Steven Tanger Center for the Performing Arts


Steven Tanger Center for the Performing Arts in downtown Greensboro, North Carolina is an $85 million 3,000-seat performing arts facility, with an opening date yet to be determined. It will replace 2,400-seat War Memorial Auditorium in the Greensboro Coliseum Complex; the auditorium was torn down in October 2014. The Community Foundation of Greater Greensboro raised $35 million privately, to be paid over ten years. The city of Greensboro is paying $30 million. Construction was delayed a year so the foundation could get a $25 million bank loan to guarantee its contribution. The Greensboro Symphony and Guilford College's Bryan Series are expected to use the facility. The facility will also host Broadway productions and concerts. The facility is named for Steven Tanger, CEO of Tanger Factory Outlet Centers, who pledged $7.5 million toward the project in 2013. After working for a year, a task force recommended a state of the art center in February 2013. Groundbreaking was held April 26, 2017 and the first work took place July 13.

History

In 2000, Greensboro arts groups wanted a new performance facility or changes to existing facilities which were inadequate. War Memorial Auditorium, with 2,400 seats, was too large for some events but had a small stage and orchestra pit as well as poor acoustics; Coliseum Managing Director Matt Brown had plans for $5 million in improvements but no funding. The Carolina Theatre downtown had only 1,100 seats. A preliminary study recommended a performing arts center with 1,700 to 2,000 seats, and a smaller 500-seat facility. The study also said the city had enough events for both existing and new facilities. Arts leaders wanted a more detailed study.
A 2001 downtown master plan estimated the cost of a new performing arts center at between $35 and $45 million. A feasibility study was done in 2004.
2006 and 2008 bond referendums to renovate were unsuccessful. In 2008, Brown said events were being lost to the Durham Performing Arts Center and that Greensboro was entitled to a facility of equal quality. Until that happened, the auditorium could be repaired as needed, but that would not be enough.
In January 2012, Brown asked the city council to consider a $36 million performing arts center to replace the auditorium, paid for with $25 million in bonds and $11 million in accommodations tax revenues. A Greensboro Performing Arts Center Task Force began meeting in February. At their first meeting, Interim City Manager Denise Turner Roth said a downtown location, which the city council wanted, would cost up to $15 million more, with $10 million of that amount coming from donations.
In June 2012, the task force recommended a 3000-seat $60 million facility downtown.
In 2013, Greensboro attorney Kathy Manning agreed to serve as chair to seek private funds for the performing arts center.
Originally, the city-owned former YMCA site was to be used but it was not enough. Land was purchased at North Elm and Lindsay Streets and Summit Avenue at a cost of $11.5 million.
During the closing ceremony for War Memorial Auditorium on September 4, 2014, Brown showed what the planned veterans' memorial would look like. Names of veterans shown on plaques at the auditorium would eventually go in the new memorial near the Tanger Center.
Because the Tanger Center is expected to lose money in its early years, a new premium parking lot at the Coliseum Complex will be used to help with operating expenses. Expected revenue from the lot is nearly $400,000 a year. A second, 250-space lot at the Tanger Center is expected to provide $675,000 per year.
On July 29, 2015, the city revealed the cost of the center would be $58 million, $8 million over the original estimate, and not including $11.5 million for the land. This was after cuts had been made, and more cuts were expected.
On December 8, 2015, the city council approved a plan to raise $11 million more for the center, after it became clear the original budget was already exceeded by more than $10 million. The Chamber of Commerce building would be replaced by VIP parking expected to provide $1.6 million. Private donors would be asked for $3.5 million more. Ticket service fees would be $1 more, and $1 less of the existing $3 service fee would go to arts groups, with each raising a projected $3.75 million over 25 years. Also, $4.4 million of the costs would be eliminated if possible. The city would also have to authorize $9,617,858 in bonds.
At a January 27, 2016 news conference, H3 Hardy Collaboration Architecture showed designs for the exterior and lobby. The facade will be limestone and glass. The lobby will include art to be paid for by a donation.
On February 17, 2016, Phillips Foundation announced a $1.5 million grant; this is in addition to a $3.5 million grant in May 2013, for which the 8000-square-foot lobby will be named Phillips Hall. Phillips Foundation will also provide art for the lobby.
Brown and others announced on December 16, 2016 that the $38.5 million fund-raising goal had been met and that $300,000 of the additional $3 million had been raised. Construction was expected to start in May 2017 and will be complete in early 2020. The 111,000-square-foot building will face Abe Brenner Place and occupy part of a 5.5-acre lot also bordered by North Elm and East Lindsay Streets and Summit Avenue. The 3000 seats will be white oak with red upholstery, and divided into lower orchestra, upper orchestra and balcony. A Founders Room will be available for events. The site will also have 329 VIP parking spaces.
As of March 8, 2017, the opening date of early 2019 was uncertain. Potential donors had been saying for several months that delays would result in their waiting to give their money.
Steven Tanger and North Carolina Governor Roy Cooper attended the groundbreaking April 26, 2017. At the time, Brown predicted a June 2019 opening.
D.H. Griffin won the bidding for Phase I, which started July 13, 2017.
On December 19, 2017, the Greensboro city council awarded a $57.9 million contract to Barnhill Contracting Company of Raleigh, North Carolina. Work could start in January 2018, but this meant a completion date of January 2020. The project's total cost was $84.7 million, plus $5 million in financing costs. The Tanger Center would be collateral for $48 million in limited obligation bonds.
A web site is now available and includes what is described as a Real Time Camera permitting viewers to watch construction progress.
As of May 2019, completion is expected January 28, 2020 and the total cost is $90 million, $5 million of that related to bond financing.
On March 13, 2020, it was announced that the center's opening would be delayed further due to statewide bans of gatherings consisting of more than 100 people due to the COVID-19 pandemic, effectively postponing multiple opening events.