Otavi Mining and Railway Company


The Otavi Mining and Railway Company was a railway and mining company in German South West Africa. It was founded on 6 April 1900 in Berlin with the Disconto-Gesellschaft and the South West Africa Company as major shareholders.

Construction

OMEG built a narrow gauge railway extending from Swakopmund on the Atlantic coast to the mines of Tsumeb. Construction began in 1903 and reached Tsumeb three years later. The first of railway required 110 steel bridges to cross deeply eroded gullies through sparsely vegetated arid terrain. Most were deck plate girders. The railway, known as the Otavibahn, was the longest gauge railway in the world at its time of construction.
Construction coincided with the Herero and Namaqua Genocide. Delays resulted from labor shortages and military heeresfeldbahn operations. A 91-kilometer branch was completed in 1908 from Otavi to mines near Grootfontein.
During World War I, German troops had moved inland by the time South African troops reached Swakopmund in January, 1915. German forces destroyed the railroad as they retreated, and South African forces reconstructed a narrow gauge line over the route to Karabib in 1915.
German troops surrendered following defeat at Otavi in July, 1915; and service was re-established over the remaining narrow gauge line from the railway shops at Usakos with freight transfer facilities at Karabib.

Nationalization and conversion to Cape gauge

The Otavi line was nationalized in 1923. Train service was interrupted by a locust infestation in 1924 until steam nozzles were installed on locomotives to sweep the insects off the rails before their crushed bodies could reduce traction under the locomotive wheels. The worst flooding in forty years caused extensive washouts in 1925.
The Tsumeb mines closed in 1933. German rearmament activity reopened the mines from 1936 until the South African government closed the mine as enemy property in 1940. Tsumeb mines reopened again in 1946. The remainder of the line was regauged to narrow gauge in 1961 and became part of the TransNamib.
with high-side gondola near Tsumeb about 1931.
Garratt, preserved in operating condition on the Welsh Highland Railway. This later version of the locomotives used from 1927 to 1933 is the model considered for use in 1958.
, Namibia

Rolling stock

The first locomotives designed for regular service were fifteen 0-6-2T built by Arn. Jung. Henschel & Sohn built twelve locomotives similar to the Jung design and three 0-6-0T. Twenty 8-wheel auxiliary tenders carrying 8 cubic metres of water and of coal were built to enable these tank locomotives to complete longer runs. Henschel & Sohn built three HD class 2-8-2 in 1912 with separate 8-wheel tenders for long-distance running. These locomotives weighed and remained in service for 50 years as the 2-8-2 type became standard for the railway.
By 1913, train service included 4 express trains, 14 mixed trains, and 29 freight trains each week. Express and mixed trains included a baggage car, a car for African passengers, and a coach for first and second class passengers. The passenger cars carried concrete ballast in a depressed center section to minimize the possibility of wind tipping a lightly loaded car off the rails. Express trains stopped only at designated stations, but other trains would stop at intermediate points when transport was required. Equipment included:
A special rail motor coach was built for an anticipated visit of Kronprinz Wilhelm in 1914. A 6-cylinder Daimler-Benz gasoline engine gave the car a speed of and the title of the fastest gauge rail car. World War I intervened to prevent Wilhelm's visit, and the car was used as an inspection vehicle after the war.
Two Henschel & Sohn 4-6-2 locomotives built in 1914 had disappeared during the war; but Baldwin Locomotive Works delivered a 4-6-2 in 1916. A coach converted for meal service from 1916 to 1931 is believed to be the only gauge dining car ever operated.
Six more Henschel & Sohn 2-8-2 were delivered in 1922. These locomotives were designated South African Railways NG5 class. Three SAR NGG 13 Class 2-6-2+2-6-2 Garratt locomotives were used from 1927 until 1933. Henschel & Sohn delivered three SAR NG15 Class 2-8-2 locomotives in 1931. Four sleeping cars were built for the railroad in 1938; when Henschel & Sohn delivered three more 2-8-2 SAR NG15 Class. Fifteen more SAR NG15 Class 2-8-2 locomotives were delivered as three groups of five in 1949, 1952, and 1957. Purchase of additional Garratt locomotives was briefly considered in 1958 but cancelled due to the upcoming track gauge conversion to narrow gauge.