Town Hall railway station is a railway station currently under construction as part of the Metro Tunnel project. It is being built below Swanston Street between Flinders and Collins Streets.

Design

Initially it was planned to build the station using the cut-and-cover method, however this was changed so that the tunnels would run deeper underneath the ground in order to not disturb services, utilities and businesses on Swanston Street. Construction commenced in 2018 with the station expected to open in 2025.
The station is planned to have direct underground access to nearby Flinders Street Station through the already existing Campbell Arcade connection.

Town Hall Station Precinct

As part of the construction of Town Hall Station, the city Square precinct is set to be rebuilt as a public gatherings and events space.
There will be 70 new bike parking spaces built to cope with increasing demand, as well as improved tram interchanges on Flinders, Collins, and Swanston streets.

See Also

Metro Tunnel Project