Purple Line Extension


The Purple Line Extension, formerly known as the Westside Subway Extension and the Subway to the Sea, is a new heavy rail subway corridor in Los Angeles County, California, extending the D Line from its current terminus at in Koreatown, Los Angeles to the Westside region. Currently under construction, the corridor will become part of the Los Angeles Metro Rail system. The project is being supervised by Los Angeles County Metropolitan Transportation Authority. The subway has been given high priority by Metro in its long-range plans, and funding for the project was included in two county sales tax measures, Measure R and Measure M.
The project's draft environmental impact statement was completed in September 2010, and a locally preferred alternative was selected in October 2010. Metro released the Purple Line Extension's final environmental impact report in 2012. The entire project was approved at the Metro Board of Directors meeting on April 26, 2012, and construction has been separated into three phases.
Currently this project's first and second phases are under construction. Combined, these two sections will add nearly of heavy rail service to the City of Los Angeles. Construction on Phase 1, between the existing Wilshire/Western station and the planned Wilshire/La Cienega station, started on November 11, 2014. Phase 2 pre-construction work between Wilshire/La Cienega station and Century City/Constellation station began in April 2017, and the official Phase 2 groundbreaking ceremony took place on February 23, 2018. Phase 3 advanced utility relocation pre-groundbreaking work began in February 2018 for the future Westwood/UCLA and Westwood/VA Hospital stations. No groundbreaking for Phase 3 has been scheduled.
A fourth phase has long been discussed, which would extend the Purple Line from the Westwood/VA Hospital station 3.5 miles under Wilshire Boulevard to Santa Monica beach, terminating at or near the E Line or future Lincoln Boulevard Transit Corridor terminus.

Overview

Currently, the line is planned to run between and Westwood/VA Hospital, with tail tracks that could allow for future expansion further west. The following new subway stations will be built:

Early concepts

Early transit planners recognized the importance of Wilshire Boulevard as a spine and key boulevard in Los Angeles. Early plans for regional Metro Rail envisioned a rapid-transit route between Downtown and the Westside, with a branch going north on Fairfax to Hollywood and into the San Fernando Valley. In 1961, the "New Proposed Backbone Route Plan" described a subway along Wilshire Boulevard from Westwood to Downtown. This project was never funded. Ballot initiatives in 1968 and 1974 to build a subway to West Los Angeles were rejected by voters, but in 1980 voters passed Proposition A, which created a half-cent county sales tax to fund rail construction. Ultimately, the Southern California Rapid Transit District, one of Metro's predecessors, planned a subway that would extend from Downtown Los Angeles to Fairfax Avenue, then north on Fairfax to Hollywood and the Valley. Due to the "methane zone" that plan was modified, and Vermont Avenue was chosen for the north–south route instead of Fairfax.

Prior opposition and halt of Wilshire branch

Several factors led to the eventual halt of plans to extend the subway west along Wilshire Boulevard. For decades, the route was mired in political and socioeconomic debate, with politicians giving vent to anti-subway sentiments and NIMBY isolationism. The City of Beverly Hills also opposed the subway, as did two key legislators from the area: Congressman Henry Waxman and Los Angeles City Councilman Zev Yaroslavsky.
Following a methane explosion in 1985 at a Ross Dress for Less clothing store near Fairfax and Third Street, Congressman Waxman worked to legally designate a large part of Mid-Wilshire as a "methane zone." This zone stretched on either side of Wilshire Boulevard from Hancock Park to west of Fairfax. Waxman was able to pass federal legislation banning all tunneling through this zone. Subsequently, any plans for a subway west of Western Avenue diverted the line south around the methane zone, using Crenshaw, Pico, and San Vicente Boulevards. These plans never came to fruition, and to qualify for federal funding, the SCRTD instead started anew and rerouted the subway north on Vermont Avenue, then traveling west under Hollywood Boulevard and then north toward the Valley. The Red Line was completed in 2000.
The Red Line project began in 1986. Soon after construction began, the project began to draw a considerable amount of bad press. Access to many local businesses was blocked for weeks, causing some small businesses to shut down. Disagreements arose between Metro and Tutor-Saliba over tens of millions of dollars in cost overruns. A sinkhole in Hollywood seemed to symbolize the disastrous nature of the subway project. As a result, in 1998 voters approved a measure sponsored by County Supervisor Yaroslavsky that banned use of Proposition A and Prop C sales tax funds for any subway tunneling in the county. This effectively ended any chance of a Westside Subway in the foreseeable future.
The segment of the Red Line project to was completed and began service in 1996. Wilshire/Western is presently the western terminus of the Purple Line.

New support and approval

In 2000, an urban art group known as Heavy Trash placed signs advertising a fictional "Aqua Line". The signs, with the text "Coming Soon", showed a subway route extending along Wilshire to the ocean, with 10 station stops. Although the campaign was a hoax, it demonstrated newfound support and revealed the frustrations surrounding the lack of a subway connecting Santa Monica and the Westside with Downtown Los Angeles. The name "Aqua Line" was later repurposed as the proposed name for the Expo Line.
During the 2000s, support for the subway began to materialize, largely due to the massive impact of traffic on Wilshire Boulevard and throughout the region. The Metro Rapid bus line that currently operates along Wilshire Blvd. runs at capacity. In 2005, Los Angeles voters elected Antonio Villaraigosa mayor of Los Angeles. In his campaign and after the election, Villaraigosa declared an extension of a subway line to Santa Monica a major priority, offering visionary slogans such as "subway to the sea", "the most utilized subway in the nation, maybe the world," and "the most cost-effective public-transportation project in America." As mayor, Villaraigosa served several one-year-long terms as Metro Board chairman.
In December 2005, Congressman Henry Waxman, who had sponsored the "methane zone" tunneling ban 20 years earlier, championed the reversal of his own legislation, upon a committee's assertion that tunneling through the methane zone was now safe. To make this happen, Waxman introduced new congressional legislation to overturn the ban.
In July 2006, the Metro board approved staff and funding to initiate a Major Investment Study to study the corridor west of Western Avenue for a possible subway extension. In the following month, the Metro Board voted to designate the Wilshire branch of the Red Line, between Union Station and Wilshire/Western Station, as the Purple Line.
With a new name and a new study initiated, the Purple Line extension began to receive public support from several organizations. In 2006, the Westside Cities Council of Governments endorsed the extension. In September 2006, both Cedars-Sinai Medical Center and UCLA joined the Council's Mass Transit Committee to advocate for the subway extension. In 2007, the Beverly Hills City Council endorsed a Wilshire alignment that includes one station at the corner of Wilshire and La Cienega boulevards and another on Wilshire Boulevard between Beverly Drive and Rodeo Drive.
On June 28, 2007, the Metro board approved a $3.6 million contract with Parsons Brinckerhoff to provide an Alternatives Analysis, an assessment of tunnel feasibility, and conceptual engineering with options for future preliminary engineering and environmental clearance for this extension.
Congressmember Henry Waxman's legislation to lift the ban on tunneling through the "methane zone" finally became law in December 2007, as part of the 2008 omnibus spending bill. The passage of this long-awaited legislation allowed, for the first time in two decades, the planning and building of a westward extension of the subway.
In 2009, the Wilshire Subway Extension was included in Metro's Long Range Transportation Plan, and environmental studies were begun.

Environmental review process

Initial alternatives analysis

During the alternatives analysis, many alternatives were considered. These included different alignments, as well as several modes of transit. Most alignments were variations/combinations of two basic alignments: the "Wilshire alignment" and the "West Hollywood alignment".
  • The Wilshire alignment has been suggested as a corridor to the Westside for decades. Wilshire Boulevard has many destinations along its path, including Miracle Mile, Beverly Hills and Century City. The route heads west from primarily along Wilshire Boulevard until it reaches Santa Monica Boulevard. At that point, the route diverts through Century City before returning to Wilshire in Westwood.
  • The West Hollywood alignment was proposed during the public scoping process. The route travels along Santa Monica Boulevard and San Vicente Boulevard, connecting in the north to the Wilshire route in the south. The West Hollywood route generated considerable support from the public, transit advocates, and the City of West Hollywood.
Other alignments studied involved various deviations from Wilshire Boulevard, to allow service to destinations such as Beverly Center, Cedars-Sinai Medical Center and Farmers Market.
The alternatives analysis recommended further study on four alternatives: "No Build", TSM, the Wilshire Alternative, and a combination Wilshire/West Hollywood Alternative. Both build alternatives use heavy rail as its transit mode, primarily because this would allow interconnection to the existing Metro Rail subway system. All proposed alignments involving other transit modes were eliminated.

DEIR alternatives

The five alternatives considered in the Draft Environmental Impact Report are:
DEIR AlternativeDescriptionNew trips
Estimated cost
Alternative 1Wilshire route to UCLA24,142$4.036
Alternative 2Wilshire route to VA27,615$4.358
Alternative 3Wilshire route to Santa Monica35,235$6.116
Alternative 4Wilshire route to VA, plus West Hollywood route31,224$6.985
Alternative 5Wilshire route to Santa Monica, plus West Hollywood route40,123$8.747

Alternatives 3 and 5 are the build alternatives carried over from the alternatives analysis. In addition, three new alternatives were added. These new alternatives are variations of the two AA-recommended alternatives which all stop short of Santa Monica. They were added to reflect the realities of limited available funds, as well as the priorities in Metro's Long Range Transportation Plan.
The following table shows all potential metro stations, and the alternatives for which they apply:
StationAlt 1Alt 2Alt 3Alt 4Alt 5
Wilshire/Crenshaw×-×××
Wilshire/La Brea×××××
Wilshire/Fairfax×××××
Wilshire/La Cienega×××××
Wilshire/Rodeo×××××
Century City×××××
Westwood/UCLA×××××
Westwood/VA××××
Wilshire/Bundy××
Wilshire/26th St××
Wilshire/16th St××
Wilshire/4th St××
Santa Monica/La Brea××
Santa Monica/Fairfax××
Santa Monica/San Vicente××
Beverly Center××

In addition to the five build alternatives, the DEIR identified six sets of options:
NameIssueOptions
Option 1Should a station be built at Wilshire/Crenshaw?
  • Yes
  • No
Option 2Where should the Wilshire/Fairfax station be located?
  • Slightly west of intersection
  • Under intersection
  • Option 3Where should the Wilshire/La Cienega station be located?
  • East of intersection
  • West of intersection
  • Option 4Which route should be used between Wilshire/Rodeo and Century City stations?
  • "Santa Monica Blvd" alignment
  • "Constellation North" alignment
  • "Constellation South" alignment
  • Option 4Where should the Century City station be located?
  • Santa Monica Blvd.
  • Constellation Blvd.
  • Option 4Which route should be used between Century City and Westwood/UCLA stations?
  • "East" alignment
  • "Central" alignment
  • "West" alignment
  • Option 5Where should the Westwood/UCLA station be located?
  • Wilshire/Gayley
  • Wilshire/Westwood
  • Option 6Where should the Westwood/VA Hospital station be located?
  • South of Wilshire
  • North of Wilshire
  • Route Selection: Alternative 2

    In September 2010, Metro published the draft environmental impact statement for the project. The report made no specific recommendation among the five alternatives. However, Metro staff did signal that only Alternatives 1 and 2 would be serious candidates for the Locally Preferred Alternative, since only those two alternatives match the project scope defined in Measure R and Metro's Long Range Transportation Plan.
    In October 2010, Metro staff recommended continuing study on Alternative 2. Staff also recommended:
    In eliminating the West Hollywood Connection Structure, Metro staff eliminated the future possibility of a West Hollywood line as a heavy-rail branch of the Wilshire Subway, as described in Alternatives 4 and 5. Staff cited the $135 million cost, as well as lower than expected performance and cost-effectiveness. Staff left open the possibility of other future alternatives which would not require a connection structure such as light rail, with a possible future extension south of Wilshire on San Vicente Boulevard, connecting to a future extension of the Crenshaw/LAX light-rail line currently being built that would run north of Exposition Boulevard.
    Due to protests from Beverly Hills residents and local officials, the Metro Board approved an amendment requesting detailed study and comparison of the two Century City station options in the FEIR. Metro eventually chose the Century City station location of Constellation Boulevard and Avenue of the Stars intersection, displeasing Beverly Hills and its school district as the route traveled under Beverly Hills High School. They preferred the Santa Monica Boulevard and Avenue of the Stars intersection. Metro argued earthquake faults and abutting a golf course made the location undesirable and would be under-served. After legal battles and court hearings Metro prevailed, proving the DEIR was correct. At the Metro Board meeting in late October 2010, the Metro Board certified the DEIR and accepted the staff recommendation as the Locally Preferred Alternative. A Metro presentation dated October 29, 2013, shows the route to the Westwood Veteran's Administration Medical Center being approved, and the Phase I segment to La Cienega had commenced. This presentation also shows construction methods and timeline for all three phases.

    Project budget and planning

    The project's estimated costs have increased since it was first proposed in the 1950s. Metro proposed Measure R in 2008; estimated costs in 2008 exceeded Metro's funds available so they decided to promote the passage of heavy rail to Westwood and dropped the use of the locally used term "Subway to the Sea". This was done to lower the costs, bring public awareness to help pass measure R and cover central LA and connect Century City to downtown LA. The Expo Line to Santa Monica beach was under construction at the time and Metro didn't want to promote two lines to Santa Monica as they needed countywide support for passage.
    Metro estimated in the late 2000s the full project would cost $4.2 billion. After the passage of the Measure R sales tax in 2008, an additional $4.074 billion was added to its construction funds. In 2016, LA county voters passed Measure M and funds were appropriated to accelerate the project.
    Metro estimates that the three phase project, adding 9 miles of track and 7 new stations, will cost a total of $8.2 billion. Metro has received over half of its funds from "New Starts" grants and low interest loans from the federal government.
    According to the accelerated schedule after measure M, the full extension would ultimately be opened in three segments as follows:
    • 2023: open to La Cienega;
    • 2025: open to Century City/Constellation;
    • 2026: open to Westwood/VA.
    Funding is being sought to further accelerate the project's timeline as officials prefer to open all stations before the start of the 2028 Summer Olympics and Paralympic Games, which Los Angeles will host.

    Opposition

    BHUSD President Lisa Korbatov objected to the placement of the subway tunnel underneath Beverly Hills High School between the Wilshire/Rodeo and Century City/Constellation stations, noting that the district had planned to construct new buildings and a below-ground parking lot precisely where the tunnel would impact the high school's property.
    Metro chose a route placing the Century City/Constellation station at Constellation Boulevard instead of Santa Monica Boulevard, due to lower ridership projections adjacent to the Los Angeles Country Club and an earthquake fault zone in the latter area. Korbatov claimed that Metro did not properly study the route to the Constellation Boulevard station, and said it could pose a safety risk to students, citing no sources. She also pointed out that the subway tunnel would prevent BHUSD from carrying out many of its long-range construction plans. The school district and city filed a lawsuit in July 2012 against Metro.
    In April 2014, Los Angeles County Superior Court Judge ruled that Metro had properly conducted environmental studies under the California Environmental Quality Act and a transit hearing under the requirements of the Public Utilities Code. BHUSD and Beverly Hills interest groups, after spending $10 million on the lawsuit through August 2017, lost the appeal to prevent Metro from contracting with the FTA for the subway project. The school district and city appealed the decision to the California Court of Appeals and lost again, The court citing Metro is in compliance.
    On January 26, 2018, BHUSD again submitted a lawsuit against the FTA and Metro for them to conduct another environmental study for health reasons and prohibit the FTA from granting federal funds to the Project until the agencies have fully complied with federal law. BHUSD alleged in June 2018 that Purple Line construction in Century Park East property is affecting their property. Metro responded they are complying with their compact agreement made prior to construction. Metro's response to the new lawsuit stated they have complied and the supplemental environmental in Beverly Hills and the Century City/Constellation station meets all legal requirements. That additional analysis confirms they can safely build the project, including the portion beneath Beverly Hills High School. As recently as October 2018, Lisa Korbatov and other members of the BHUSD maintained the district is continuing their litigious action against Metro and the Purple Line Extension construction project. In June 2019, the lawsuit was placed on hold by a local district court judge. No actions taken, stating it is in "Abeyance". BHUSD is requesting mediation. Metro has declined mediation in the past citing they have always been in compliance with the DEIR/EIR results and previous environmental review studies added by the courts. In May of 2020, the courts sided with metro once again, citing "Metro satisfied the obligation and that their determination was not arbitrary or capricious" ending the lawsuit. Work continues on the subway extension and Metro reports it has not affected their timeline for completion. They report its "on time and on budget".
    Lisa Korbatov is now a Republican lobbyist for BHUSD and per reports has now spent over $16 Million in school tax bonds to sue Metro.

    Construction

    Phase One

    In July 2014, a joint venture by Skanska, Traylor and J.F. Shea Co. was selected by the Metro board, in a 9 to 3 vote, as the winner of the $1.6 billion contract for Section 1. Skanska was selected over a competing bid by Dragados that was $192 million lower because of Skanska's experience building other Los Angeles transportation projects, like the Expo Line and the Regional Connector.
    Groundbreaking occurred for Section 1 of the extension in November 2014. The segment will cost $2.8 billion: the federal government will provide a $1.25 billion "New Starts" grant and an $856 million infrastructure loan, with the remainder of the budget from Measure R funds. When complete, each station will have a ridership of around 62,000 on weekdays. Twin Herrenknecht boring machines "Soyeon" and "Elsie" began digging the section in the fall of 2018 from the La Brea Station to Wilshire/Western station. Soyeon arrived at Wilshire/Western in June 2019, marking the halfway point of phase one. The TBMs were then returned to Wilshire/La Brea to head west to Wilshire/La Cienega.
    As of January 2020, phase 1 is 57.4% complete.

    Phase Two

    In January 2017, phase two of the project, which will extend trackage further to Century City, was awarded a $1.6 billion grant from the Federal Transit Administration, covering the majority of the $2.6 billion estimated cost of the project. Federal funding was secured through the last months of the Obama Administration and local funds with the passage of Measure M. On January 27, the Metro board awarded a $1.37 billion construction contract to a joint venture between Tutor Perini and O&G Industries, with construction scheduled to be completed by 2025. Phase two was given notice to proceed in April 2017 by Metro to Tutor/O&G and it began the pre-construction phase. Major work at the planned Wilshire/Rodeo Station in Beverly Hills began at the end of 2018. The official groundbreaking ceremony for phase 2 took place on February 23, 2018. The twin boring machines were introduced as Ruth Bader Ginsburg and Harriet Tubman and delivered on June 17, 2019 to the Century City/Constellation station staging site. Where it will head east to the Wilshire/La Cienega station. Due to CoViD-19 pandemic stay at home orders, Metro was able to fast track piling and decking of Wilshire/Rodeo station from a January 2021 completion to a June 2020 completion.
    As of January 2020, Phase 2 is 25% complete.

    Phase Three

    The $410 million tunneling contract was announced to the joint bid of Frontier-Kemper and Tutor Perini JV for the 2.59 miles twin tunnels construction portion and the $1.8 Billion contract with Tutor Perini for the "design/build" of stations. These two stages were contingent on receiving the final federal full funding grant agreements approved by congress in 2016. Advance utility relocation began in February 2018 for the future Westwood/UCLA station. While federal funding for phase three had already been approved in 2016, there was some delays from the Trump Administration in issuing funds.
    Metro needed "Letters of No-Prejudice" from the USDOT FTA for tunneling before October 2018, as it would have delayed the projects approved schedule. Metro would have had to re-issue the contract. USDOT finally issued the letter to proceed in September 2018. It also issued $491 million in starting grants, along with $100 million in November 2018 and another $100 Million in July 2019 of the FFGA. With these amounts received, Metro and Frontier-Kemper/Tutor Perini JV then proceeded on an expedited tunneling schedule and commenced construction.
    In February 2019, Metro approved the project's overall $3.6 billion budget, and officially awarded contractor Tutor Perini the design/build contract. In April 2019, Metro received a second "letter of no prejudice" from the FTA for construction of stations, testing, and track work. On February 2020, Metro received its total and final FFGA of $1.3 billion "New Starts" grants. Construction work continues on an accelerated schedule in time to open by 2027.
    As of January 2020, phase 3 is 7% complete. Construction progress is limited while in design stage. Tunnel design is 92% complete and station design is 30% complete.