Nuclear Power Demonstration


Nuclear Power Demonstration was the first Canadian nuclear power reactor, and the prototype for the CANDU reactor design. Built by Canadian General Electric, in partnership with Atomic Energy of Canada Limited, Ontario Hydro and the US Atomic Energy Commission, it consisted of a single 22 MWe pressurized heavy water reactor unit located in Rolphton, Ontario, not far from AECL's Chalk River Laboratories. NPD was owned by AECL and operated by Ontario Hydro.
The NPD was the prototype and proving ground for research and development that led to commercial application of the CANDU system for generating electric power from a nuclear plant using natural uranium fuel, heavy water moderator and coolant in a pressure tube configuration with on-power refuelling.

Description

The NPD station was located on the west bank of the Ottawa River about upstream from the City of Ottawa. It was situated close by the AECL research establishment at Chalk River and the HEPC hydro generating station at Des Joachims, Ontario. It had a maximum continuous output of 22 MW, which gave a net station output of 19.5 MW.
The reactor was fueled with of UO2 in the form of ceramic pellets sheathed in Zircaloy-2 tubes. The fuel was subdivided into nine bundles per channel, and fuel changing was designed to be carried out on power by remotely operated machines which push a fresh bundle in one end of the channel and remove the spent bundle from the other end, a design feature that carried through to the later CANDU products.
The primary role of NPD was as a prototype for CANDU engineering. Over the years it served as a test bed for new fuels, materials, components, and instruments.
Equally important, NPD was the training and simulation center for generations of Canadian and off-shore CANDU operations staff. This role began shortly after the start of operation, when a training program was set up by Ontario Hydro.

History

In December 1961, the major construction phase was concluded and system testing was in full swing. Criticality was first attained on April 11, 1962, and first steam of nuclear origin was produced on May 8. The first electrical power was fed to the system on June 4, and on June 28 first full-power generation of 20 MW gross was attained.
NPD began operation in 1962 and was operational until 1987, long after vastly more powerful and modern CANDU units came on-line. The first nuclear-produced power in Canada was generated at NPD, which also served as the "proof of concept" prototype for the later CANDU designs. As with all commercial CANDU units to follow, NPD operated with natural uranium fuel in a horizontal pressure-tube core, was both moderated and cooled by heavy water, and was refuellable on-load. NPD closed in 1987 after exceeding its operational goals. As of 2006, all fuel and non-nuclear equipment have been removed from the site, while much of the nuclear equipment is still present. AECL intends to leave potentially active or contaminated equipment on site for some decades yet to allow for further radioactive decay.
The site was commemorated by a historical plaque detailing the operational history and highlights of the station. However, for reasons of security and public safety, the plaque is set three kilometres west of the site at a highway lookout, and the site itself cannot be seen from the plaque's location. Another bronze plaque and monument commemorating NPD, formerly located on the NPD site, was relocated to the Schoolhouse Museum about three kilometers to the east of the site. The Schoolhouse Museum also includes a scale model of the plant and other historical artefacts.
NPD was followed by the 200 MWe Douglas Point Nuclear Generating Station on the shore of Lake Huron.