Honolulu Rail Transit


The Honolulu Rail Transit Project is an urban rail rapid transit system under construction in Honolulu County, Oahu, Hawaii, U.S. The mostly-elevated system features design elements from both heavy rail systems and light metros, with a commuter rail-like design incorporated into trains and suburban stations. It will become the first large-scale publicly run metro system in the United States to feature platform screen doors and driverless trainsets. The first phase of the project, linking East Kapolei on the ʻEwa Plain and Aloha Stadium, is scheduled to open in late 2020. Its second phase continuing the line across urban Honolulu to Ala Moana Center is due to open in December 2025.
For more than 20
years, debate over the development of a rail system in Honolulu has been a major point of contention in local politics, especially leading into the 2008, 2012, and 2016 election cycles. Proponents of the system say it will alleviate worsening traffic congestion, already among the worst in the United States. They assert that the urban agglomeration in south Oahu is ideally suited to rail as it is constrained by mountains to a narrow strip along the coast, which will be well served by a single rail line. On the opposite side, freeway advocate Panos Prevedouros questions its cost effectiveness compared to alternatives and claims that it will have marginal impact on future congestion and that new roads will therefore still be required. The rest of the rail opponents mostly object to its cost.
The project is financed by a surcharge on local taxes as well as a $1.55 billion grant from the Federal Transit Administration. After major cost overruns, the tax surcharges were extended in 2016 by five years to raise another $1.2 billion; however that additional funding was only sufficient for construction out to Middle Street in Kalihi. The FTA stated that its contribution is contingent to completion of the line all the way to Ala Moana Center and will not be increased. After much wrangling, the state legislature in 2017 approved $2.4 billion in additional taxes to allow the city to complete the project according to the original plan.
Construction of the final section through downtown Honolulu, which is expected to be the most difficult to build, is just starting. The contractor selection process for this section was restarted in September 2017 and is expected to take eighteen months. The first major contract for that section, a $400 million contract to relocate utilities to clear the path of the line, was awarded in May 2018.
The final cost has grown from preliminary projections of $4 billion in 2006 to between $9 billion and $10 billion by 2017. Critics have called for a "forensic audit" to establish the cause of the increase. The tax increase legislation passed in 2017 also requires the State auditor carry out an audit of the project's accounts and to consider alternatives for completing the system.

History

Plans for a mass transit line to connect Honolulu's urban center with outlying areas began in the 1960s, but funding was not approved until 2005. The controversy over the rail line was the dominant issue for local politics leading into the 2008 Honolulu elections, and culminated in a city charter amendment which left the final decision to a direct vote of the citizens of Oahu. Construction of the rail line was approved with 53% of voters in favor, and ground broke on project construction on February 22, 2011.

Previous projects

For more than 50 years, some Honolulu politicians have attempted to construct a rail transit line. In 1966, then-mayor Neal S. Blaisdell suggested a rail line as a solution to alleviate traffic problems in Honolulu, stating, "Taken in the mass, the automobile is a noxious mechanism whose destiny in workaday urban use is to frustrate man and make dead certain that he approaches his daily occupation unhappy and inefficient."
Frank Fasi was elected to office in 1968, and started planning studies for a rail project, named Honolulu Area Rapid Transit, in 1977. After Fasi lost the 1980 reelection to Eileen Anderson, President Ronald Reagan cut off funding for all upcoming mass transit projects, which led Anderson to cancel HART in 1981. Fasi defeated Anderson in their 1984 rematch and restarted the HART project in 1986, but this second effort was stopped in a 1992 vote by the Honolulu City Council against the necessary tax increase.
Fasi resigned in 1994 to run for governor, with Jeremy Harris winning the special election to replace him. Harris unsuccessfully pursued a bus rapid transit project as an interim solution until he left office in 2004. His successor, Mufi Hannemann, began the Honolulu High-Capacity Transit Corridor Project, the island's fourth attempt to build a mass transit system operating in a dedicated right-of-way.

Studies

The City and County of Honolulu Department of Transportation Services released the first formal study related to the HHCTCP on November 1, 2006, the Alternatives Analysis Report. The report compared the cost and benefits of a "fixed guideway system", along with three alternatives. The first expanded the existing bus system to match population growth. A second option called for a further expansion to the bus system, with improvements to existing roads. The third alternative proposed a two-lane flyover above the H-1 freeway between Pearl City and Honolulu International Airport, continuing over Nimitz Highway, and into downtown Honolulu. The report recommended construction of the fixed guideway, and is considered the city's official justification for building a rail line.
A second planning document, the Draft Environmental Impact Statement, studied possible natural and social impacts of the construction and operation of the HHCTCP. The DEIS was completed and cleared for public release by the Federal Transit Administration on October 29, 2008. After minor changes were made to comply with state law, the document was distributed via the city's official project website four days later. The DEIS indicated that impacts of the rail project would include land acquisition from private owners on the route, displacement of residents and businesses, aesthetic concerns related to the elevated guideway, and noise from passing trains.
The city was criticized for timing the release only two days before the 2008 general election. City Councilmember Ann Kobayashi, running as a mayoral candidate against incumbent Hannemann, suggested that the city deliberately withheld key information to early voters who had already cast their ballots for the mayoral candidates, and a city charter amendment related to the project. The anti-rail advocacy group Stop Rail Now criticized the report for not further discussing bus rapid transit and toll lanes, options studied earlier by the city in its Alternatives Analysis.
The third and final official planning document, the Final Environmental Impact Statement, was approved and cleared for public release by the FTA on June 14, 2010. The FEIS addresses and incorporates public comments received regarding the DEIS. The FTA subsequently declared the environmental review process complete in a record of decision issued on January 18, 2011.

Impact on Honolulu mayoral elections

The importance of the Honolulu High-Capacity Transit Corridor Project in the 2008 mayoral election led one observer to describe the vote as a "referendum on rail transit". Two challengers emerged as rivals to incumbent Mufi Hannemann: City Councilmember Ann Kobayashi and University of Hawaii professor Panos D. Prevedouros. Kobayashi supported a "rubber-tired" mass transit system, as opposed to the conventional steel-wheel-on-steel-rail system chosen by the Hannemann administration. Prevedouros, on the other hand, opposed any type of mass transit project, favoring construction of a reversible tollway over the H-1, similar to the Managed Lane option which the Alternatives Analysis studied and rejected as unworkable, and reworking existing road systems to ease congestion. No candidate won a majority of votes in the September 20 non-partisan primary, forcing a runoff between Hannemann and Kobayashi; Hannemann successfully retained his post with 58% of the vote in the November 4 general election.
On April 22, 2008, the Stop Rail Now advocacy group announced their intent to file a petition with the city to place a question on the 2008 ballot to create an ordinance that read: "Honolulu mass transit shall not include trains or rail". Stop Rail Now attempted to submit the petition with 49,041 signatures to City Clerk Denise De Costa on August 5, but was initially denied after De Costa claimed the city charter did not allow the petition to be submitted less than 180 days before a general election, as the wording of the petition called for a special election. Stop Rail Now filed a lawsuit to force the city to accept the petition, and the courts ruled in Stop Rail Now's favor on August 14. Stop Rail Now's petition drive ultimately failed on September 4 when De Costa deemed only 35,056 of the signatures valid, well short of the 44,525 required.
In response to the possibility that Stop Rail Now's petition would fail, the City Council had however voted on August 21 to place a proposed amendment to the city charter on the ballot, asking voters to decide the fate of the project. Mayor Hannemann signed the proposal the following day. The City Council's proposed amendment was not intended to have a direct legal effect on the city's ability to continue the project, but was meant as a means for Oahu residents to express their opinions on its construction. The charter amendment was approved with 53% of votes cast in favor of rail and 47% against. Majorities of voters in Leeward and Central Oahu, the areas that will be served by the project, voted in favor of the amendment, while the majority of those living outside the project's scope in Windward Oahu and East Honolulu voted against it. In mid-2010, Hannemann resigned as major to run for governor and Kirk Caldwell assumed the position of interim mayor.
In the 2016 Honolulu mayoral elections the main three candidates again took opposing views on rail. Honolulu City Council Member Charles Djou, former mayor Peter Carlisle, and incumbent Kirk Caldwell all ran for mayor with the stated goal of finishing rail. However, Republican Djou ran on drastically cutting spending on rail by cutting funding on buying cars on the rail before its completion, and hiring mainland consultants. Kirk Caldwell also stated that spending on rail should be cut, but instead by shortening the rail to end at Middle Street. Carlisle was the only candidate in full support of funding the rail system and stated that rail has gone too far to be stopped. Kirk Caldwell won the election, and promptly went on to adopt Carlisle's position that rail should be completed.

Delays and cost overruns

Construction on the HHCTCP rail line was originally scheduled to begin in December 2009 but did not occur on that date owing to delays in the project review process and delays in obtaining federal approval of the environmental impact statement.
speaking at the project's groundbreaking ceremony
In January 2010, Republican Governor Linda Lingle publicly recommended that the city alter plans for the rail line after news reports on FTA documents where the federal agency raised issues over declining tax revenues in connection with a global economic recession, and commissioned a study by the state to review the project's finances in March. The state financial study, publicly released on December 2, 2010, indicated that the project would likely experience a $1.7 billion overrun above the $5.3 billion projected cost, and that collections from the General Excise Tax would be 30% below forecasts. Then Mayor Peter Carlisle dismissed the study as "damaged goods," and "a pre-determined anti-rail rant." He also pointed to several conclusions as "erroneous" and "inaccurate" before concluding that "spending a third of a million dollars for this shoddy, biased analysis is an appalling waste of our tax dollars." Lingle's Democratic successor, Neil Abercrombie, publicly stated that the financial analysis would not affect his decision to approve or disapprove of the project, saying that the state's responsibility is limited to the environmental review process, and that decisions regarding the project's finances belong to the city and the FTA. Governor Abercrombie subsequently approved the project's final environmental impact statement on December 16, 2010. The Honolulu City Council held a hearing on January 12, 2011 about the state's financial review, but the hearing was not attended by any state officials, who had been invited to testify.
On January 18, 2011, the FTA issued a "record of decision", indicating that the HHCTCP had met the requirements of its environmental review and that the city was allowed to begin construction work on the project. The record of decision allowed the city to begin negotiating with owners of land that will be purchased for the project, to begin relocating utility lines to make way for construction of the line and stations, and to purchase rolling stock for the rail line. A ground-breaking ceremony was held on February 22, 2011 in Kapolei, at the site of the future East Kapolei station along Kualakai Parkway.
In March 2012, Dan Grabauskas was hired on a three year contract as CEO and Executive Director of HART. In 2014 HART CEO Dan Grabauskas blamed lawsuits, launched in 2011, for some of the cost overruns after bids to construct the first nine stations exceeded the budget by $100 million. His claims were disputed by the plaintiffs in one of the cases who said HART could have put the stations out to tender and that HART had deliberately delayed the legal proceedings so a judgement would only be delivered after a significant proportion of the line had been completed.

Burial issues

Like most major infrastructure work in Hawaii, construction of the rail line is likely to uncover historic human remains, notably in its downtown Honolulu section. The Oahu Island Burial Council refused to sign a programmatic agreement on October 21, 2009, over concerns about likely burial sites located along the line's proposed route over Halekauwila Street in Kakaako. Three construction projects in the area since 2002 have each encountered unforeseen human remains that led to delays, and archaeologist Thomas Dye stated, "The council is absolutely right that you should expect to find burials on Halekauwila Street".
The Burial Council's core contention is the city's decision to conduct an archaeological survey of the rail line's route in phases, meaning construction on a majority of the line will be complete by the time the survey in the Kakaako area is performed, which in turn increases the likelihood that any remains discovered will be moved instead of being allowed to remain in situ. In response to the Burial Council's concerns, the city agreed to begin conducting an archaeological survey of the area in 2010, two years earlier than originally planned. The state Department of Land and Natural Resources later signed the city's programmatic agreement on January 15, 2011, over the continuing concerns of the Burial Council.
The city's decision to conduct the archaeological survey in phases subsequently led to a lawsuit filed on February 1, 2011, by the Native Hawaiian Legal Corporation on behalf of cultural practitioner Paulette Kaleikini. The suit, which named both the city and the State of Hawaii as defendants, contended that state law requires the full length of the rail line to have an archaeological survey conducted before any construction takes place, and seeks to void the environmental impact statement and all construction permits issued for the project. Kaleikini's lawyers filed on February 18 a request for an injunction to stop work on the project until the case is resolved. The suit was initially dismissed on March 23, 2011, after Circuit Court Judge Gary Chang ruled that state and federal laws allow the archaeological surveys to be conducted in phases. Kaleikini's lawyers subsequently appealed to the Hawaii Supreme Court, which heard oral arguments in the case on May 24, 2012. The court ruled on August 24, 2012, that it agreed with plaintiff Kaleikini that the archaeological survey needed to be completed before construction could take place, and that the State Historic Preservation Division did not comply with state law when it approved the project. The case has now been remanded to Circuit Court. On December 27, 2012, the United States District Court for the District of Hawaii granted the plaintiffs' injunction, and ordered that all construction-related activities in segment 4 of the archaeological survey be halted until compliance with the Hawaii Supreme Court decision made earlier this year is met. This ruling does not affect construction activities in the first three segments, nor does it affect construction planning, design, or engineering in segment 4, which is the final segment to be built. The Phase 4 area encompasses the downtown area and its immediate environs, including Chinatown, Mother Waldron Park, and Beretania Street. Judge Tashima, the only sitting judge on the case, ruled on condition of the injunction that the city is required to file periodic status updates on their compliance with the judgment. The injunction will then terminate 30 days after defendants file a notice of final compliance.

Social impact

The development of this project has been a point of contention among environmental, indigenous, and residential interest groups, as the United States Department of Transportation is accountable for nationwide compliance with Title VI of the Civil Rights Act of 1964. Specifically, residents of the North Shore, Wai‘anae Coast, and Central and East regions of Oahu, home to mostly middle and lower-class communities, as well as those of mostly upper class Hawaii Kai and Windward Oahu, pay the higher excise tax without reaping the direct benefits of the Rail Transit project. Indigenous Hawaiians constitute large percentages of the communities scattered along the southwest coast of the island, where residents generally exist under the national poverty line, but the project may possibly serve wealthier, “local” Hawaiian residents while bypassing the poorer indigenous Hawaiian community. Numerous studies have identified various benefits, including increased home values and increased median household income, that fall upon residences located near a rail transit station; public transit implementation thus constitutes a measure of public and private investment in a community.

Financing

Initial General Excise Tax (GET) surcharge

After winning the 2004 election, Hannemann announced that construction of a rail line was an administration priority. The following May and upon prompting by the city, the Hawaii State Legislature passed a bill to allow counties a one-half percent increase in the Hawaii General Excise Tax, from 4% to 4.5%, to fund transportation projects. According to the bill, increased revenue would be delivered to counties implementing the raised tax to fund general public transportation infrastructure throughout Hawaii, and to pay for mass transit in the case of the City and County of Honolulu. Money collected from the initial 4% GET would remain state revenue.
Republican governor Linda Lingle initially threatened to veto the bill, believing that money destined for county governments should be collected by the individual counties. After compromising with legislative leaders and Mayor Hannemann, however, she allowed the bill to become law. On July 12, 2005, the bill was enacted as Act 247 of the Session Laws of Hawaii 2005, without the Governor's signature. A month later, the Honolulu City Council authorized the one-half percent GET increase, and Hannemann signed the measure into law on August 24. Act 247 required Honolulu to use the funds only for the construction and operation of a mass transit system, and barred its use for public roads and other existing transit systems, such as TheBus. Since no other county authorized the excise tax increase before the deadline of December 31, 2005, the Hawaii GET remains at 4% for Hawaii's three other counties. The increase went into effect on January 1, 2007, and was due to expire on December 31, 2022.
The Legislature considered a bill in the 2009 legislative session that would have redirected income from the half-percent increase back to the state to offset a $1.8 billion projected shortfall in the following three fiscal years. The bill was opposed by Mayor Hannemann and other city leaders who believed that redirecting the money would jeopardize federal funding for the project, and was eventually dropped after U.S. Senator Daniel Inouye indicated to the Legislature that he shared the city's concerns.

GET surchange extensions and "Hotel Tax" surcharge

In January 2016 the Council extended the GET for another five years to add $1.2 billion in funding to cover a budget blowout. The Council also required that the money raised by the extension go into a contingency fund and to pay for disability access to the system. HART was required to provide quarterly financial reports to the Council.
On September 1, 2017 the Legislature, after meeting for a week in a special session on rail financing, approved further taxes to raise $2.4 billion for the project. The taxes include a further three-year extension to the 0.5 percent General Excise Tax surcharge, which will now expire in 2030, and a thirteen-year, 1.0 percent surcharge on the existing 9.25 percent statewide Transient Accommodation Tax which is charged to tourists. Efforts to pass a funding bill in May 2017 had failed and the impetus for the special session was a FTA deadline of September 15 for a funding plan to cover the shortfall. The bill also grants the state government oversight over the project including the appointment of two non-voting representatives on the HART board and calls for an audit of HART by the state auditor. It was signed into law by the governor on September 5.

Federal Transit Administration's request for recovery plan

In mid 2016 the FTA requested that HART develop a "recovery plan" by August 7, 2016. Also in June a separate report by Jacobs Engineering, the project management contractor, said under a worst-case scenario the final cost would $10.79 billion.
In January 2017 group called "Salvage the Rail" published a plan, based on Option 2A from six alternatives proposed by the FTA to HART in 2016, that would terminate the elevated section at Middle Street and run at street level to the terminus along a route one block inland from the HART plan. The system would need to be reconfigured to use new driver-operated low floor vehicles, lowering the platforms on the stations already constructed. Proponents say it would save $3 billion and four years of construction, as well as avoid disturbing burial sites under the downtown area.
After a lodgement extension was granted by the FTA, HART submitted its recovery plan in April 2017 which concluded that completion of the original 21 station route was the only viable option. An alternative "Plan B" to build only 14 stations within the already funded $6.5 billion budget, was ruled out because of lower ridership, legal risks, insufficient contingency and other reasons. The new project cost was $8.165 billion with media reports indicating that after financing charges are included it could be over $10 billion. An updated schedule for opening said the section from East Kapolei to Aloha Stadium will open at the end of 2020 and operation of the full route by December 2025.
In September 2017 HART submitted an updated recovery plan to the FTA with a new estimate price of $9.02 billion. The plan still includes $8.165 billion in construction costs, but has reduced financing costs of $858 million following state legislation granting both prolonged and new taxes to fund the project. The State Auditor has been tasked to consider alternatives for completing the system, as part of its audit of HART. As of January 2018 the FTA has not formally accepted the new recovery plan but has asked HART for more details including how it came up with its tax-revenue forecasts.
In February 2019, the FTA served HART with two subpoenas. The first asked the agency to send investigators documents relating to its real estate acquisition program. HART said some of the documents show it overspent on relocating residents and businesses along the rail route, which may have cost up to $4 million. The second sought the minutes from all board of directors meetings from 2011 through 2018, including the board-members’ private discussions in executive sessions.
In September 2019, the FTA accepted the recovery plan.

Route

The project constructs an almost entirely elevated rapid transit line from the eastern edge of Kapolei, near the University of Hawaii-West Oahu campus, to Ala Moana Center. The line passes through communities along southern Oahu, via Honolulu International Airport and downtown Honolulu. It will have twenty-one stations and run from Kapolei to Honolulu, passing through Waipahu, Pearl City, Waimalu, Aiea, and Halawa. Originally, the line was to fork near Aloha Stadium into two routes, one passing further south via Honolulu International Airport, and the other through Salt Lake, before reuniting at Middle Street in Kalihi. The city council initially decided to build the Salt Lake route before the airport route, as a result of horse-trading with City Councilmember Romy Cachola, whose constituents included Salt Lake residents and whose vote was needed to pass the decision. After the city charter amendment on rail transit passed, the City Council reconsidered the decision, and decided to re-route the rail line to pass by Pearl Harbor and the airport, without a Salt Lake alignment. The airport route is 4% more expensive, but is expected to have significantly higher ridership since it will ferry workers to both the airport and the Pearl Harbor military base. The only at-grade trackage will be a section near Leeward Community College.
, the western portion of the line is scheduled to open in late 2020, and the full line is scheduled to open in late 2025. The project is divided into four segments or sections, with overlapping construction periods and revenue service dates.
The long term plan includes four extensions: two extensions east, from Ala Moana Shopping Center to the University of Hawaii-Manoa campus and to Waikiki, one extension west from East Kapolei to Kalaeloa, and the link through Salt Lake which was dropped from the initial plans. In 2010 it was estimated the extensions could be completed after the initial four-section project, possibly as early as 2030. None of these extensions is currently funded, but in November 2017 the rail authority took a first step towards preserving a corridor for the extension between Ala Moana Center and the University of Hawaii at Manoa.
When complete, the trains will carry more than 6,000 people per hour, from 4 am to midnight. It is estimated the trains will serve 119,600 daily riders.

Design

On October 21, 2009, the city announced Kiewit Pacific Co. had won the $483 million contract to build the first two sections of the line, bidding $90 million under the expected price. The stations were tendered separately.
The construction of the rail line started from suburban areas in Kapolei and Ewa, and progresses east towards the urban center in Honolulu. There will be 112 columns from East Kapolei to Ewa. The choice to start from Kapolei was made because the first phase must include a baseyard for trains, which is more cheaply built away from the center, and also because the city chose to delay construction in the urban center to later phases of the project due to associated major impacts to existing infrastructure and unpopular traffic delays.
To speed construction, the elevated trackway is built using precast concrete box girder bridge segments. This method was first used for MARTA in the 1980s. The trackway was designed by FIGG Bridge Engineers and HNTB. It is supported on single piers, each in diameter at the base and high, flaring at the top to support the lower section of the box girder; the piers are themselves supported by drilled shafts from in diameter.
Casting of the box girder segments began in 2014 at a rate of 13 segments per day; in total, 5,238 segments will be required for the first phase. The segments are cast locally in Kalaeloa. Each segment weighs and measures , and the deck ranges in thickness from. Once the piers were erected, a pier bracket ram was placed and a launching gantry was used to bridge the span between adjacent piers; a deck-mounted crane lifted the precast segments onto the gantry, which supported them while they were tensioned together. In total, 430 of the 438 spans in Phase 1 were assembled using precast box girder segments, at an average rate of 1 to 2 days per span.
in 2015
For the eight long spans required to bridge the / Waiawa interchange in Pearl City, a balanced cantilever construction method was used instead. This covers the segments from Pier 252 to Pier 256. Instead of precast segments, Kiewit used segments cast in-place, starting from the piers set in the freeway medians and working towards adjacent piers. The yellow-painted traveling forms at each end were used to cast each segment, then moved to the fresh end to cast the next segment. Each segment required of rebar and of concrete, and weighed. 73 segments were required. The final pour for the balanced cantilever was performed in September 2016.

The third section of the route to be completed is the Airport section east from Aloha Stadium to Middle Street that includes four stations, including the Honolulu International Airport station. AECOM won the contract to design the Airport section in 2012 with a $38.8 million bid. The construction contract was awarded to a joint venture of Shimmick-Traylor-Granite in August 2016, who bid $874.8 million; construction started in December 2016.
The Airport section consists of 214 total spans which are also being constructed using precast concrete box girder bridge segments, like the earlier Farrington and Kamehameha sections, but for the Airport section, the segments are lifted and supported by an overhead gantry crane while they are tensioned. Both a conventional overhead gantry and an articulating gantry are being used during the guideway assembly. More than 2700 precast segments are required for the Airport section, which also includes more than 230 columns for the piers and 5400 permanent sound walls. For the pier foundations, shafts up to deep were drilled. Where the guideway contacts the supporting piers, custom bearings have been installed to accommodate movement ranging from and rotation of 0.015–0.03 radians.
The fourth and final segment of the route, the City Center section terminating at, may be completed under a public-private partnership. It is estimated the City Center section will cost $1.6 billion to complete. Under the proposed public-private partnership, the City Center section will be procured under a design-build-finance-operate-maintain contract, which will award the successful bidder the right to operate and maintain the entire system for a period of 25 years after completing the City Center section. The City of Honolulu would retain oversight over operations and maintenance, public information, and responsibility for fare vending and enforcement. A contract for $400 million was awarded to clear utilities in the City Center section in May 2018.

Stations

Local construction company Nan, Inc. won contracts to build six of the nine western stations in 2015; the West Oahu Station Group contract was worth $56.1 million, and the Kamehameha Highway contract was worth $116 million. The Farrington Highway Station Group contract was awarded in 2015 to Hawaiian Dredging for $79 million. The STGJV were awarded the contract to build the four Airport section stations as part of their $875 million contract for the Airport section.
The Hawaiian Station Naming Working Group, an expert working group, was named by the Honolulu City Council Resolution 09-158 on April 29, 2009 to develop Hawaiian names for each station of the Honolulu Authority for Rapid Transportation system. HSNWG proposed Hawaiian names for the nine rail stations on the Ewa end of the rail system in November 2017, and HART adopted the proposed names on February 22, 2018. On April 17, 2019, HART released a list of Hawaiian names proposed by HSNWG for the remaining 12 rail stations on the eastern end of the rail system, between Pearl Harbor and Ala Moana Center. The 12 names were released for public comment, and the HSNWG will review comments before presenting a final list of names to the HART Board of Directors.

Rail Operations Center

The Rail Operations Center is the railyard, operations, and maintenance facility, divided into four buildings. It is in Pearl City, between the campuses of Leeward Community College and Waipahu High School, just west of. The design has been awarded LEED Silver certification.
The buildings on the ROC campus are:
The contract for the ROC was awarded to the Kiewit/Kobayashi Joint Venture in 2011. The contract was initially awarded at a cost of $195 million; when the ROC was completed in July 2016, the actual incurred costs were $274 million.

Rolling stock

The line will use four-car train sets, each with the capacity to carry about 780 passengers, similar in weight to light rail systems elsewhere in the United States, as opposed to heavier, and thus more expensive, lines found on rapid transit systems like the subways and elevated systems of Chicago and New York City. However, the stations will be standalone structures and will be substantially bigger than typical light rail stations. Physically, the Honolulu system will have a good deal in common with light rapid transit systems such as SkyTrain in Vancouver, British Columbia or the Copenhagen Metro, as well as the Docklands Light Railway in London. The system will be the first metro system in the United States to feature platform gates and will be driverless.
Rolling stock for the line will initially include 80 cars in 20 four-car train sets.
Each car will be long, weigh, and have 36 seats with a listed total capacity of 195 people. The cars will be powered by a third-rail electrification system.

Contract and delivery

The contract for the rail cars was signed on November 28, 2011 by HART and Ansaldo Honolulu, a joint venture between AnsaldoBreda and Ansaldo STS. AnsaldoBreda and Ansaldo STS previously collaborated on the construction and operation of vehicles for the Copenhagen Metro and the Brescia Metro. Both companies were later purchased by Hitachi Rail in 2015 and Ansaldo Honolulu was subsequently renamed to Hitachi Rail Honolulu. Under the $1.4 billion contract, HRH is responsible for designing and fabricating the rail cars, a test to validate train performance, and operations and maintenance during the first five years of revenue service, with an option to continue O&M services for HART for an additional five years provided the review of the first five years is favorable.
The two unsuccessful bidders for the rail car contract, Bombardier Transportation and Sumitomo Corporation of America, filed protests over the award. Both protests were rejected during the administrative process, but Bombardier sought judicial review of their bid protest. The administrative decision against Bombardier's protest was affirmed by both the state Circuit Court and the Intermediate Court of Appeals.
The first two cars arrived in Hawaii in March 2016, and the first train was unveiled to the public at the Rail Operations Center on May 2, 2016. To meet "Buy America" requirements for federally-subsidized transit projects, the bodyshells are fabricated at the Hitachi Rail Italy plant in Reggio Calabria, Italy, then shipped to HRI's Pittsburg, California plant for final assembly. The Pittsburg factory has since been partially leased to Bombardier Rail, who will assemble cars for BART there.
In December 2016, Hitachi Rail Italy reported defects were discovered in the welds in the extruded aluminum beams of twenty-seven car shells, four of which were already in Hawaii. The manufacturer will fix the problems, but warned delivery may be delayed as production of new vehicles will be halted. In March 2017 HART said they would meet the interim opening needs after repair of the defective cars and that full opening would not be affected.
In May 2017 trains were towed on tracks in Honolulu for the first time, to check clearances. Testing of trains under their own power commenced in October 2017.

Timeline of progress