Pont Gustave-Flaubert


The Pont Gustave-Flaubert is a vertical-lift bridge over the River Seine in Rouen, Seine-Maritime, Normandy, France. It was officially opened on 25 September 2008 after four years of construction.
The bridge itself cost approximately to build. Additional costs, including work to surrounding infrastructure and approach roads, brought the total cost to €137 million. Construction began in June 2004. Rouen City Council named the bridge after the 19th-century novelist Gustave Flaubert, who was born and died in Rouen.

History

The design team, included the engineering firm Arcadis NV and the consultancy firm Eurodim. The specialist machinery was designed by Aymeric Zublena, one of the architects of the Stade de France, and Michel Virlogeux, designer of the Pont de Normandie Bridge and the Millau Viaduct.

Construction

The contract for the bridge construction, without the approaching viaducts, was €60 million. It was won by Quille, a subsidiary of Bouygues, in association with the Eiffel company, Eiffage and the Belgian firm Victor Buyck. The déclaration d'utilité publique passed in September 2001.
Work began in June 2004 and the installation of "butterflies" at the top of the stanchions was completed on 16 and 17 August 2006; the approaches were completed on 21 and 22 August 2006.
On 14 April 2007, the barque Belem, which had been docked for a month, went under the bridge, after initial tests that allowed the bridge to lift enough to let her pass. A crowd from Rouen was present to celebrate the event.

Name

The bridge is named after the writer Gustave Flaubert. The name was finally chosen on 15 December 2006 by Rouen City Council of Rouen, after consultation with the people of Rouen who had a choice between Flauber and René-Robert Cavelier, Sieur de La Salle. It was previously known as "the sixth bridge".

Location

Two general routes were considered:
The western route was dismissed because of the hilly, afforested terrain, and the second route chosen because of its greater proximity to the residential and business areas of central Rouen.
The bridge is near the interchange of the Autoroute de Normandie, at its southern approach, via the RN338, A150 autoroute and the slip road which connects the A29 and A28.
This link was intended to help the western districts of Rouen while providing the necessary connections to the industrial and commercial areas, and the Port of Rouen. Near its base at the right bank is an old port area undergoing redevelopment. The Maritime, Fluvial and Harbour Museum of Rouen is in this area. The left bank is a brownfield site that will probably be sold for redevelopment.

Structure

Several types of structure were considered. The essential requirement was to construct a Seine river crossing which allowed large vessels access to the Port of Rouen, upstream.
These various unsatisfactory solutions led the client to consider the fact that large ships only needed access beyond the bridge 20 to 30 times a year, so that three kinds of moveable bridge were considered:
All these potential solutions have their advantages and disadvantages. In particular, moveable bridges totally cut the traffic flow when they are open to river traffic. However, in the end, a lift bridge was chosen.

Features

The bridge is a lift bridge with a bridge span of and a total height of. It is the third tallest building in Rouen, after Rouen Cathedral and Rouen Castle. The air draft is when the deck is down, which still allows the passage of barges and smaller craft. It is above the Seine when raised. It is thus the tallest lift bridge in the world.. The total length, including the approach viaducts, is.
The dual decks, each of which is long and weighs, is supported by four pylons piled into the Seine riverbed. It takes twelve minutes fully to raise or lower the lift section.

Operation

The lift section is expected to open around 30 times a year, in particular for the Rouen Armarda and for cruise ships who dock in the city centre. Traffic is projected at 50,000 vehicles a day, relieving central Rouen of around a quarter of the 190,000 trucks that cross the river each day.
Some have questioned its usefulness and believe that the bridge will rise far less. Owners of boats have said they will not take the risk of being stuck on the other side of the bridge in case of bridge failure. A new Pleasure Terminal has also already been built downstream.