West Thurrock Power Station


West Thurrock Power Station was a coal-fired power station on the River Thames at Stone Ness, West Thurrock in Essex. The station was at the northern end of the 400 kV Thames Crossing of the National Grid.

History

The station was built by the Central Electricity Generating Board and, unlike most of the power stations further up the Thames, West Thurrock was built on a 37 hectare green field site, 1.5 miles west of Grays. Construction, which included the piling and landfilling of the marshy riverside, took several years, starting in 1957 and continuing until 1965 – although the first generator was commissioned in 1962. It was the first CEGB station designed to exceed 1000 MW, having a final output of 1300 MW. West Thurrock was one of the CEGB's twenty steam power stations with the highest thermal efficiency; in 1963–4 the thermal efficiency was 35.54 per cent, 35.78 per cent in 1964–5, and 35.70 per cent in 1965–6.
The architectural design was by Farmer and Dark.The station had two 200 MW units and three of 300 MW units housed in a reinforced concrete turbine hall. The roof was of multiple transverse barrel vaults. The five boilers were built by Babcock & Wilcox and were unusual being open to the elements and were originally designed to burn pulverised coal. They were adapted to burn natural gas between 1971 and 1980, and heavy fuel oil burning facilities were added in 1985. The total steam capacity of boilers was 8,445,000 lb/hr. Steam pressure and temperature at turbine stop valve was 2350 psi at 566 °C. Ash from the boilers was sold to a local factory and used to make building blocks. The station had two tall chimneys made from reinforced concrete.
After the UK's electric supply industry was privatised in 1989, West Thurrock was operated by National Power. In 1992, one of the station's units were decommissioned. The station's other four units were decommissioned in 1993. The closure left a stockpile of nearly half a million tonnes of coal, which was transported downstream to the nearby Tilbury Power Station by Rhine barge.
After demolition part of the site was redeveloped as a works making industrial chemicals for the adjacent Procter & Gamble works and using the former coaling jetty. A proposal to build a large postal sorting office on the former fly-ash lagoons proved controversial due to the wildlife that had colonised the site.
An unusual feature of the site is the northern end of the pair of 192-metre tall pylons supporting the 400 kV link across the river Thames.

Electricity output

Electricity output for West Thurrock power station over the period 1964–1987 was as follows:
West Thurrock annual electricity output GWh.