Long Lake (oil sands)


The Long Lake oil sands upgrader project is an in situ oil extraction project near Anzac, Alberta, southeast of Fort McMurray in the Athabasca oil sands region of Alberta.
The project is owned and operated by CNOOC Petroleum North America, formerly known as Nexen.
Long Lake is an integrated steam-assisted gravity drainage site which produced of bitumen in 2017. The project used proprietary OrCrude technology as well as hydrocracking and gasification to produce Premium Synthetic Crude oil, with a production capacity of approximately, however the upgrader was shut down following a 2016 explosion.

History

Development

In 2001, Nexen formed a joint venture with OPTI Canada Inc. to develop the Long Lake lease using SAGD for in-situ bitumen production and OrCrude technology to upgrade the bitumen to PSC.
The first phase of the project received regulatory approval in 2003 and was sanctioned in 2004. Construction at the site began in 2004. Steam injection began in 2007 and the first production was in 2008.
SAGD bitumen operations at Long Lake started in mid-2008 and production of PSC from the upgrader began in 2009. Early in 2009, Nexen acquired an additional 15% interest in the Long Lake project, increasing the company’s ownership level to 65%. Following this acquisition, Nexen became responsible for operating the entire project.
There have been some technical problems and the project has failed to meet production projections. As of early 2011, the site was producing about and OPTI was struggling under a heavy debt load and lack of liquidity. On February 1, 2011, OPTI appointed Lazard Freres & Co., a bankruptcy specialist, raising speculation that restructuring or bankruptcy for the company was imminent. In 2011, CNOOC Limited acquired OPTI, which included the 35% non-operated interest in the Long Lake project and joint venture lands.
On February 25, 2013, Nexen was acquired by CNOOC Limited.

2013 Alberta floods

Enbridge Pipelines Inc., a subsidiary of Enbridge Inc., reported a pipeline leak site, about 70 kilometres southeast of Fort McMurray, near its Cheetham terminal on June 22, 2013 of approximately 750 barrels of Light Synthetic Crude oil from CNOOC’s Long Lake upgrader SAGD project that spilled into a wetland area near Anzac. Unusually heavy rainfall in the region may have caused "ground movement on the right-of way that may have impacted the pipeline." Operations between Hardisty and Cheecham were restored on June 23 when Enbridge’s Athabasca pipeline was safely restarted.

2015 oil spill

On July 15, 2015, a pipeline oil spill at the facility was discovered in the afternoon by a worker in which the factory's failsafe system was unable to detect. As of July 16, 2015, at least —or 31,500 barrels—of oil emulsion has been spilt onto an area of approximately, The company said efforts were made to stabilise the leak, such as shutting down operations at the time of discovery and isolating the area. The company said the pipeline was installed in 2014 and contains an emulsion mixture of bitumen, wastewater, and oil sand. Determining the cause of the spill would take months, according to a company employee.
Efforts were made to clean up the affected area, such as vacuum trucks, and avoid further environmental impact, like affecting wildlife. On July 19, one duck was found dead from the spill.
The facility resumed operations by September 2015, but 45 pipelines remained shut down at that time.
Investigations concluded that the subsurface pipeline ruptured in the muskeg due to improper design on June 15, but remained undetected by detection systems for a month until being discovered by workers. Nexen was fined $750,000 for the spill.

2016 explosion

On January 16, 2016 an explosion occurred in the hydrocracker unit killing Drew Foster, 52 and injuring Dave Williams, 28 who succumbed to his injuries January 25. In 2019, Nexen plead guilty to charges resulting from the incident and was fined $450,000.

Recent history

In 2018, Nexen announced a $400 million expansion project, which is expected to begin production in late 2020.

Process

The Long Lake project uses SAGD to extract bitumen from the underground oil sands. The process involves using two separate horizontal wells into the reservoir. One well is used to inject steam, which reduces the viscosity of the bitumen. The previously stable bitumen then drains into the second well, which extracts it to the surface.
The Long Lake upgrader used OPTI's OrCrude process, which refines by-products of the extracted bitumen into usable fuel, which is used to generate steam. This process also generates hydrogen, which fuels the refinement of extracted bitumen through hydrocracking. The upgrader was idled and then permanently closed following the 2016 hydrocracker explosion.

Infrastructure

The Long Lake upgrader is linked with the Enbridge Athabaska Pipeline, a 17-kilometre-long, 12-inch diameter pipe from Long Lake to Cheecham terminal. Enbridge’s 540-kilometre Athabasca from Cheecham to Hardisty, a major part of the network that serves Alberta's oil sands, "can carry up to 570,000 barrels per day of crude from the Athabasca and Cold Lake regions to Hardisty, Alta., a major pipeline hub in eastern Alberta, about 200 kilometres southeast of Edmonton."

Anzac (Long Lake) Heliport

The Anzac Heliport is located on the Long Lake site.