Construction of the first two units started in 1959. The first 32 MW unit was commissioned in 1963 and the last 215 MW unit was commissioned in 1978. There is a plan to build a new 450 MW unit by the Gezhouba Group.
Description
The power station has an installed electric capacity of 715 MW and it produces around 3.1 TWh of electricity per year. In addition, it supplies heat for Tuzla and Lukavac. The plant burns 330,000 tons of coal annually. Units 1-6 are supplied from the Kreka and Banovići mines. Unit 7, at the moment, is not built. Unit 4 has a flue gas stack, Unit 6 a flue gas stack.
Background
For several years a new 450 MW unit has been planned at the Tuzla coal power plant in Bosnia and Herzegovina, owned and operated by the state-owned Elektroprivreda Bosne i Hercegovine. Although it is usually cited as a replacement for existing units, Elektroprivreda BiH plans to close only the existing units 3 and 4 in 2018 and 2021 respectively, while units 5 and 6 will continue to operate until after 2030. Thus Tuzla 7 would result in additional coal capacity compared to the current situation.
Financing
An Engineering, procurement, and construction contract worth EUR 785 million was signed with China Gezhouba Group Co. on 30 August 2014, but it was later admitted that the plant would not be economically feasible. In May 2016 an annex to the contract was signed, which brought the cost down to EUR 722 million. In December 2014 a Memorandum of Understanding on financing the facility was signed with the Exim Bank of China, and in November 2016 a framework agreement on financing was signed. On 27 November 2017, The China Exim bank and Bosnian power utility Elektroprivreda BIH signed a 613 million euro loan agreement for the Tuzla 7 lignite power plant.
The environmental permit for Tuzla 7 is incomplete as it does not cover the foreseen ash landfill on the Šićki Brod site. According to Article 71 of the Federation of Bosnia and Herzegovina's Law on Environmental Protection, an environmental permit must include measures for managing waste produced by the facility in question. In addition, using the Šićki Brod site as an ash landfill would contravene the Tuzla Canton and Lukavac and Tuzla municipality spatial plans, and is opposed by the Lukavac municipality council and the population living in the local communities surrounding the location. In April 2016 they presented a petition with 2100 signatures against the site to the Ministry of Environment and Tourism. The government has still no answer to all the protesters in 2019. The ash landfill if it ever gets build would destroy an whole eco system. With the ash reaching deep down to natural water springs which many local people use to drink and use, the whole area would depend on nondrinkable tap water. The ash would also directly pollute more than 150k people just around Lukavac and Tuzla. The nearby places like Plane,Bistarac,Bukinje,Brgule and Lukavac already have a problem with pollution, with the ash landfill built the area would suffer even more. And that would be hazardous for all the people living there. Drinkable water would be polluted and so as the very good land which many farmers use to grow food.
Scarce water resources
The Tuzla power plant takes cooling water from the Modrac Reservoir, the same source as much of the drinking water for Tuzla. This reservoir is fed mainly by the Turija River and the Spreča River; it already suffers from pollution caused by coal production and separation. If the Banovici coal power plant is built – another project just a few kilometers away from Tuzla—it will directly compete with the Modrac Lake for water in drier periods.
Health impacts
In November 2013, the Center for Ecology and Energy from Tuzla launched a report on the health impacts of existing and planned coal thermal power plants in the Tuzla area. Using the methods developed in the World Health Organization's Health Response to Air Pollutants in Europe project, the study found that in 2013 in Tuzla existing power plants will have caused the loss of 4900 years of life, 131,000 lost working days and more than 170 hospitalizations due to cardiac and respiratory diseases. Although the Tuzla coal plant is the largest source of pollution in the area, it should be taken into account that this situation is aggravated further by the cumulative impacts with other pollution sources such as the Coke plant and soda factory in Lukavac, thus increasing the health risks even further. Average life expectany has shortened to 51yo in places nearby.
Local protests
The air quality in Tuzla is notorious, ranked second by the World Health Organisation among Europe's most polluted towns in 2017. The legal limits for pollutants PM2.5 and SO2 were breached in the long winter of 2017-2018; the Clean Air Movement—a group of citizens living in Tuzla concerned about the worsening health condition as a result of air pollution exposure—took to the streets to demand that authorities find long-term solutions to this ever-present problem. The authorities however have still no answer to all the protesters. The air pollution reached its peek in 2018 and beginning of 2019 with Air Quality Index reaching more than 500 which is by all the standards hazardous for all the people.