Evergreen Extension


The Evergreen Extension is a long extension of the Millennium Line of Metro Vancouver's SkyTrain rapid transit system. The extension runs from Lougheed Town Centre in Burnaby to Lafarge Lake–Douglas in Coquitlam and included six new SkyTrain stations and an upgraded existing station on the Millennium Line. It began operations on December 2, 2016.
Since the extension opened, the Millennium Line has operated between VCC–Clark and Lafarge Lake–Douglas. In 2012, the extension was expected to serve 70,000 passengers per day by 2021.

History

A rapid transit extension to Coquitlam was intended to be phase II of the new Millennium Line that was completed in 2002. As the costs of the project rose, however, plans to extend the line into Coquitlam were halted, though not before a third incomplete platform on the westbound side of the Lougheed Town Centre station was built, with a spur of tracks for the extension.
After completion of the Millennium Line, TransLink undertook several studies regarding the fate of the extension, considering a variety of possible options, including a diesel multiple unit-based railway, a streetcar line, a new SkyTrain line, and an express bus service. In September 2002, the 97 B-Line express bus service was launched. In 2004, it was decided that a streetcar line was the best option, as it would better blend in with the neighbourhood, cost less, better fit ridership patterns, and not compete with customers from the existing West Coast Express.
Detailed design began in October 2006, when the TransLink Board approved the Evergreen Light Rail Transit project definition phase. Despite a series of public consultations held during this period, in a community update issued May 2007, TransLink summarized the state of the project as follows:
This statement prompted local news agencies to assume TransLink had shelved the project. TransLink responded by issuing a subsequent statement on July 19: "The Light Rail Transit system for the Northeast Sector is the number one rapid transit priority for TransLink", TransLink Chair Malcolm Brodie said. "We have defined the project, and now we are waiting for funding to be confirmed from senior levels of government."
On February 1, 2008, the provincial government and TransLink unveiled a revised business case for the Evergreen extension, preferring the Advanced Light Rapid Transit used by SkyTrain over the light rail technology that had been proposed. The expected completion date was pushed back from 2011 to 2014. On April 18, 2008, the Transport Ministry and TransLink announced that of the two routes proposed in the business case, the North West route was selected after consultation with the various municipalities. On August 5, 2008, the provincial government and TransLink agreed on Evergreen Line delivery. On May 4, 2009, the Ministry of Transportation released a Project Description Report for the Evergreen Line. The report provided more information about the scope and characteristics of the proposed line and detailed the project's environmental and socio-economic requirements.
On September 3, 2009, the release of the report on TransLink's 2010 ten-year plan by Martin Crilly, the Regional Transportation Commissioner appointed by the provincial government, indicated that rapid transit expansion, which included the Evergreen Line, was highly unlikely without a predictable source of operational funding. Although he stopped short of offering his opinion on the project, he agreed nonetheless with TransLink that upgrades to the existing system should be prioritized before the construction of the Evergreen Line.
Later that month, the second project update was released by the Evergreen Line Project. The update stated that contractor selection would begin in early to mid-2010, environmental assessment would be completed in 2010, and construction would proceed in late 2010. The update also announced open houses for the environmental assessment process for September 2009 and open houses for preliminary design in October and November 2009. It did not make reference to the funding issues that remained unresolved.
On October 26, 2009, the TransLink Mayors' Council voted against the increased funding necessary to pursue the Evergreen Line, instead voting for keeping existing services as they are. However, on October 28, 2009, Premier Gordon Campbell stated that the project would continue even though it had been voted down.
On October 7, 2011, the Mayors' Council approved the "Moving Forward" 2012 Supplemental Plan to fund various transportation projects in the Metro Vancouver region, including the Evergreen Line. Funding would be provided in part by a two-cents-per-litre increase in the Metro Vancouver fuel tax that was to be implemented in April 2012, with further funding from new sources that had yet to be determined. Of the projected $1.4 billion cost for the Evergreen Line, TransLink would provide $400 million, the provincial government would contribute $583 million, and the federal government would contribute $417 million. Transportation Minister Blair Lekstrom announced that construction was expected to begin in mid-2012, soon after a winning bid for construction had been chosen from three shortlisted builders.
On January 25, 2012, the provincial government announced that pre-construction work would proceed on the line, including the removal of some buildings and the construction of underground utility tunnels.
In May 2012, preliminary construction began, including the removal of some buildings and the construction of underground utility tunnels in certain areas of Port Moody and Coquitlam. At the same time, the province also awarded contracts to widen sections of North Road that were to be affected by construction of the line in the middle of the year.
On July 19, 2012, the Government of Canada, the City of Coquitlam, and Coquitlam Centre Mall reached an agreement to add Lincoln station to the Evergreen Line project, with the federal government contributing $7 million to the public–private partnership.
On October 4, 2012, SNC-Lavalin was chosen as the primary contractor to construct the Evergreen Line.
On December 3, 2012, the provincial government and TransLink signed a contract with Bombardier Transportation to supply 28 SkyTrain cars.
On December 8, 2012, the final early works contract for the Evergreen Line was awarded and was to be completed by March 2013. The statement also promised that the project was still on track for completion in 2016.
On February 5, 2013, Thales Canada announced that it had been awarded a contract by Partnerships BC to install the company's SelTrac communications-based train control.
On March 23, 2013, the final names of the Evergreen Line stations were announced. It was also announced that construction of the Evergreen Line guideway would start in the Burquitlam area of Coquitlam in mid-2013 and continue south to Lougheed Town Centre station. The stations were to be built in the following order:
In October 2014, the elevated guideway section between Lougheed Town Centre station to the South Tunnel Portal was completed. The launching truss was transported to Coquitlam Central station, where crews continued to build the elevated guideway north to Lafarge Lake–Douglas station.
On February 13, 2015, the provincial government announced that the opening of the line would be delayed until late 2016, due to a slower-than-expected tunnel boring process. Any costs associated with the delay would come at no cost to the taxpayers and would instead be covered by the contractor.
In June 2015, the project management team announced that they would begin testing trains between Lougheed station and Burquitlam station in July 2015. In the week of July 6, 2015, testing began.
On November 27, 2015, the provincial government announced that the opening of the line would be further delayed until early 2017.
As of April 2016, the project was 85% complete, including trackwork in elevated and at-grade guideways, guideway construction, tunnel boring, tunnel base, station buildings, and testing between Lougheed and Burquitlam station.
On September 8, 2016, it was announced that the line would be opening before Christmas 2016 but that a concrete date had yet to be set.
On October 22, 2016, Expo Line and Millennium Line route changes took effect to accommodate the Evergreen Extension. The changes, announced on September 19, 2016, were implemented ahead of the Evergreen Extension opening to familiarize riders with the new operating pattern.
On November 7, 2016, TransLink announced that the extension would open on December 2, 2016.

Project funding

Funding for the project was provided from four major groups:
The July 2012 project update gave the following description of the alignment:
From the line's opening until June 24, 2018, trains ran in the direction of left-hand traffic instead of the standard right-hand traffic between Burquitlam and Lougheed Town Centre, and used two switches just south of Burquitlam station to return to normal travelling direction. Normal right-hand running between those two stations commenced on June 25, 2018, in order to reduce delays.

Design

The May 2009 Project Description Report and September 2009 Project Update provided previously unconfirmed details about the Evergreen Line, including the following:
The LRT-based plan foresaw eleven stations. As part of the decision to use ALRT technology, four planned stations were cut: Cameron, Buller, Lansdowne, and Coquitlam Civic Centre.

Stations

Six new stations were confirmed for the opening of the Evergreen Extension:
Two existing SkyTrain stations were upgraded to serve the Evergreen Extension:
The design blueprints showed allowances for two future stations, at Queens Street in Port Moody and Falcon Drive in Coquitlam, should future development warrant their construction, according to the Evergreen Line project office. Also in the design plans was a short spur at Coquitlam Central station, added to allow for a possible future extension of the line to Port Coquitlam.