Yamdrok Hydropower Station


The Yamdrok Hydropower Station, also known as the Yamdrok Yumtso or Yamzhog Yumcog hydropower station, is a hydroelectric power station just north of Yamdrok Lake, about southwest of Qüxü.
The power station is in the Lhoka Prefecture of the Tibet Autonomous Region, China. Opposition to using the lake, considered holy, delayed construction at first. The project ran into difficulties and was two years late, completed in 1998.
Water is taken from the natural lake through long tunnels, without the need for a dam, and the power station discharges it into the Yarlung Tsangpo River. The design is a pumped-storage system, where off-peak power from other generators on the grid is used to pump water back into the lake when power is not needed. However, the river water has high levels of sediment and nitrates compared to the lake, and lower levels of minerals. Pumping may upset the lake's ecosystem, while not pumping may drain it.

Plans

Yamdrok Tso is the largest freshwater lake in southern Tibet, with a surface area of at an elevation of.
It drains an area of.
Some Tibetans consider that the Yamdrok Yumtso or Scorpion Lake, is holy and contains the spirit of Tibet.
The Panchen Lama criticized the project.
It was started in 1985, but due to vocal opposition from Tibetans and the intervention of the Panchen Lama the project was halted in 1986.

Construction

The project was relaunched after the Panchen Lama died in 1989.
In response to the Panchen Lama's concern about the environmental impact of draining the lake, the power station was planned as a pumped storage power station. It would discharge water into the river at peak hours, and pump water from the river up to the lake in off-peak hours, so there would be no overall loss of water volume in the lake.
Rather than build a dam, four tunnels were bored through the sides of the lake to carry water down to the power station.
Four turbines were supplied by J.M. Voith AG of Germany, as well as pumps and steering systems.
An Austrian company provided on-site engineers.
In 1991 between 4,000 and 5,000 members of the People's Armed Police began construction.
In 1993 freshwater wells near the lake began to dry up.
In June 1996 it was reported that the project had run into severe problems.
When Vice Premier Wu Bangguo came to a ceremony where he would turn on the first turbine, the plant was not ready and electricity had to be brought in from Yangpachen thermal power plant. Inquiries revealed that the tunnels that brought water from the lake to the turbines were leaking badly and could not be used. It was said that the earth had collapsed in one tunnel and the lake had already dropped by. Fang Changquan, commander of the People's Armed Police construction brigade, was dismissed.
The deputy commander of the construction brigade was given responsibility for the next project, building the Zhikong Hydro Power Station on the Lhasa River.
Trial operations began in 1997, and Xinhua reported that it was fully operational in September 1998.
Jiang Zemin was present at the official opening ceremony on 18 September 1998.
There was not enough power available for pumping, so it was used only for power generation, discharging the lake water into the river.
The station displaced the Yangbajain Geothermal Field as the main power supply for Lhasa when it came into operation.
The investment had cost almost 2 billion yuan.

Description

The station has a pumping channel long with a vertical drop of.
It initially had four 22.5 MW reversible Francis turbine-generators, which delivered a total 90 MW of electricity and can reverse to pump water back into the lake.
During the tenth five-year plan period a conventional 22.5 MW generator set was put into operation, bringing total installed capacity to 112.5 MW.
Annual generating capacity is 0.8409 billion kwh.
Each turbine uses two cubic meters of water per second.
Water from the power stations passes through a settling basin with effective depth of storing about, and in the reverse mode water is pumped from the settling basin to the lake.

Environmental concern

The Yamdrok Tso lake is a resting place for many migratory birds.
It is almost a closed system, fed by rain and melting snow from the surrounding mountains, and drained only by a small tributary of the Yarlung Tsangpo.
The inflow of water to the lake from the shores is balanced by evaporation, leaving high levels of dissolved minerals that give the lake a deep turquoise blue color.
The lake is also low in nitrates and sediment compared to the river, so pumping river water into the lake would affect the water quality and could cause environmental problems.
Without pumping, the lake level will drop steadily.
Indian hydroelectrical experts have expressed skepticism about the stated plan to pump water into the lake when power demand is low.
They note that the energy needed to pump water up to the lake will be much greater than the energy produced when water falls down from the lake, and power would also be lost in transmission from Lhasa and beyond to the pumps, so replenishment of the lake would be uneconomical.
The saline lake water may also affect the quality of river water downstream from the tailrace outlet.