First Jordan Hydro-Electric Power House


The First Jordan Hydro-Electric Power House, also known as the Rutenberg Power Station or the Naharayim Power Plant or the Tel Or Power Plant, was a conventional dammed hydroelectric power station on the Jordan river, which operated between 1932 and 1948. It was situated in the Emirate of Transjordan, but built to supply power to Mandatory Palestine. The plant was built in an area known as Jisr el-Majami, later renamed by the Palestine Electric Corporation as Naharayim, and following the Israel–Jordan peace treaty it is today part of the Jordanian area of Baqoura.
The plant was constructed – under concession from the Mandatory government – by Pinhas Rutenberg's Palestine Electric Corporation, based on a plan put forward in 1926. It followed his original 1920 Rutenberg plan to build ten reservoirs and fourteen hydroelectric plants on the Jordan river. Financial capital for the project came from the worldwide Jewish community, organized with limited publicity in order to allow Rutenberg to be presented as an "entrepreneur" rather than part of the Zionist Organization.

Concession

On 8 December 1920, Pinhas Rutenberg submitted a 60 page proposal to the British government, proposing to build 14 hydroelectric power stations along the Jordan River On 21 September 1921, a concession agreement was signed between the British Government and Rutenberg granting him a monopoly over "utilization of such of the waters of the River Jordan and its basin including the Yarmuk River and all other affluents" and a right to "erect a power house near Jisr-el-Mujamyeh". This agreement required Rutenberg to form a company with at least GBP1 million of capital within two years; such company was formed, named the Palestine Electric Corporation. The concession was then formalized on 5 March 1926 for a 70-year period and validated in Mandatory Palestine by the Electricity Concessions Ordinance 1927 and in the Emirate of Transjordan by the Electricity Concession Law, 1928.

Construction

The plant was constructed between 1926 and 1933. About 3000 workers were employed during the construction. Rutenberg's original proposal explained that the location near Jisr el-Majami was the only site on which it was "possible to begin construction of a powerhouse immediately", due to the required proximity to the Sea of Galilee and because it represented the location which had been most densely settled by Jews. The choice of the location influenced the ongoing Anglo-French discussions over the location of the mandatory borders, which became the Paulet–Newcombe Agreement. A similar dynamic appeared in the finalization of the eastern border with respect to what became known as the "Semakh triangle".

Operation

The plant operated between 1932 and 1948. The opening ceremony took place on 9 June 1932, attended by Emir Abdullah I of Jordan and British officials including the High Commissioner Arthur Grenfell Wauchope, Colonel Charles Henry Fortnom Cox, and Sir Steuart Spencer Davis.
The plant ceased operations following the 1948 Arab-Israeli war. It was captured and looted by the Iraqi Army on 14 May 1948. Transjordan had a secret agreement with Israel regarding protection of the works. United States Chargé d'affaires Wells Stabler reported in a confidential despatch that when the Iraqi army arrived, the Israeli operators of the plant blew up some of the electricity generators in the plant and the plant was subsequently looted by the Iraqi troops. Thirty-eight workers were captured; they were released only after the Armistice Agreements were signed on 3 April 1949. Stabler's despatch on 11 July 1949, written after a visit to the site, read:
It is understood that prior to the hostilities In May 1948, the Jordan Government and the Jewish Agency reached some form of agreement concerning the protection of the Hydro-Electric works. It is possible that the Jordan Government would have been able to observe this agreement if it had not been for the arrival of the Iraqi forces. When the Iraqi forces came into the area, the Israelis departed, but only after blowing up certain of the dynamos in the main dynamo building. Later the Iraqi finished the job, even removing numerous machines.... The area has been under the control of the Arab Legion since the departure of the Iraqi troops three months ago. All looting and damage has been stopped by the Legion and the area is under guard.... It is quite obvious that the Rutenberg Hydro-Electric works can only be operated again by an agreement between Jordan and Israel. Jordan, on its part, is incapable of operating such a works by itself and, moreover, the Israelis can control the flow of the Jordan. Israel, on the other hand, cannot commence operations of the works as all the buildings are in Jordan territory. In addition, Jordan can control the flow of the Yarmuk River. It would appear that it would take some time yet to reach an agreement on the operation of the Rutenberg Hydro-Electric works as it remains, along with the Dead Sea Potash Works, an important bargaining point for Jordan.

Proposals to reopen

Various proposals were made for cooperation between Israel and Jordan regarding the use of the Jordan river in the wake of the 1948 war. After armistice agreement was signed PEC executives proposed to open the plant but the Jordanian king refused. Proposal to apply the seven-state Tennessee Valley Authority scheme to the area was submitted to the United Nations in 1953, stating: