had proposed Kollam bypass project in 1972. The then Public Works Department minister Mr. T. K. Divakaran was the man behind Kollam bypass project. The earlier plan was to construct a bypass road through Kollam city via Olayil, Thevally, Vellayittambalam. But T. K. Divakaran denied that proposal and asked to re-draw the plan through Mevaram. Ayathil, Kallumthazham, Kavanad route and then mooted the bypass plan as per the new route. Later in 1993, a stretch of 3 km from Mevaram to Ayathil was completed and 1.5 km Ayathil-Kallumthazham stretch was completed in 1999 and the remaining Kallumthazham-Kavanad stretch completed in 2019. This stretch includes three bridges, five culverts, one vehicle underpass, and five major intersections, and needs to pass over the Ashtamudi Lake. The road includes a seven-metre two-lane carriageway, paved shoulders and earthen shoulders. The importance of the Kollam bypass is that it touches 3 major National Highways, NH 183, NH 744 ) passing through the state of Kerala. The two-lane Kollam Bypass road was inaugurated on 15 January by Prime MinisterNarendra Modi. The road is witnessing heavy traffic congestion since its opening. In January 2019, the Government of Kerala and NHAI have decided to widen the road into 45 meters. As per the plan, Kollam Bypass would become a four-lane road with overbridges at Mevaram, Kavanad and underpassages at Ayathil, Kallumthazham and Kadavoor junctions.
Timeline
Project Details
Length: 13.14 km
Total Construction Cost:
Construction Mode: Engineering Procurement Construction
Contractor: Cherian Varkey Construction Company, Kochi
South End: Mevaram
North End: Kavanad
Major Bridges: 3 nos
Underpass: 1 nos *
ROB: 1 nos *
No of Pilings: 190 nos
Piers: 46 nos
Culverts: 7 nos
Included in the plan. Not yet started/completed
Junctions
Kavanad
Kadavoor
Kallumthazham
Ayathil
Mevaram
Latest developments on bypass project
18 bidders have qualified for the bypass tender process - April 2014
Government of India and Government of Kerala have decided to share the cost of Kollam bypass project equally - May 2014
Government of India has granted approval for Kollam bypass, a joint venture of the State and the Central governments in January 2015.
Chief Minister of KeralaOommen Chandy signed an agreement with a private company on 11 February 2015 to complete the works within 30 months. The total cost for works would be Rs. 352 crore. The Government of Kerala has added the Kollam bypass project to its list of mega projects.
Cherian Varkey Construction Company-RDS is the contractor for the project. Same company is responsible for the execution of Alappuzha Bypass also. It was an EPC Contract for the construction of 2 Lane Bypass.
Preliminary works for Kollam bypass has been commenced again on 4 March 2015 after a long gap. Currently, clearing of the way for bypass is going on here. Re-aligning of telephone cables, water pipelines and KSEB feeder lines will commence soon as part of this work.
26 November 2017 is the final deadline for the completion of Kollam Bypass. If the construction company fails to meet the deadline, a fine will be imposed on the company based on the delayed days.
The construction work comes to a standstill due to the insufficiency of gravel. - October 2016
In July 2017, Central Minister Pon Radhakrishnan announced that Kollam Bypass work would be completed only by August 2018 due to the scarcity of construction materials and soil to fill the land. Also, Kollam MP N. K. Premachandran announced that the bypass road will be commissioned in August 2018.
Government of Kerala hopes to open Kollam Bypass by September 2018.
Kollam bypass will be ready in a month. Street lights would be installed through out the stretch. - 25 October 2018
The inauguration of Kollam Bypass will be on 2 February 2019 by Pinarayi Vijayan, Chief Minister of Kerala. - 24 December 2018
Prime Minister's office confirmed with Kollam MP N. K. Premachandran that Narendra Modi will inaugurate Kollam Bypass on 15 January 2019 - 9 January 2019
Government of Kerala asked toll exemption to Central Ministry for Kollam bypass - 9 January 2019