Kai Tak Development


The Kai Tak Development, abbreviated as "KTD" and formerly called South East Kowloon Development, refers to the redevelopment of the former Kai Tak Airport site in Kai Tak, Kowloon, Hong Kong.
After the airport relocated to Chek Lap Kok in 1998, the Hong Kong government planned for urban development on the old airport site. The plan calls for a multi-purpose sports complex, a metro park, the Kai Tak Cruise Terminal, a hotel, a housing estate, and commercial and entertainment construction projects over an area of more than. The plan also covered nearby development in areas including Ma Tau Wai, Kowloon City, San Po Kong, Kowloon Bay and Kwun Tong.
The planned population is 86,000 people, accommodated in 30,000 housing units, including 13,000 constructed as part of public housing estates. The total gross floor area is over with over of open space. The total cost for the development is about HK$100 billion.
After several years of planning and discussion, and the decision of a judicial review on Central and Wan Chai Reclamation, the Hong Kong government restarted KTD review and planning in 2004. The Executive Council passed the revised development plan and restarted the project. According to the development plan, the first stage projects finished in or before 2013. The second stage projects will be finished in or before 2016 and the final stage projects will be completed in or before 2021.

History

1980s

The Hong Kong colonial government commissioned the "Study on Harbour Reclamations and Urban Growth" in October 1983. It was a study for a proposed plan to address the urban development of Hong Kong. The government worked on the "Metroplan Selected Strategy" study between 1987 and 1990. Its purpose was to provide a wide-ranging plan for urban renewal-focused land-use, transportation and environmental planning. The study area included West Kowloon, Kai Tak and other regions. The study was passed by the Executive Council of Hong Kong on 17September 1991. Afterwards, related government departments implemented the strategy according to the study.

1990s

In 1998, the Hong Kong Planning Department undertook several studies on East Kowloon development. After several modifications, the land reclamation plan and the population plan were altered considerably.

South East Kowloon Development Statement (June 1992-1993) ()

This plan proposed the development of Kai Tak as a "City Within a City", covering, including of reclaimed land. It proposed land development for residential, commercial and industrial use. The new town designated population was around 285,000. The development would also include a park and a promenade. The proposed development included two MTR connections, with Diamond Hill and Kwun Tong.

Feasibility Study for South East Kowloon Development (September 1995-1998) ()

The study refocused the development as a "City Within a City" with territorial facilities. The site area and reclamation provisions remained the same as in the previous proposal. However, the designated population rose to 320,000 while the metropark was expanded to. It was also the first plan to propose leisure facilities, such as a multi-purpose sports complex and aviation museum. Other facilities, including a hospital, rail yard, and post office were proposed. The MTR provisions were replaced by the Sha Tin to Central Link.

2000s

Comprehensive Feasibility Study for the Revised Scheme of South East Kowloon Development (November 1999-2003) ()

The study re-designated the Kai Tak Development as an "Environmentally Friendly City". In response to opinions on land reclamation, the authority reduced the reclamation area to while the overall site area declined to. The new designated population is 26,0000. The metropark was to shrink to but the promenade would be extended to. It also first proposed a cruise terminal. The MTR-centric strategy continued in the study, with the new Environmentally Friendly Linkage System proposal.
In June 2002, the Executive Council of Hong Kong approved Outline Zoning Plans for Kai Tak and Kai Tak. Major development projects included the MTR Sha Tin to Central Link depot on the original airport site, a multi-use stadium, a metropark, the Kai Tak Cruise Terminal with helicopter landing site at the end of former runway, and the Central Kowloon Route. Also, a new "Trunk Road T2, Southeast Kowloon", paralleling the Kwun Tong Bypass, will be built within the development area, allowing traffic to go directly to Tseung Kwan O through the Tseung Kwan O - Lam Tin Tunnel.
However, on 27 February 2003, the non-government organisation Society for Protection of the Harbour applied for Judicial Review against the Town Planning Board. The Society believed that the Wan Chai Development Phase II would violate the Protection of the Harbour Ordinance. The High Court's final judgement is against the Town Planning Board. The reclamation plan was suspended. The High Court's judgement raised three tests had to be satisfied for reclamation:
  1. there had to be a compelling, overriding and present public need which clearly outweighed the public need to protect the harbour;
  2. there had to be no other alternative to implement the undertaking for which it was proposed, and
  3. that any invasion of the harbour should be restricted to the minimum impairment necessary to implement the undertaking.
This judgement affected the reclamation plan within Kai Tak Development. In order to satisfy the three tests, the new Harbour-front Enhancement Committee was established for consultation on the reclamation in Wan Chai and Kai Tak. The committee, led by chairman Lee Chack-fan, was organised by six government officials and twenty-three members from different professional organisations, environmental organisations, harbour protection organisations and business merchants.

Kai Tak Planning Review (July 2004-2006) ()

Due to the High Court judgement, the Planning Department began the Kai Tak Planning Review with "No reclamation" as its principle. This was the final plan.

Proposed development timeline

The first stage infrastructure projects are expected to completed by 2013. These are the first stage projects:
The second stage infrastructure projects are expected to completed after 2016. These are the second stage projects:
The final stage infrastructure projects are expected to completed after 2021. These are the final stage projects:

MTR Tuen Ma Line

The Tuen Ma Line involves construction of two stations within the KTD: Kai Tak Station and Sung Wong Toi Station.

Environmentally Friendly Linkage System

The Environmentally Friendly Linkage System is a monorail transportation system with 12 stations proposed by the government. It will cost around 1.2 billion Hong Kong dollars. The estimated passenger count in up to 200,000 in 2031. The system will account for 15 percent of the public transportation in the Kowloon East Development. The EFLS project is now headed by the Development Bureau with public consultation carried out by the Civil Engineering and Development Department. Construction is predicted to start in 2018 and to be completed in 2023.
There is opposition to the monorail system and other proposing a tram system as a more feasible alternative.

Highway and roads

Hong Kong's Route 6 is proposed to cross the KTD area, using the Central Kowloon Route, Trunk Road T2 and Tseung Kwan O - Lam Tin Tunnel. It will connect West Kowloon, Kowloon East and Tseung Kwan O.