Ouvrage Galgenberg forms a portion of the Fortified Sector of Thionville of the Maginot Line. It is situated in the Cattenom Forest, near the gros ouvrageKobenbusch and petit ouvrage Oberheid. The ouvrage was tasked with controlling the Moselle valley and as such was called the "Guardian of the Moselle." Galgenberg did not see significant action in 1940 or 1944. After a period of reserve duty in the 1950s and 1960s it was deactivated. It is now a museum.
Design and construction
The Galgenberg site was surveyed by the Commission d'Organisation des Régions Fortifiées, the Maginot Line's design and construction agency, in 1930. Work began the next year, and the position became operational in 1935, at a cost of 48 million francs. The contractor was Verdun-Fortifications. The site occupies the heights of the Galgenberg. Ouvrage Sentzich is close by in the side of the Galgenberg massif, overlooking the town of Sentzich and the road to the north.
Description
The ouvrage comprises two entries and six combat blocks:
Personnel entry: shaft, one GFM cloche and one JM/AC47 embrasure.
Block 1: Infantry block with one JM/AC47 embrasure and one GFM cloche.
Block 2: Infantry block with one JM/AC47 embrasure, one JM embrasure, and two GFM cloches.
Block 3: Infantry block with machine gun turret and one GFM cloche.
Block 4: Artillery block with 81mm mortar turret and one GFM cloche.
Block 5: Observation block with one GFM cloche, one machine gun cloche, and one observation cloche.
Block 6: Artillery block with 135mm gun turret, one grenade launcher cloche and one GFM cloche.
Galgenberg has a small "M1" main magazine compared to other 'gros ouvrages''.
Casemates and shelters
The Observatoire de Cattenom is located behind Galgenberg, near the Casernement de Cattenom, which provided above-ground peacetime quarters for the garrisons of the nearby ouvrages. The observation point was armed with one GFM cloche and an observation cloche. Flanking Galgenberg to the north is the Casemate du Sonnenberg, armed with one JM/AC37 embrasure, one JM embrasure and one GFM cloche. None of these are connected to the ouvrage or to each other. All were built by CORF
Manning
The 445 men and 15 officers of the 167th Fortress Infantry Regiment and the 151st Position Artillery Regiment were under the orders of Captain Guillaume de la Teyssoniére. The units were under the umbrella of the 42nd Fortress Corps of the 3rd Army, Army Group 2. The Casernement de Cattenom provided peacetime above-ground barracks and support services to Galgenberg and other ouvrages in the area.
History
Galgenberg did not see significant action in the Battle of France in 1940, nor in the Lorraine Campaign of 1944. In 1940 Galgenberg fired on German infiltrators in the area. An accident with an 81mm mortar projectile damaged a mortar tube on 14 June 1940, which was repaired after three days. The Germans largely bypassed the valley of the Moselle, advancing along the valley of the Meuse and Saar rivers, threatening the rear of the Thionville sector. An order to fortress troops by sector commander Colonel Jean-Patrice O'Sullivan to prepare for withdrawal on 17 June was reversed by O'Sullivan. The garrison therefore remained in place. The garrison therefore remained in place. Following negotiations, the positions on the left bank of the Moselle finally surrendered to the Germans on 30 June 1940.
Renovation
In the 1950s the French government became concerned about a possible invasion by the Warsaw Pact through Germany. The Maginot Line, while obsolete in terms of its armament, was viewed as a series of useful deeply buried and self-sufficient shelters in an era of air power and nuclear weapons. A number of the larger ouvrages were selected to form defensive ensembles or môles around which a defense might be organized and controlled. Galgenberg was nominated as a communications station, in concert with the command posts at Rochonvillers, Soetrich and Molvange.
Current condition
The ouvrage has been maintained by the Association Ligne Maginot du Secteur Fortifié du Bois de Cattenom, which also maintains Bois Karre, since 1987 and portions of the ouvrage are open to visits during the summer months. The combat blocks are not accessible, but work is continuing to restore the fortification.