Kusile Power Station


Kusile Power Station in South Africa is a coal-fired power plant under construction by state electricity utility Eskom.

Location

Located about 15 kilometres north of the existing Kendal Power Station near Witbank, Mpumalanga.

Original Concept

Kusile Power Station is designed to consist of six 800 megawatt coal-fired generating units for a total generating capacity of 4,800 megawatts. This station would be the first in Eskom's fleet with flue gas desulphurization technology.

Project Engineer

was appointed as the project engineer for construction.

Main equipment suppliers

provided the steam turbines, whilst Hitachi would provide the super critical boilers.

Coal supply

The power utility, Eskom stated that it "will obtain most of the coal required for this Power Station from Anglo Coal's New Largo operations, south east of the Kusile Power Station."
Eskom’s consultants estimate that 35 new coal mines will be required to support the Medupi and Kusile plants.

Construction timeline

Initially expected to take 6 years to complete, the project was not expected to complete Unit 1 until 2017 and the entire project not until 2021.
The dates for full commercial operation were shifted numerous times mostly due to:
This resulted in Kusile and Medupi considered as some of the worst-performing units in Eskom's fleet. In February 2019, Eskom GM for group technology Titus Mathe reported R8 billon would be needed to fix design defects at Medupi and Kusile.

Critics

The building of this power station attracted various criticisms.

Interference

Hitachi Power Africa, a subsidiary of Hitachi, Ltd.,found by the U.S. Securities and Exchange Commission to have made US$6 million in corrupt payments to a front company for the African National Congress, the ruling political party in South Africa. Hitachi agreed to pay US$19 million to settle charges. Hitachi Power Africa rebranded as Mitsubishi Hitachi Power Systems Africa in February 2014.

Cost

Kusile Power Station is estimated to cost R118 billion to complete.

Financial Institution Support

The following institutions were involved in supporting the project:

Emissions

The plant is expected to emit est 36.8 million tonnes of CO2-equivalent per year once completed.
A 2011 report by Greenpeace Africa and the University of Pretoria’s Business Enterprises calculated Kusile's climate change to water use, and impact on health,estimating that the damage caused will cost between R31.2 billion and R60.6 billion a year, and that 30% of Kusile’s externality cost would have been able to generate five times the power with renewable energy.
In November 2011, Greenpeace activists chained themselves to a gate and climbed a crane, a few weeks before the country hosted a global conference on climate change. Authorities arrested nine people, on charges of trespassing and malicious damage to property.
The design of the station does allow for the installation of flue gas desulphurization technology.

Inquiry

By 2018, the governments Public Enterprises Minister Pravin Gordhan announced a forensic probe into delays and cost overruns on the completion of Kusile and Medupi Power Stations.

Corruption controversy

In November 2019 South African investigative journalist Pieter-Louis Myburgh published an article in the Daily Maverick detailing an alleged slush fund corruption scandal involving Eskom executives and at least four contractors. The scandal involved contracts worth a combined R10 billion resulting in an estimated R75 million being lost due to irregular activities. By the time of the publication of Myburgh's article the construction of Kusile was five years past its original completion date and an estimated R80 billion over budget.