Euroduplex


The Alstom Avelia Euroduplex, more commonly known as just Euroduplex, is a high-speed double decker electric multiple unit train manufactured by Alstom. It is primarily operated by the French national railway company SNCF, and also in operation with the Moroccan national railway company ONCF. It is the 3rd generation of the TGV Duplex.
The Euroduplex trains are interoperable, containing equipment allowing them to travel between several European continental countries with various types of electrification and signalling systems such as France, Germany, Switzerland, Spain and Luxembourg. A Moroccan variation is the first high speed train to operate in Africa.

Description

The Euroduplex trains are an evolution of the TGV Duplex Dasye and still share the main features. The drive is of type SNCF TGV POS asynchronous traction motors, European signaling system European Rail Traffic Management System. The trailers feature improved information systems and the 3UFC type feature new interiors with rotating seats and USB sockets.
The main differences with the TGV Duplex Dasye:
The 3UFC type have new interiors that include:
Riding on the success of the concept TGV Duplex, and praised by customers, the company decided to develop a fleet of interoperable trains, especially suitable for 15 kV 16 ⅔ Hz, the train is a tricurrent version of TGV Duplex.
The Euroduplex has entered commercial operation by the French national railway company on.
In parallel with the development of high-speed lines internationally, Alstom SA won a tender for the supply of equipment for high-speed TGV Morocco, the first high-speed train on the African continent.

Operators

SNCF

In June 2007, in addition to 25 extra TGV Dasye sets, the SNCF has placed a large order for 55 Alstom tricurrent high speed trains, TGV 2N2.
These 55 trains can be divided into:
In April 2010, the first train RGV, numbered 4701, was tested at La Rochelle. On 16 June 2010, the train arrived at the site of ELWT Conflans to be equipped with different systems to perform many tests in the coming months before commercial operation. Between 20 and 30 July 2010, the train conducted speed tests in Switzerland, Germany, the Netherlands, Belgium and the French Alps.
SNCF and Alstom organized the symbolic delivery of the first train on May 30, 2011 on the LGV Est.
The 2007 contract included an option for 40 additional trains. SNCF exercised this option to take delivery of the second batch of Euroduplex sets from 2015. These the 3UFC type and named "l'Océane" were delivered between 2016 and 2019 and have replaced some sets on TGV Atlantique with the opening of the LGV Sud Europe Atlantique. They offer a new inerior design and a improved capacity by 10% due to the third car being multi-class and were delivered between 2016 and 2019 and are numbered from 851 to 891.
To save the jobs of the Alstom factory of Belfort, the french state announced in October 2016 a order of fifteen trains to be used on the Intercity line between Bordeaux and Marseille. That order was done by the SNCF in February 2017. These trains are from the 3UFC type numbered from 836 to 850 and are in delivery starting form August 2019 and are used with the others 3UFC.
Finally in July 2019, the SNCF announced the order of twelve trains that will be delivered between 2021 and 2022. The complete fleet would have 122 trains once the final order would be done.

ONCF

In December 2010, the Moroccan company ONCF ordered 14 sets of the Euroduplex for Kenitra–Tangier high-speed rail line. The contract of €400 million expected commissioning in 2015. The trains are electrified at 25 kV and 3 kV and can operate at up to on the section TangiersKenitra and between on the Moroccan conventional network.
The Moroccan trainsets have a total capacity of 533 passengers in two first class carriages, five second class carriages, and a catering coach, instead of the French configuration of three first class coaches, four second class coaches, and a catering coach.
The first two cars will be delivered during the summer of 2015, transported from the port of La Rochelle by the ship Ville de Bordeaux. The project being more than two years late on its initial schedule, Alstom Transport incurs additional costs, in particular through the forced storage of several trains in its factories. The first dynamic tests of a train began in January 2016, on the classic line connecting Tangier to Casablanca, with drivers who were specially trained ; these tests were completed in July 2016. At the same time, the twelve trains were delivered1. LGV testing began in February 2017 and was completed in June 2018; during one of them, carried out on May 4, 2018, the train rode at 357 km/h.
The maintenance center, with a total capacity of 30 trains and an area of 14 hectares, is located in Tangier-Moghogha.

Usage

SNCF

Since its introduction into commercial service, the 4700 numbered trains operate priority international services:
The trains are used on domestic routes.
The 800 numbered trains are designed to provide international services to Spain:
The 3UFC are all operating from Paris Montparnasse firstly towards Bordeaux — AgenMontaubanToulouseArcachon — Dax — BayonneBiarritzSaint-Jean-de-Luz — Saint-Jean-de-Luz — PauLourdesTarbes. Then towards Le MansRennesQuimperBrestAngersNantesSaint-NazaireLe CroisicLes Sables-d'Olonne

ONCF

Since November 26 2018, the Moroccan trains make the connections between Tanger and Casablanca via Rabat. The name of the commercial service is Al Boraq.
It is operated in partnership with SNCF, within the framework of the joint venture "Moroccan high-speed train maintenance company".

Gallery