Crossrail 2


Crossrail 2 is a proposed rail route in South East England, running from nine stations in Surrey to three in Hertfordshire, providing a new North–South rail link across London. It would connect the South Western Main Line to the West Anglia Main Line, via Victoria and. It is intended to alleviate severe overcrowding that would otherwise occur on commuter rail routes into Central London by the 2030s. Should permission be granted, construction is expected to start around 2023, with the new line opening from the early 2030s. The project's cost has been estimated at £31.2 billion. Boris Johnson, when Mayor of London, called for the line to be called the "Churchill line", after Winston Churchill.
The line is the fourth major rail project in the capital since 2000. National Rail's projections of overcrowding, including in suburbs and tourist destinations less well-served by the Underground, led it to call for more new lines and cross-London line proposals have gained more importance with Euston being named as the terminus of the planned High Speed 2 rail line.
The project was earlier known as the Chelsea–Hackney line in reference to a potential route. The plan for a line on this alignment has existed in various forms since 1970, initially as an Underground service and later as a standard railway.

Current plans

This route is from the 2015 public consultation.

Core section

Operating in new tunnels at 30 trains per hour :
Also in new tunnels, connected to a junction north of Dalston, at 10 and 15 trains per hour:
Running at between 10 and 15 trains per hour on new rails above ground, connected to a junction north of Dalston:
all stations to for Crossrail 2 services and .

Potential eastern extension

The 2015 consultation earmarks a "potential future Eastern Branch"
Above ground, after surfacing south of Wimbledon station, using the existing SWML slow line, and providing between 4 and 20 trains per hour, the southern section comprises:

2013 consultation

In May 2013, TfL began public consultation on two potential options:
The results of the consultation were published on 29 November 2013 by TfL and revealed broad support for the Crossrail 2 plans. 96% of respondents supported or strongly supported the plans, whilst 2% opposed or strongly opposed them. The regional route had greater support than the metro route, with 84% of respondents supporting or strongly supporting the regional route versus 73% for the metro plans.
The greatest level of opposition to the principle of Crossrail 2 came from the residents of Kensington and Chelsea, the only area with more than 5% of respondents who strongly opposed the scheme. Nearly 20% of respondents from this area either opposed or strongly opposed the scheme; the corresponding percentages in all other areas did not exceed 10%.

2014 consultation

In June 2014, a consultation began on small modifications to the 2013 proposals. The changes proposed fell broadly into three areas: extending the Alexandra Palace branch to New Southgate; relocation or removal of the Chelsea station; and moving the point at which the two northern branches diverged to beyond either Dalston Junction or Hackney Downs station, calling at only one of these two stations.

2015 consultation

A further consultation began in October 2015. In October 2015, the route proposal was changed in three ways:
In January 2015, Surrey County Council published a detailed report lobbying for TfL to consider extending branches to Dorking and Woking.

Cost and funding

The cost of the scheme has been estimated at £27–32 billion, in 2014 prices including the cost of new trains and Network Rail works. However Transport for London argued the full cost of the project could be £45 billion in 2017. To ease the funding issues TfL recommended spreading the funding over a longer period and completing the project by the 2040s, ten years after the initial projection.
In the 2016 Budget, the Treasury gave the "green light" for the project, and allocated £80 million towards developing the project, with the aim of bringing forward a Hybrid Bill "this Parliament", meaning before 2020.
In the 2017 Autumn Budget, the Treasury said only that it will "continue to work with Transport for London on developing fair and affordable plans for Crossrail 2, including through an independent review of funding and financing". On 2 March 2018, the UK's Transport Secretary, who represents a seat centred on a prospective terminus of one of the branch lines, announced Mike Gerrard would lead the Treasury's required Independent Affordability Review, which is expected to conclude in the summer of 2018.
The Mayor of London intends to charge Mayoral Community Infrastructure Levy in the same manner as for the original Crossrail project.

History

A south-west/north-east tube line was originally planned as early as 1901 and a Bill was put before Parliament in 1904. However, political manoeuvring by rival tube magnate Charles Yerkes ended the proposal.

1970s

A south-west to north-east tube line was proposed in 1970 by the London Transport Board's London Rail Study as the next project after the completion of the Victoria line and the Fleet line. Designed to relieve pressure on the District, Central and Victoria lines and to link two areas without tube services, the route would have taken over the branch of the District as far as, then followed a new underground alignment via ; thence to, and continuing over one of the branches of the Central line. For financial reasons the line was not built, but the idea has remained.

1980s

Following the Central London Rail Study of 1989, a route through central London was safeguarded. As the route would serve both King's Cross and King's Road it was suggested that it could be named Kings line. It was decided, however, that the Jubilee line extension should take priority and the project was postponed.

1990s

In 1995, an alternative Express Metro plan was put forward that would utilise more existing track, have fewer stations and be built to National Rail standards. It would take one of three routes from on the District line to ; either, and or King's Road as in the original safeguarded plan; or to and and then via Chelsea Harbour and King's Road or via Battersea. From Hackney Central it would split into two branches, to and then on to taking over the Central line; and taking over the North London Line to, a route now followed by the Docklands Light Railway.
The 1991 safeguarding also included a spur south of Victoria across the river to Battersea Park, for stabling trains and to access a riverside tunnelling site.

2000s

The London East West Study in 2000 considered Crossrail, the Chelsea–Hackney line and a combination of the two, from to and then to. The Study supposes main-line gauge, and would omit a station at. Its version of the Chelsea-Hackney Regional Metro splits in the north, with one branch via Dalston taking over the branch of the Central line, the other to, then using the disused alignment of the Northern Heights plan, taking over the branch of the Northern line. The Express Metro option would run on the East Coast Main Line.
Crossrail was given the go-ahead in 2007 in preference to the Chelsea–Hackney line, despite some commentators favouring the latter putting implementation after Crossrail's completion date of 2018. The Chelsea–Hackney plans were taken over by Crossrail as Crossrail 2.
In 2007, the 1991 route was updated – Sloane Square was dropped and the Central line's Epping branch from Leytonstone was re-safeguarded. Due to objections from residents of Sloane Square, it was reinstated the following year. South West Trains' Wimbledon depot was safeguarded as a depot for the line. The safeguarding was enlarged from tube gauge to Network Rail loading gauge as it became clear that larger and longer trains would be needed. Of the three routes proposed for south-west London the Royal Borough of Kensington and Chelsea initially favoured one going south via Imperial Wharf to Clapham Junction, but now supports the takeover of the District line's Wimbledon branch. Under these present plans, only one entirely new station would be constructed, at Chelsea.

2010s

2008 safeguarded route

A route for the line was safeguarded in 2008. It linked the District line's Wimbledon branch with the Central line's Epping branch via,,,,,,,,,,, and. The safeguarding also includes a spur from Victoria under the Thames to Battersea Park for stabling and access to a tunnelling site. The safeguarded route was reviewed by the Department for Transport in 2013.

Northern and southern destinations

Network Rail's July 2011 route utilisation strategy for London and the South East supports the existing safeguarded route but speculates about possible modifications in addition to re-routing via Euston. To the south, it suggests that the tunnels should go from Victoria via Clapham Junction to beyond Wimbledon, instead of surfacing near Parsons Green and taking over the District line from there to Wimbledon. To the north, it suggests that the West Anglia corridor would be a better destination than a branch of the Central line. These suggestions are driven by what the RUS sees as the need for extra capacity on the South Western Main Line and the West Anglia corridor.
With the planned terminus of HS2 at, Chelsea–Hackney was put back to the top of the agenda for new lines, diverted via Euston.
The London and South East second generation RUS by Network Rail proposed some changes to the safeguarded route: serving rather than the branch of the District line, not serving, and serving as well as. The RUS was also open to changes north of and branches south of Clapham Junction, both of which were seen as later phases.
TfL responded by releasing its preferred options - an automatic metro and a regional scheme:
In July 2015, Surrey County Council commissioned a study to propose in detail and with cost-benefits analysed proposals, services from Surbiton as far as the main line stop of Woking. Options explored were the re-routing trains so as not to terminate at Waterloo and creative timetabling plans to add capacity to the South Western main line such as the option of moving trains onto the lighter-used New Guildford Line which runs between Surbiton and Guildford, looking at more semi-fast stopping patterns enabled as well once the Waterloo bottleneck is lifted.
Both TfL routes at both ends of the route serve Clapham Junction to a higher level than relieving the District line, and the Victoria line at its northern end, and the Central line. The regional option relieves the South Western Main Line, and congested sections of the Northern line and Piccadilly line, by creating alternative routes for journeys from outside Zones 1 and 2.
In February 2013, business group London First's Crossrail taskforce, chaired by former Secretary of State for Transport Andrew Adonis published its recommendations for Crossrail 2, favouring the regional option. Later the same day, Network Rail endorsed the plans.
On 5 February 2015 Dr Michèle Dix was appointed managing director of Crossrail 2.
In March 2016, the National Infrastructure Commission said that Crossrail 2 should be taken forward "as a priority" and recommended that a bill should pass through Parliament by 2019 with the line opening by 2033.

Support and opposition

Support

, Mayor of London in 2013, said at that time: "The key question now is not whether Crossrail 2 should happen, but how quickly we can get it built".
The current Mayor of London, Sadiq Khan, also supports the proposal, as does the former Secretary of State for Transport Chris Grayling.
Many local authorities in South-east England and London released a letter on 13 April 2017, expressing their support for Crossrail 2. ITV news reported in April 2017 that "dozens of MPs" supported Crossrail 2.
After TfL conducted a public consultation in 2017, it was reported by the Fitzrovia Partnership that 96% of respondents supported Crossrail 2 and 80% of respondents preferred the broader of the two options, the Regional option.
The London Chamber of Commerce announced it support in July 2017 with the Greater Manchester Chamber of Commerce announced support for Crossrail 2 in September 2017.

Opposition

In 2014, Transport for London announced that the site of the art-house Curzon cinema in Soho had been identified as an area that "may be required to enable the construction of a Crossrail 2 ticket hall" and that "plans for the above site redevelopment may include a replacement cinema". In 2015, the chairman of the "Save Soho" campaign group called the development "deeply worrying".
The plans for Wimbledon station involve the redevelopment of parts of Wimbledon town centre, including the Centre Court shopping centre. Merton Council issued a seven-page cross-party objection to the plans.
There was only a short interval between the announcements of the confirmation of continued government support for Crossrail 2 in 2017, and of the scaling back of proposed railway electrification projects which would particularly benefit Wales and Northern England. Money has been earmarked in the longer term to match London's large forecast population growth. All such forecasts rely on assumptions in terms of where people will wish to live, jobs will be created and housing targets have been set accordingly for 2015–2030, in contrast to the low growth forecast for the rest of England, all of which could be altered by government policy. Greater Manchester mayor Andy Burnham considered that the in-principle spending decision gives undue and unbalanced priority to London and South East England over other parts of the United Kingdom.