Sukhumvit line


The Sukhumvit line or Light Green line, is an elevated metro rail line of the BTS Skytrain in Bangkok, Thailand. From the central Siam Station, where it connects with the Silom Line, the line runs both northwards along Phaya Thai and Phahon Yothin Roads to Wat Phra Sri Mahathat in Bang Khen District, and eastwards along Rama I, Phloen Chit and Sukhumvit Roads, through Bang Na District to Kheha Station in Samut Prakan. BTS daily ridership is 740,000 passengers per day.

History

The first part of the line opened in December 1999 and consisted of seventeen stations from Mo Chit to On Nut. Currently, there are 40 stations in operation. Its formal name is The Elevated Train in Commemoration of HM the King's 6th Cycle Birthday First line .

Stations

A planned station at N6 has never been built.

Extensions and current construction

East

1st extension, in operation - Construction started in August 2006 on a four billion baht, 5.25 km extension from On Nut to Bearing. The extension was funded by the BMA. The original scheduled opening date was mid-2009. However, a delay in tendering of the contract for the electrical and signalling works resulted in a two-year delay.
The extension did not open until over two years later, on 12 August 2011. The delay in opening prompted the BMA to offer free travel for this extension until the end of 2011 as compensation. An additional flat fee is charged additionally to the distance-based fare of the rest of the BTS network.
2nd extension, in operation - Construction started in April 2012 on a 12.6 km, nine station extension from Bearing station to Kheha station. The extension was funded by the MRTA as it is outside BMA city limits, Bangkok Province. Construction was contracted to take 1,350 days and the extension was originally scheduled to open by early 2017. In April 2013, the MRTA awarded Ch Karnchang the contract for track laying and electrical systems.
As of June 2014, civil works were stated to be 28.3 percent complete. In August 2016 the BMA agreed to take over the operation of the extension from MRTA. Delays over the agreement of how much the BMA should pay MRTA caused a delay in the commencement of test runs on the extension. Track works were 98% completed by November 2016. The total cost of the extension was estimated at 21.4 billion baht. In January 2017, it was announced that the opening of the extension could be further delayed to 2018-2019 due to budgetary concerns and ongoing disputes between the MRTA and BMA.
The first 1.2 km section of the extension to Samrong station opened in April 2017. The full extension to Kheha opened on December 6, 2018.

North

1st and 2nd extension, currently under construction
An 11.4 km, 11 station northern extension from Mo Chit station to Saphan Mai in Don Mueang District has been planned since the Sukhumvit line opened. Originally, this extension was scheduled to be completed by 2008. However, due to a combination of changes in government, a prolonged environmental study, and problems with locating a suitable train depot the extension has been continually delayed. A further 16.5 km, nine station extension from Saphan Mai to Lam Lukka was also planned once the extension to Saphan Mai had been completed.
After multiple delays, in mid-2013 a decision was made to tender extension and at the same time, by the end of 2013. However, the dissolution of parliament in November 2013 delayed this yet again. A tender was finally released in January 2014 with an April deadline before being delayed until late May 2014 due to concerns from bidders. A military coup in late-May 2014 suspended the bidding process whilst the military administration reviewed all major projects. In late June, the military administration affirmed the tender will proceed before the end of 2014. In August 2014, the MRTA announced that the new tender deadline will be 30 September 2014. Five bidders qualified and the successful bids were announced in December 2014. The tender specifies a construction period of 1,350 days.
On 3 April 2015, MRTA signed four contracts for this extension:
The MRTA, contactors and Thai Traffic Police met on 2 September 2015 and confirmed construction would begin on 8 September 2015. A flyover at Kasetsart was demolished, which commenced on 12 September 2015.
As of 31 December 2017, the progress of civil works construction was at 53.31% according to the MRTA. As of the end of April 2018, the MRTA stated that civil works progress had advanced to 63.27%. As of 30 September, overall construction had progressed to 78.79%. By the end of March 2019, civil construction had nearly been completed having progressed to 99.42%
Opening dates
1) The first section to Ha Yaek Lat Phrao station opened on 9 August 2019.
2) The next 4 stations from a Yaek Lat Phrao station to Kasetsart University opened on 4 December 2019.
3) The next 4 stations from Kasetsart University to Wat Phra Sri Mahathat opened on 5 June 2020.
4) The next 3 stations from Wat Phra Sri Mahathat to Saphan Mai will open in October 2020.
5) The remaining stations to Khu Khot will open in December 2020.

Future extension plans

East:
North: