OPR-1000


The OPR-1000 is a South Korean designed two-loop 1000 MWe PWR Generation II nuclear reactor, developed by KHNP and KEPCO. The OPR-1000 was originally designated as the Korean Standard Nuclear Power Plant, and was re-designated as the OPR-1000 in 2005 for foreign sales. It was developed based partly on the Combustion Engineering designs, through a technology transfer agreement. The reactor core design was derived from the C-E designed Arkansas Nuclear One Unit 2, the nuclear steam supply system was derived from the C-E designed units at Palo Verde Nuclear Generating Station and auxiliary plant design was derived from the earlier Unit-1 and Unit-2 at the Yeonggwang Nuclear Power Plant.
Based on the OPR-1000 design, KEPCO has developed a Generation III+ uprated plant, the APR-1400.

Reactor fleet

The reference plants used to develop the OPR-1000 design using technology transfer are Yeonggwang Unit-3 and Unit-4, which came on-line in 1995 and 1996, respectively. The first plants designated as OPR-1000 plants are Ulchin Unit-3 and Unit-4, which came on-line in 1998 and 1999, respectively.
Korea Hydro & Nuclear Power states an improved OPR-1000 design has been implemented at eight units:
Including the reference Unit-3 and Unit-4 at Hanbit, there are a total of twelve OPR-1000 plants, all inside South Korea.
SiteUnitStatusConstruction
Start
First
Criticality
Operation
Hanbit3operational23 December 198913 October 199431 March 1995
Hanbit4operational26 May 19907 July 19951 January 1996
Hanbit5operational29 June 199724 November 200121 May 2002
Hanbit6operational20 November 19971 September 200224 December 2002
Hanul3operational21 July 199321 December 199711 August 1998
Hanul4operational1 November 199314 December 199831 December 1999
Hanul5operational1 October 199928 November 200329 July 2004
Hanul6operational29 September 200016 December 200422 April 2005
Shin-Kori1operational16 June 200615 July 201028 February 2011
Shin-Kori2operational5 June 200727 December 201120 July 2012
Shin-Wolsong1operational20 November 20076 January 201231 July 2012
Shin-Wolsong2operational23 September 20088 February 201524 July 2015

History

The first start of the OPR-1000 at Shin Kori Nuclear Power Plant Unit-1 was 28 February 2011.
This OPR-1000's first malfunction was noted on 2 October 2012 at 8:10 a.m. Shin Kori-1 was shut down after a warning signal indicated a malfunction in the control rod, which is used to control the rate of fission of nuclear materials, according to the Korea Hydro & Nuclear Power Co. It is the first time that reactor, located 450 kilometers southeast of Seoul, has been shut down due to a malfunction since it began commercial operation on 28 Feb. 2011. An investigation was undertaken to verify the exact cause of the problem.
In 2012, a probe was opened regarding some fraudulently-certified parts installed in five OPR-1000 reactors over a ten-year period. Hanbit-5 and -6, which had a greater number of fraudulent parts, were shut down until the parts could be replaced, and Hanbit-3 and -4 and Hanul-3 were allowed remain on-line pending parts replacement. Hanbit-5 and -6 were cleared for restart in early 2013, but in April 2013, following a tip, four additional units were shut down and not allowed to restart until fraudulently-certified safety-related control cabling was replaced: Shin Kori-1 and -2 and Shin Wolsong-1 and -2; although construction on Shin Wolsong-2 was complete, it had not yet achieved operational status, and it was not allowed to start up until cabling was replaced. The same cabling was used at the APR-1400 units then under construction at Shin Kori, forcing a year-long delay in their startup. After cabling was replaced, Shin Kori-1 and -2 and Shin Wolsong-1 were approved for restart in January 2014. Shin Wolsong-2 was connected to the grid in February 2015, with commercial operation commencing in July 2015.