunction with the upgrade, and new underground stations will have full-height platform doors installed.
The North South Corridor will have the TBL train protection and Alstom's ATO system in use on the current East Rail Line including the Lok Ma Chau Spur Line replaced with Trainguard MT CBTC supplied by Siemens. At the same time, all platforms would be modified and equipped with half-height platform gates to provide level boarding and minimize the gap with the train. Refurbishment and expansion work on platforms and stations will also be carried out.
Admiralty, Diamond Hill and Hung Hom stations, all of which will become major interchanges following full opening of the new lines, will be expanded or relocated to cater to increased demand.

New rolling stock

The East West Corridor will operate using a combination of both new and existing rolling stock, while the North South Corridor will have its existing rolling stock fully replaced with new stock.
was removed from the 2007 final proposal due to its depth. Because of this, pedestrian facilities with lifts, travellers and covered walkways will be built for the Tsz Wan Shan community, connecting with Diamond Hill station.
On Hong Kong Island, Wan Chai Swimming Pool and Harbour Road Sports Centre were both re-provisioned on alternate sites, as the original buildings were demolished to make way for Exhibition Centre station.
Hongkong Post's International Mail Centre in Hung Hom was also demolished to make way for the line. It was rebuilt in Kowloon Bay and renamed the Central Mail Centre.

Route

From the Ma On Shan line at Tai Wai station, the Tuen Ma Line will continue southwards on an embankment to Hin Keng station, and then head southeast in tunnel towards Kowloon. After Diamond Hill station, the line will turn southwest and continue in tunnel through Kowloon City to Hung Hom station, interchanging with the Kwun Tong line extension at Ho Man Tin along the way. At Hung Hom, the East West Corridor will connect to the West Rail line just south of its new platforms at the station and interchange with the East Rail Line.
The East Rail Line extension will connect to the East Rail Line north of Hung Hom station, adjacent to the southern portal of the tunnel under Princess Margaret Road; and will enter a tunnel to new platforms at Hung Hom station, interchanging with the Tuen Ma Line. The line will then traverse under Victoria Harbour, parallel to the Cross-Harbour Tunnel, and then continue in tunnel westwards from the Causeway Bay Typhoon Shelter to Exhibition Centre and Admiralty stations.
The Kwun Tong line extension, an associated project completed in late 2016, is a southeast extension of the Kwun Tong line from Yau Ma Tei station to Ho Man Tin station, where there will be an interchange to the Tuen Ma Line. The line then continues under Wuhu Street and Tak On Street to a single dead-end platform at Whampoa station.

Stations

Naming

At initial stage, Sung Wong Toi station was named as To Kwa Wan station, while To Kwa Wan station was named as Ma Tau Wai station. Yet, such naming did not please adjacent community as geographically former To Kwa Wan station was not recognised as part of To Kwa Wan. Therefore, MTR internally amended the naming but had not been revealed to public until 2017 Panel on Transport of Legislative Council.