List of main infrastructure projects in Indonesia


This list of main infrastructure projects in Indonesia includes recently completed projects, activities reported being under way, and main projects which have been announced as likely to start in the near future.

Introduction

Three points may be noted about this list.
  1. Individual projects. The list includes individual projects rather than broader programs that combine many projects. However the distinction between projects and programs is not always clear. For example, the Trans-Java toll road consists of many individual activities each of which might be considered as small individual projects. However, the construction of the toll road is often referred to in the media and by government officials as a project. It has therefore been considered a single project for the purposes of this list. On the other hand, the Indonesian government has announced two 10,000 MW 'fast track' electricity generation investment programs. These programs clearly consist of a wide range of individual large and small projects and so the two fast track electricity programs have not been listed as individual projects here.
  2. Delays. As in common in many countries, it is often the case in Indonesia that projects take longer than originally expected to get underway. And some projects do not proceed beyond an encouraging announcement phase. Projects listed below as 'proposed' are significant projects which appear to have some reasonable prospect of proceeding within the foreseeable future.
  3. Masterplan. As a background to the list, most projects listed here are mentioned in the significant Indonesian government's Masterplan 2011-2015 released in May 2011. The Masterplan amounts to an outline of investment plans in the infrastructure sector. A comprehensive list of potential projects is listed in the appendix to the Masterplan although in most cases the source of investment funding is not specified.

    Currently underway

Jakarta-Bandung and Jakarta-Surabaya high-speed rail

Estimated cost: around $US 5.5 billion
Estimated cost: Rp 51.6 trillion for 619 km.
The idea of a trans-Java toll road stretching from the ports of Banyuwangi in the province of East Java to Merak in Banten province in the west of Java has been under discussion in Indonesia for many years. There were plans to get the project underway during the 1990s but work was put on hold following the impact of the 1997-98 Asian Financial Crisis in Indonesia. The length of the major highway road is mentioned, variously, at between 800 km to over 1,100 km depending on precisely which subsections of the overall activity are said to be included. There are usually at least 20 subsections listed as part of the overall project. The status of the subsections currently ranges from operational to still in the planning stage. Land acquisition is often a major problem. There are frequent reports in the national press of land acquisition programs for various sub-projects within the overall scheme. The cost of constructing the major part of the toll road is listed in the Indonesian government's Masterplan 2011-2015 as Rp 51.6 trillion.
Estimated cost: Rp 351 trillion
The plan is to construct a trans-Sumatra toll road from Banda Aceh at the northern tip of Sumatra to the province of Lampung in the south, a distance of perhaps around 2,000 km or more. The plan is to begin the large project with the construction of a 22-km stretch from Palembang to Indralaya in the province of South Sumatra beginning in March 2013. The state-owned construction firm PT Hutama Karya has been appointed by the Ministry of State-Owned Enterprises] to begin work on the overall project of constructing the overall toll road.
Estimated cost: Around $4 billion. Listed in the Indonesian government MP3EI Masterplan at Rp 26 trill over the period 2013 to 2019.
The Indonesian firm PT Bhimasena Power Indonesia is developing the project, and ultra-supercritical coal-fired power plant, in Batang Regency, near Pekalongan. The plant, which will have a capacity of 2,000 MW, is scheduled to begin commercial operations in 2017. A consortium of J-Power, Itochu Corporation of Japan, and the coal-mining firm PT Adaro Energy Tbk, will build the plant. The plant will be an IPP and power will be sold to the PLN. The project was initially due to be completed by end-2016. Initial planning work was done with support of the International Finance Corporation. The cost of the initial planning work is expected to be recouped from successful contractors. The state Indonesian Infrastructure Guarantee Fund is reported to have agreed to provide financial guarantees to the investors covering financial risks if PLN fails to meet its financial obligations.
Estimated cost: varies from Rp 15.5 trillion to Rp 23 trillion
The Jakarta Mass Rapid Transit Project mainly consists of the planned construction of a series of MRT rail links across Jakarta.
First phase will be a 15.5 kilometer North-South corridor with 13 stations. The plan is to construct a central MRT station with a line running from Lebak Bulus to the Hotel Indonesia traffic circle. Initial plans are for six underground stations and seven above-ground stations. Groundbreaking is expected to take place during 2013. The project was originally said to be targeted for completion in late 2016 although more recently a target date of 2018 has been mentioned. The project has support from the Japanese government and major Japanese construction firms have been showing interest in bidding for sections of the activity. Funding will be initially provided from a Yen 120 billion soft loan from JICA.
Second phase, it is expected that the line will be extended northwards
Third phase is the east-west line that will connect Tangerang to Bekasi and will connect to second phase in Kebon Sirih station, Central Jakarta.
Estimated cost: Rp 23.8 trillion rupiah.
The Jakarta light rail transit system is planned to connect Jakarta city centre with suburbans in Greater Jakarta such as Bekasi and Bogor.
First phase of LRT is planned to include three lines: Cibubur-Cawang - Dukuh Atas: 24.2 km, and Bekasi Timur - Cawang: 17.9 km. Construction Phase I began on September 9, 2015 and will be finished by 2021.
Second phase will extent the first phase lines: Cibubur-Bogor Baranangsiang, Dukuh Atas-Palmerah-Senayan, and Palmerah-Grogol. The construction phase of extension for the planned route from Grogol - Pesing - Rawa Buaya - Kamal Raya - Dadap - Soekarno–Hatta International Airport is proposed, but was not mentioned in Peraturan Presiden Republik Indonesia Nomor 98 Tahun 2015.

Trans-Sumatra railway

Estimated cost : US$5.5 billion
It was announced that the Transportation Ministry was preparing plans for a 2,168 km rail link from Aceh in the northern tip of Sumatra to Lampung at the southern tip. A feasibility study was expected to be prepared during 2015. In the first stages, selected segments of the proposed Sumatran rail link would be given priority.

Trans-Kalimantan railway

Trans-Sulawesi railway

Postponed

Sunda Strait Bridge

Estimated cost: perhaps between $US 15 - 20 billion
The Sunda Strait Bridge project is an ambitious plan for a road and railway megaproject between the two Indonesian islands of Sumatra and Java. In October 2007, after years of discussion and planning, the Indonesian government gave the initial go-ahead for a project which included several of the world’s longest suspension bridges, across the Sunda Strait. The project remained at the feasibility stage during the period of the administration of president Susilo Bambang Yudhoyono although senior government figures, including the president, repeatedly said that the project would begin before the end of his administration in 2014. A number of ministerial meetings were held in the period 2010 - 2014 to discuss steps needed to support the project. However, in November 2014, the incoming Joko Widodo government announced that plans to build the bridge would be shelved.