Wairau Hydro Scheme


The Wairau Hydro Scheme is a canal based hydroelectric project proposed by TrustPower on the Wairau River in Marlborough, New Zealand. The $280 million project would divert up to 60% of the river through of canals to generate up to of electricity.

Resource consents