Hyderabad Metro
The Hyderabad Metro is a rapid transit system, serving the city of Hyderabad, Telangana, India. It is the second longest operational metro network in India after the Delhi Metro with 57 stations and the lines are arranged in a secant model. It is being funded by a Public Private Partnership, with the state government holding a minority equity stake. A special purpose vehicle company, L&T Metro Rail Hyderabad Ltd was established by the construction company L&T to develop Hyderabad metro rail project under Public Private Partnership mode. A stretch from Miyapur to Nagole with 24 stations, was inaugurated on 28 November 2017 by Prime Minister Narendra Modi. This was the longest rapid transit metro line opened in one go in India. It is estimated to cost. As of February 2020, about 490, 000 people use the Metro per day. Trains are crowded during the morning and evening rush hours. A ladies only coach was introduced on all the trains from 7 May 2018.
History
Metro Rail Project was First initiated by then Chief Minister of United Andhra Pradesh state, N. Chandrababu Naidu in 2003 as Hyderabad continued to grow, the MMTS had insufficient capacity for public transport, and the Union Ministry of Urban Development approved construction of the Hyderabad Metro Rail Project, directing the Delhi Metro Rail Corporation to conduct a survey of the proposed lines and to submit Detailed Project Report. To rising public transport needs and mitigate growing road traffic in the twin-cities of Hyderabad and Secunderabad, the State Government of N. Chandrababu Naidu and the South Central Railway jointly launched the Multi Modal Transport System in August 2003. The initial plan was for the metro to connect with the existing MMTS to provide commuters with alternate modes of transport. Simultaneously, the proposals for taking up the construction of MMTS Phase-II were also taken forward.In 2007, N.V.S Reddy was appointed Managing Director of Hyderabad Metro Rail Limited and the same year, Central Government approved financial assistance of 1639 crore under Viability Gap Funding scheme. The option of underground metro system in Hyderabad was ruled out by L&T due to the presence of hard rocks, boulders and the topography of the soil in Hyderabad. On March 26, 2018, Telangana Govt announced that it would set up a SPV "Hyderabad Airport Metro Limited ", jointly promoted by HMRL and HMDA, to extend the Blue line from Raidurg to Rajiv Gandhi International Airport, Shamshabad under phase-II after the completion of Phase-I in 2019.
Initial bidding
The bidding process was completed by July 2008 and awarded to Maytas, which failed to achieve financial closure for the project as per schedule by March 2009.Re-bidding
government cancelled the contract and called for a fresh rebidding for the project. In the July-2010 rebidding process, Larsen & Toubro emerged as the lowest bidder for the project. L&T came forward to take up the work for about as viability gap funding as against the sanctioned. Kiran's Government proactively pursued the project but it was delayed due to separate state agitation and later due to the apprehensions of the new government.Mascot
The mascot of Hyderabad Metro Rail is Niz. It was derived from the word Nizam, who ruled the princely state of Hyderabad.Awards and nominations
HMR project was showcased as one of the top 100 strategic global infrastructure projects at the Global Infrastructure Leadership Forum held in New York during February–March 2013.L&T Metro Rail Hyderabad Limited has been conferred the SAP ACE Award 2015 in the 'Strategic HR and Talent Management' category.
In 2018, Rasoolpura, Paradise and Prakash Nagar metro stations were awarded Indian Green Building Council's Green MRTS Platinum Award.
Hyderabad Metro was adjudged as the Best Urban Mass Transit Project by the Government of India, in November 2018.
Construction milestones
- Groundbreaking for the project was conducted on 26 April 2012 the concessionaire started the pillar erection on the same day for Stage-I and on 6 June 2012 for Stage-II. The work for Corridor 2 has been delayed due to traders in Koti and Sultan Bazar demanding realignment of the route to safeguard traders and old age heritage markets. If the recent bill proposed in Parliament which allows construction within a 100-metre radius of heritage structures and sites of historical or archaeological importance is passed, Metro might receive a chance as it helps to connect the Old city with IT corridor.
- The construction of the entire 71.16 km has been split into 6 stages with the first stage originally scheduled to be completed by March 2015
- In November 2013, L&T Hyderabad Metro started laying of rails on the metro viaduct between Nagole and Mettuguda, a stretch of 8 km.
- The first highly sophisticated train of the Hyderabad Metro Rail came from Korea during the third week of May 2014. Stringent trial runs commenced from June 2014 till February 2015. The trial runs started on the Miyapur to Sanjeeva Reddy Nagar stretch in October 2015.
- CMRS inspection for Stage-II was done on 9, 10 August 2016.
- The steel bridge of the HMR was successfully placed over the Oliphant bridge in August 2017.
- In November 2017, Commissioner of Railway Safety granted safety approval for 12 km stretch from Miyapur to SR Nagar, 10 km stretch from SR Nagar to Mettuguda and 8 km stretch from Nagole to Mettuguda.
- 16-km Ameerpet-LB Nagar Metro stretch was opened for commercial operations from 24 September 2018.
- The Ameerpet - Hi-Tec City route was opened on conditional basis on March 20, 2019. The reversal facility after HITEC City metro station was started on 20 August 2019.
- On 19 May 2019, the construction of all the 2,599 pillars for the 66-km Hyderabad Metro rail was completed.
- The Green Line Corridor from Jubilee Bus Station to Mahatma Gandhi Bus Station was issued the Safety Certificate by the Commissioner of Metro Rail Safety and inauguration of services on the section was done on Feb 7, 2020 by Hon'ble Chief Minister of Telangana, Sri K. Chandrasekhar Rao.
Network
Otis Elevator Company supplied and maintains the 670 elevators in use on the system.
In May 2018, L&T Metro Rail signed a contract with Powergrid Corporation of India to install electric vehicle charging facilities at all metro stations beginning with Miyapur and Dr. B R Ambedkar Balanagar stations. L&THMRL has setup free wifi access units for commuters at Miyapur, Ameerpet and Nagole metro stations, in association with ACT Fibernet, as part of a pilot project. Metro Rail Phase II expansion plan is for about 85 km. In April 2019, K. T. Rama Rao said that of metro rail was planned for Hyderabad, with metro along entire Outer Ring Road. All metro corridors are scheduled to terminate at Shamshabad, near Rajiv Gandhi International Airport, as planned in Hyderabad Metro Rail Phase-II. In August 2019, KT Rama Rao said that state cabinet has approved the Hyderabad Metro Airport Express Link from Raidurg to the airport.
Current status
Construction phases
The construction work was undertaken in two phases. There are six stages of completion in Phase I.Phase I
Phase I of the project includes 3 lines covering a distance of around. The metro rail line between Nagole and Secunderabad was originally scheduled open by December 2015; it was partly opened on 29 November 2017 with a new completion date of December 2019. A -long green line in the old city will pass through Dar-ul-Shifa, Purani Haweli, Eitebar Chowk, Volta Hotel, Sultan Shahi, Syed Ali Chabutra, Shamsheer Gunj, Moghalpura, Hari Bowli, Shah-Ali-Banda and ends at Falaknuma. This stretch is scheduled to be completed by 2022.- Line 1 - Red Line - Miyapur – LB Nagar - 27 stations
- Line 2 - Green Line - JBS - Falaknuma 15 stations
- Line 3 - Blue Line - Nagole – Raidurg - 24 stations
Construction schedule
Phase II
The Government is planning second phase of metro rail extending further. The construction of Phase II will be taken up solely by the state government, instead of Public Private Partnership mode in Phase I. Delhi Metro Rail Corporation was entrusted to give a detailed project report for Phase II. Metro Rail Phase II expansion plan is for about 62 km, which includes providing link to Shamshabad RGI Airport. In February 2020, Hyderabad Metro MD NVS Reddy said that three corridors are considered for phase 2. The DPR has been submitted to state government. The proposed routes are as following:Target Section | Distance | Line | Line Colour | Status |
Raidurg–Gachibowli –Shamshabad RGI Airport | Line IV | TBA | DPR submitted | |
Nagole–LB Nagar | Line III extension | Blue | DPR submitted | |
Lakdi ka pul–BHEL | Line V | TBA | DPR submitted |
Hyderabad Airport Metro Express
In August 2019, TRS Working President, Minister for Municipal Administration & Urban Development, Industries and IT&C K. T. Rama Rao said that the work on Hyderabad Metro Airport Express from Raheja Mindspace to Shamshabad RGI Airport will start soon. The 31 km long Hyderabad Metro Airport Express link will cost around 5000 crore. The 31-km Airport Express Metro Corridor is proposed to have 27-km elevated, 1 km on ground and a 2.5-km underground section to connect to the airport terminal. The airport route will have 9 elevated stations and one underground station.# | Station Name |
1 | Bio-Diversity junction |
2 | Nanakramguda |
3 | Narsingi |
4 | TS Police Academy |
5 | Rajendranagar |
6 | Shamshabad |
7 | Airport Cargo station |
8 | RGIA Terminal |
Lines
Since the first version of the plans, the three corridors mostly remained the same, but minor changes were introduced. These include the lack of stop at Lalaguda, or a stop at Lakdikapul instead of Secretariat. Also, the lines have been marked with several different combination of color. Ameerpet- LB Nagar metro stretch opened on 24 September 2018. HiTec City to Raidurg, 1.5-kilometre stretch on Corridor Three - Nagole to Raidurg, is opened on 29 November 2019, as it involves construction of 49 pillars and the Raidurg terminal station.Red Line: Miyapur – L.B. Nagar
Route Length —Number of Stations — 27
Link to other Corridors
- At Ameerpet – Connecting Corridors 1 and 3
- At Mahatma Gandhi Bus Station – Connecting Corridors 1 and 2
# | Station Name | Connections |
1 | Miyapur | - |
2 | J.N.T.U College | - |
3 | K.P.H.B. Colony | - |
4 | Kukatpally | - |
5 | Balanagar | - |
6 | Moosapet | - |
7 | Bharatnagar | - |
8 | Erragadda | - |
9 | ESI Hospital | - |
10 | S.R Nagar | - |
11 | Ameerpet | Blue Line |
12 | Punjagutta | - |
13 | Errum Manzil | - |
14 | Khairatabad | - |
15 | Lakdi-ka-pul | - |
16 | Assembly | - |
17 | Nampally | - |
18 | Gandhi Bhavan | - |
19 | Osmania Medical College | - |
20 | MG Bus Station | Green Line |
21 | Malakpet | - |
22 | New Market | - |
23 | Musarambagh | - |
24 | Dilsukhnagar | - |
25 | Chaitanyapuri | - |
26 | Victoria Memorial | - |
27 | L.B. Nagar | - |
Green Line: JBS – Falaknuma
Route Length —Number of Stations — 14
Link to other Corridors
- At Mahatma Gandhi Bus Station – Connecting Corridors 2 and 1
# | Station Name | Connections |
1 | JBS Parade Ground | - |
2 | Secunderabad West | - |
3 | Gandhi Hospital | - |
4 | Musheerabad | - |
5 | R.T.C. Cross Roads | - |
6 | Chikkadpally | - |
7 | Narayanguda | - |
8 | Sultan Bazaar | - |
9 | M.G. Bus Station | Red Line |
10 | Salarjung Museum | - |
11 | Charminar | - |
12 | Shah-Ali-Banda | - |
13 | Shamsherganj | - |
14 | Falaknuma | - |
Blue Line: Nagole - Raidurg
Route Length —Number of Stations — 23
Link to other Corridors
- At Ameerpet – Connecting Corridors 3 and 1
- At Parade Ground – Connecting Corridors 3 and 2
# | Station Name | Connections |
1 | Nagole | - |
2 | Uppal | - |
3 | Stadium | - |
4 | NGRI | - |
5 | Habsiguda | - |
6 | Tarnaka | - |
7 | Mettuguda | - |
8 | Secunderabad East | - |
9 | Parade Ground | Green Line |
10 | Paradise | - |
11 | Rasoolpura | - |
12 | Prakash Nagar | - |
13 | Begumpet | - |
14 | Ameerpet | Red Line |
15 | Madhura Nagar | - |
16 | Yousufguda | - |
17 | Jubilee Hills Road No. 5 | - |
18 | Jubilee Hills Check Post | - |
19 | Peddamma Temple | - |
20 | Madhapur | - |
21 | Durgam Cheruvu | - |
22 | Hitec City | - |
23 | Raidurg | - |
Depots
Hyderabad Metro currently has 2 operational depots. Miyapur and Uppal depot land is 100 acres each. The proposed Falaknuma depot will be constructed in 17 acres.Reception
The Metro has opened to overwhelming response, with over 200,000 people using it on Day 1. On the first Sunday of operations, the Metro was used by 240,000 people. As of October 2019, the daily ridership is about 400,000. Although there was hiccups in the beginning of operations in 2017 with meager ridership of less than 100,000 per day, opening the new lines to LB Nagar and Hi-Tech city in 2018–19, ridership has surged and reached milestones from 2 to 4 lakhs in very short duration.Trains are initially being operated at a frequency of 3 minutes in very peak hours and every 5 minutes in peak hours and 4 minutes in peak hours, though maximum achievable frequency is every 90 seconds. Similarly, three-car trains are being used currently, though it is planned to use six-car trains in the future.
In December 2017, Hyderabad Metro Rail launched its mobile app, TSavaari. Hyderabad Metro timings are available on T-Savari app. Ola Cabs and Uber tied up its services with app.
Hyderabad Metro Rail crossed 100 million cumulative ridership milestone in just 671 days.
Cost
The initial official estimated cost of the 72 km long Metro project stood at. The State Government decided to bear 10% of it, while L&T was to bear the remaining 90% of the cost. The construction work which was supposed to commence on 3 March 2011 commenced in 2012. In March 2012, the cost of the project was revised upwards to. This has been further revised upwards to .Infrastructure
The 71.3 km standard-gauge network will feature ballastless track throughout and will be electrified at 25 kV AC 50 Hz. An operations control centre and depot are constructed at Uppal. At some places, a flyover, underpass and metro has been constructed at the same place, as part of Strategic road development plan. L&TMRHL built real- estate projects like Next Galleria malls in Panjagutta, Irrum Manzil, Hitech City and Musarambagh with skywalks, for generating non-fare revenues under Transit Oriented Development. In 2019, Hyderabad Metro started a semi-naming policy of metro stations, awarded through an open e-tendering process, to generate non-fare revenues.CBTC Technology
At the end of 2012, L&T Metro Rail awarded Thales a Rs 7.4bn contract to provide CBTC and integrated telecommunications and supervision systems on all three lines. Thales Group supplied its SelTrac Communications-based train control technology, and trains initially run in automatic train operation mode with minimum headways of 90 seconds, although the system will support eventual migration to unattended train operation.and Goibibo.
Rolling stock
On 12 September 2012, Larsen and Toubro Metro Rail Hyderabad Ltd announced that it has awarded tender for supply of rolling stock to Hyundai Rotem. The tender is for 57 trains consisting of 171 cars which will be delivered in phases at least 9 months before the commencement of each stage. On 2 October 2013, LTMRHL unveiled its train car for Hyderabad Metro. A model coach which is half the size of the actual coach, was on public display at Necklace Road on the banks of Hussain Sagar in the heart of Hyderabad. The trains will be 3.2m wide and 4m high. There will be 4 doors on each side of each coach.On 10 April 2014, the first metro train for HMR rolled out of Hyundai Rotem factory at Changwon in South Korea and reached Hyderabad in May 2014. On 31 December 2014, Hyderabad Metro Rail successfully conducted a training run in Automatic Train Operation mode for the first time between Nagole and Mettuguda.
Ticketing and recharge
The L&T Hyderabad project has an automated ticketing system with features such as contactless smart card based ticketing, slim automatic gates, payment by cash and credit/debit card, passenger operated ticket vending machine and provision of common ticketing system. It also have a provision of NFC-based technology to enable usage of mobile phones as fare media and high performance machine to avoid long queues. Hyderabad Metro Rail smart card acts as a virtual wallet that facilitates seamless travel. A smart card can be purchased from a ticketing office at any Hyderabad Metro station or through TSavaari App. A smart card can be recharged for a minimum amount of 50 and maximum amount of 3000. The smart card can be recharged through TSavaari App, HMR Passenger website, or Paytm App. There is 10% discount on all trips made through smart card. In December 2019, Hyderabad Metro started cashless QR code payment option for e-tickets through MakeMyTrip and Goibibo.Samsung Data Systems India, a subsidiary of South Korean firm Samsung, has been awarded the automatic fare collection system package for the L&T metro rail project. The package involves design, manufacture, supply, installation, testing and commissioning of the system.
Official Ticket prices were announced on 25 November 2017. The base fare is 10 for up to 2 km.
Slab | Distance | Metro Fare |
1 | 0 - 2 | 10 |
2 | 2 - 4 | 15 |
3 | 4 - 6 | 25 |
4 | 6 - 8 | 30 |
5 | 8 - 10 | 35 |
6 | 10 - 14 | 40 |
7 | 14 - 18 | 45 |
8 | 18 - 22 | 50 |
9 | 22 - 26 | 55 |
10 | > 26 | 60 |
In popular culture
- 2018 Telugu film Devadas starring Nani and Rashmika Mandanna, was the first film to be shot in Hyderabad Metro.