Régua Dam


Régua Dam is a concrete gravity dam on the Douro, where the river forms the border line between the districts of Vila Real and Viseu. It is located in the municipality Peso da Régua, in Vila Real District, Portugal.
Construction of the dam began in 1965. The dam was completed in 1973. It is owned by Companhia Portuguesa de Produção de Electricidade.

Dam

Régua Dam is a 41 m tall and 350 m long gravity dam with a crest altitude of 81 m. The volume of the dam is 108,000 m³. The spillway with 5 radial gates is part of the dam body. There is also a bottom outlet.

Reservoir

At full reservoir level of 73.5 m the reservoir of the dam has a surface area of 8.5 km² and a total capacity of 95 mio. m³. The active capacity is 12 mio. m³.

Power plant

The run-of-the-river hydroelectric power plant was commissioned in 1973. It is operated by EDP. The plant has a nameplate capacity of 180 MW. Its average annual generation is 581.1 GWh.
The power station contains 3 Kaplan turbine-generators with 58.84 MW each in a dam powerhouse located on the right side of the dam. The turbine rotation is 107.1 rpm. The minimum hydraulic head is 20 m, the maximum 27.5 m. Maximum flow per turbine is 316 m³/s.
The turbines were provided by Kværner, the generators by Brown, Boveri & Cie.

Lock

On the left side of the dam is a lock, which can handle ships with the following maximum properties: 83 m in length, 11.40 m on the beam, 3.8 m load-draught and a cargo capacity of 2500 tons.