EuroAsia Interconnector


The EuroAsia Interconnector is a HVDC interconnector between the Greek, Cypriot, and Israeli power grids via the world's longest submarine power cable. Connecting Kofinou, Cyprus to Hadera, Israel and Korakia, Crete, Greece and stated to finish construction in 2023, the EuroAsia Interconnector is a major Project of Common Interest of the European Union and a priority Electricity Highway Interconnector Project, as an energy highway bridging Asia and Europe. Regulatory approval of electricity interconnection between Cyprus and Greece was completed on October 10, 2017. It is a historic decision for Cyprus, ending electricity isolation of the last non-interconnected EU member state.
On October 11, 2019 Minister of Environment and Energy Kostis Hatzidakis on behalf of Government of Greece and Prime Minister pointed out that Greece provides strong political support to the work of Cyprus's electrical interconnection with Greece and Israel as PCI projects, in order to lift Cyprus's electrical isolation and link the island to the European Union's electricity grids. Greek Energy and Environment Minister Kostis Hatzidakis and Israeli Energy Minister Yuval Steinitz, during the 25th UN Climate Change Conference in Madrid, both reiterated their countries’ support in the Israel-Cyprus-Crete electricity interconnection project, the PCI 3.10 EuroAsia Interconnector.
According to ENTSO-E's analysis, the interconnector will contribute to social and economic welfare between €580m and €1.12 billion in each year. ENTSO-E calculated that expected reduction of is between 1.3 and 6.8 million tonnes each year, or between 21% and 110% of total emissions of Cyprus.
On May 12, 2017 the Greek Prime Minister Alexis Tsipras met the State Grid Corporation of China Chairman Shu Yinbiao in Beijing, and CEO Euroasia Interconnector Nasos Ktorides supported the timely implementation of EuroAsia Interconnector. On December 12, 2017 transmission system operator Elia announced the conclusion of a strategic alliance agreement for the development and implementation of the 2,000 MW interconnector.
Former Cyprus Foreign Minister and head of the European Parliament Foreign Affairs Working group Ioannis Kasoulides joined the EuroAsia Interconnector on March 30, 2018 as Chairman of the Strategic Council.
A final call for tenders for the construction of Stage 1 with an estimated budget of €2.5 billion was published on November, 2019 in the Official Journal of the European Union.
On January 10, 2019 EuroAsia Interconnector Ltd, project promoter, issued tender documents for contracts for the design and construction of the EuroAsia Interconnector.
Energy-sector technical engineering recruitment firm Fircroft included the EuroAsia Interconnector as the fourth biggest among 10 major transmission and distribution projects in the world for 2019 and beyond.
On October 28, 2019 project promoter EuroAsia Interconnector Ltd announced the final stage of tenders for the HVDC converter stations of the Euroasia Interconnector. In May 2020 official Project Developer has submitted to the Connecting Europe Facility for the implementation of interconnection.

Energy in Cyprus, Greece and Israel

Energy in Cyprus

as an island is totally isolated from EU energy links and electricity networks and remains the most energy dependent country in the European Union. Cyprus is completely isolated from EU energy interconnections. About 95% of the primary energy use was imported in 2015. Oil and petroleum products represent around 92% of the gross energy consumption. Cyprus has no oil refineries. As a result of high import cost of petroleum products the price of electricity is one of the highest in the European Union.
Renewable energy share has reached 8% and according to national targets should reach 13% by 2020. Recently Cyprus announced discovery of the Aphrodite gas field with significant amounts of natural gas resources in its exclusive economic zone, and additional gas prospects are being explored. Due to regional turmoil in the Eastern Mediterranean region and the fact that 1/3 of Cyprus is unlawfully occupied, for energy security it needs a reliable and robust energy infrastructure. EuroAsia Interconnector will connect Cyprus to the European electricity grid as the last EU member fully isolated from energy interconnections.

Energy in Israel

's relationship with neighbors links politics and diplomacy with energy supply and security. Until recently domestic Israeli primary energy production was small. The country was dependent on imports of oil and coal, so that in 2012 only 13% of its energy balance was supplied from domestic resources. In 2010, the Leviathan gas field was discovered off the coast of Israel. This gas field represents a strategic change enabling Israel not only to be energy independent, but also to become an energy exporter, as the amount of gas discovered exceeds Israeli demands for at least 50 years. Unlike oil, gas is more difficult to ship and is not sold on spot markets, being priced uniquely for each deal. One reliable way for Israel to export natural gas could be in form of electricity using the Interconnector.

Energy in Greece

's location at the crossroads of East and West and geographical connection to rest of Europe enables interconnection and energy flow from Eastern Mediterranean to Europe. Greece is a highly energy dependent country. Renewable energy share has reached 22%. Crete is an energy isolated island and it is the largest isolated power system in Greece. Like all isolated island systems the cost of electricity production is very high due to transportation costs of imported fuel and high operational costs of mainly outdated power generating units. Connected system have much lower costs of electricity by using electricity from distant power stations where electricity production costs are much lower. Crete is electrically isolated from mainland Greece and the Hellenic Republic subsidises the difference in the Crete electricity costs of around €300 million per year.

Eastern Mediterranean Hydrocarbon Findings

The Levantine Sea is bounded by Greece, Turkey, Syria, Lebanon, Israel, and Egypt. Cyprus is the largest island in the Levantine sea and it is located in the middle. Many countries in the region are in disputes with neighbors.
The seafloor of the Eastern Mediterranean Basin is dotted with mud volcanoes which spew gas and occasionally oil into the benthic zone. Geologically it consists of sediment columns up to 12 km thick capped by evaporites. These geological and oceanographic facts led to speculation that Levantine sea contains big gas and oil deposits trapped in evaporites. Recently Eni discovered the Zohr gas field, largest known gas field in the Mediterranean. The Zohr gas field holds around of gas. It is estimated that in the Levant Basin there are around of undiscovered gas resources. Also they estimated that there could be up to 1.7 billion barrels of recoverable oil.

Israeli and Cyprus gas fields

is Cyprus's offshore gas field at the exploratory drilling block 12 in the Cyprus maritime Exclusive Economic Zone. It is estimated that block 12 holds of natural gas. Exploration is continuing in other blocks in the Cyprus EEZ. Calypso gas field in block 6 was found in 2018, and it is estimated that holds of gas.
First significant Israeli gas discovery was gas in Mari-B field in 2000. Mari-B field produced gas until 2013 covering 40% of Israeli natural gas demand. Offshore Tamar gas field of was discovered in 2009. Commercial production from Tamar field started in 2013. It covers nearly all industrial needs and gas from Tamar field generates over half of the country's electricity. In 2010, the Leviathan gas field was discovered off the coast of Israel. It is estimated the field contains around of
natural gas.

Infrastructure

The EuroAsia Interconnector will link Israel with Cypriot and Greek power grids with high-voltage direct current submarine power cable of length around.
It will have a capacity to transmit 2,000 megawatts of electricity in either direction.
The cable will link Israel with Cyprus. Cyprus will be connected with the Greek island of Crete with long cable. The laying depth of cable will be up to under sea level in some areas between Crete and Cyprus. It will be conducted in two stages.
In the first stage it will have 1000 MW capacity. It is expected to cost €2.5 billion in the first stage. Interconnection between Hadera in Israel and Kofinou on Cyprus will be finished in December 2023. Longest interconnection between Kofinou on Cyprus and Korakia on Crete will be delivered in December 2023.

Configuration for Stage 1

The Interconnector provides important electricity highway in Southeastern EU and ends the electricity energy isolation of Cyprus and Crete interconnecting EU and Israel. The Interconnector's main components are:
Pair of cables will connect all converter stations. A Converter station converts direct current to alternating current or the reverse. It could receive power through cable and send it to the grid. Converter stations are bipolar and could run bidirectionally enabling import or export of electricity depending on demand. Cables will run along bottom of the sea and on land will run underground. Sea electrodes are used in case of cable or converter stations fault. Sea electrodes are placed at seabed several kilometers from shore and they are connected to converter stations. Converter stations will be of Voltage Source Converter type. Each converter station is designed to be rated 1000 MW and will be made of two converter bridges of 500 MW.
Submarine power cables will be of extruded type.
cables

Configuration for Stage 2

In stage two additional 1000 MW converter stations will be built in Crete and Israel and will add an additional 1000 MW bipole cable on route Israel-Cyprus—Greece. Stage 2 will increase transfer capacity to 2000 MW.

Project of EU Common Interest

The European Commission adopted on 14 October 2013 under Regulation No. 1391/2013 first list of key EU Projects of Common Interest. EuroAsia Interconnector is accepted as a cluster of three EU Projects of Common Interest important as trans-European energy infrastructure project. Main criteria for Projects of Common Interest is market integration, security of energy supply, enhancing competition and reduction of. On 18 November 2015 the European Commission adopted second revised list of 195 EU Projects of Common Interest. EuroAsia Interconnector is included also on revised list. On 23 November 2017, Euroasia Interconnecter was included on third final list of EU Projects of Common Interest.
The European Commission issued the 4th PCI list on October 31 2019 and the Euroasia Interconnector remains as PCI 3.10.
On 29 October 2014 the EU announced funding for 3 prestudies of the Interconnector project. These studies secured half of cost from the Connecting Europe Facility. On 17 February 2017, European Commission approved €14.5 million as financial support for final detailed studies prior to Project Implementation.
EU covers half of cost of final detailed pre-works studies. The Interconnector was selected for funding as one of seven electricity projects. According to the EU Commission, the project contributes the Energy Union's goals by increasing security of energy supply, connecting European energy networks, and also contributes integration of renewable energy sources across the EU.
on 4 March 2012, Israeli energy minister Uzi Landau endorsed its commitment to implementing Interconnector to CEO Euroasia Interconnector Nasos Ktorides

EU Priority Electricity Highway

EuroAsia Interconnector has been labelled as a priority electricity corridor, and as priority Electricity Highway Project. On 23, November 2017, Euroasia Interconnector was on the third final list of EU Projects of Common Interest and has been labelled by the ENTSO-E as priority Electricity Highway Interconnector. Euroasia Interconnector was also on the fourth final list of EU Projects of Common Interest labelled as priority Electricity Highway Interconnector.

Big reduction of emission

assessed positively the Interconnector project based on cost-benefit analysis methodology. It is therefore included in the ten-year network development plan 2014 and then also TYNDP 2016.
According to the cost-benefit analysis of ENTSO-E, the Interconnector will contribute to social and economic welfare between €580m and €1.12 billion in each year. The cost-benefit analysis is done using four different visions. Reduction of emission is expected to be between 1.3 million tonnes and 6.8 million tonnes each year. For comparison Cyprus had emission of 6.16 million tonnes during 2015. Therefore, reduction of emission will be between 21% and 110% of total Cyprus emission. Based on new assessments best estimate of reduction of emission is expected to be 1.16 million tonnes for Stage 1.
Development of renewable energy sources on isolated systems like Cyprus and Crete could compromise islands electrical systems due to chaotic production fluctuations. Integration of renewable energy sources without interconnection is therefore limited. Electricity interconnection will enable and unlock integration of high percentage of renewable sources in such isolated systems.

History and development

EuroAsia Interconnector project was announced by Nasos Ktorides in Nicosia on 23 January 2012, stressing the role of Cyprus as energy bridge between Europe and Asia.
A cooperation agreement for conducting the feasibility study was signed in Jerusalem on 4 March 2012 between the project operator EuroAsia Interconnector Ltd., and the Israel Electric Corporation in the presence of Israeli minister for Energy and Water Resources Uzi Landau and Yiftah Ron-Tal, Director of the Israel Electric Corporation. On 23 March 2012, in Nicosia, the Electricity Authority of Cyprus signed a cooperation agreement with the project operator.
On 8 August 2013, the ministers of energy of Cyprus, Israel and Greece met in Cyprus. They signed the tripartite energy memorandum and reconfirmed their support for the Interconnector.
, Shu Yinbiao and Nasos Ktorides
On 14 October 2013, the Interconnector was accepted as cluster of three EU Projects of Common Interest. Later it was also accepted on the second, third and fourth lists of key EU Projects of Common Interest.
In a meeting between the Israeli and Cypriot energy ministers in June 2015, the Israeli minister suggested doubling the planned capacity of the cable. With Israel and Cyprus both having located natural gas deposits within their territories, a higher capacity cable would allow them to construct gas-driven power plants and export significant amounts of electricity to Europe.
On 11 January 2016 in Nicosia Vice-President of the European Commission Maroš Šefčovič met with President of Cyprus Nicos Anastasiades and Minister of Energy Giorgos Lakkotrypis. They discussed huge potential of eastern Mediterranean for energy supply of Europe and pointed out EuroAsia Interconnector as a bridge and highway for energy supply.
Three pre-works phase studies were awarded on 18 December 2015 to the Italian companies CESI and G.A.S. S.r.l..The three studies are for the technical design, the reconnaissance study for the optimum route and an environmental impact study.
In January 2016, the Italian research ship Odin Finder started a reconnaissance study for the optimum route of the underwater cable. It took about 100 days to complete the survey. All three preworks studies were finished in 2016 and led to the next phase of the final pre-construction studies.
presents Euroasia Interconnector
On 28 January 2016, the first Cyprus-Israel-Greece tripartite meeting took place in Nicosia.
During that meeting President of Cyprus Nicos Anastasiades, the Prime Minister of Greece Alexis Tsipras and the Prime Minister of Israel Benjamin Netanyahu affirmed their full support for the EuroAsia Interconnector. When they met again on December 8, 2016 in Jerusalem they reaffirmed their full support for the timely implementation of EuroAsia Interconnector.
On 17 February 2017, The European Commission approved €14.5 million as financial support for final detailed studies prior to Project Implementation.
On April 5, 2017 INEA signed the grant agreement to finalize the Interconnector's design by supporting final detailed pre-works studies.
On May 12, 2017 the Greek Prime Minister Alexis Tsipras
met State Grid Corporation of China Chairman Shu Yinbiao in Beijing accompanied by Euroasia Interconnector CEO Nasos Ktorides
and had discussions on jointly promoting of the Belt and Road Initiative and the strengthening of power and energy cooperation. Prime Minister Tsipras expressed his appreciation for the support Mr. Shu Yinbiao has given to the development of the Greek grid and the contribution made by State Grid Corporation of China towards the timely implementation of EuroAsia Interconnector.
The fiber-optic Quantum Cable was supported at a trilateral meeting of Prime Ministers of Greece Alexis Tsipras, Israel Benjamin Netanyahu and the President of Cyprus Nicos Anastasiades, in the Greek city of Thessaloniki on 15 June 2017. They pointed out that EuroAsia Interconnector is strategically important for Greece, upgrading her status into a regional electricity and telecom hub.
The EuroAsia Interconnector cross border cost allocation was approved by the Energy Regulatory Authorities of Cyprus and Greece on 10 October 2017 and 21 March 2018. It is a historic decision for Cyprus, ending electricity isolation of the last EU member state.
Elia, Belgium’s electricity transmission system operator, announced on 12 December 2017 that it had concluded a strategic alliance agreement with the EuroAsia Interconnector for the development and implementation of the 2,000 MW subsea electricity interconnector.
, Ambassador of Israel; George Killas, Project Director; Yiorgos Lakkotrypis, Minister of Energy; Ilias Fotopoulos, Ambassador of Greece; Thessalia Shambos, Cyprus Ambassador in Israel; Demosthenis Voivodas, Directorate of Licensing, General Secretariat of Strategic Investments of Greece
Former Cyprus Foreign Minister and head of the European Parliament Foreign Affairs Working group, Ioannis Kasoulides, joined EuroAsia Interconnector on 30 March 2018 as Chairman of the Strategic Council. On 11 September 2018, Dr. Kasoulides received the highest decoration awarded by France – Officer of the Order of the Legion of Honour.
In a speech at the public consultation held at the Hilton Cyprus on 2 April 2018, Cyprus Energy Minister Yiorgos Lakkotrypis described the project as
of particular national geopolitical importance, as it enables Cyprus and Greece to act as bridges of cooperation, linking the eastern Mediterranean with the European Union''.
On 8 May 2018, the fourth Cyprus-Israel-Greece tripartite meeting took place in Nicosia. Prime Ministers of Greece Alexis Tsipras, Israel Benjamin Netanyahu and the President of Cyprus Nicos Anastasiades reconfirmed their support to the timely implementation of EuroAsia Interconnector and Quantum Cable, the accompanying fiber optic cable.
The procurement stage of the project started on 13 February 2018 by notice for construction of Stage 1 with an estimated budget of €3.5 billion, published in the Official Journal of the European Union.
A call for four tenders with estimated budget €3.27 billion was published on 17 April 2018 in the Official Journal of the European Union.
On 10 January 2019, after a series of individual meetings with all successful converter station and cable manufacturers, EuroAsia Interconnector Ltd, as project promoter, has issued tender documents for contracts worth €3.5bn for the design and construction of the EuroAsia Interconnector.
A meeting between the European Commission and Cyprus authorities took place on February 27, 2019 in Nicosia. In a joint communique they have again shown full support for the timely implementation of EuroAsia Interconnector as a Project of Common Interest and they recognised EuroAsia Interconnector as the official project promoter. Also they pointed out that best way for the timely implementation and optimal interoperability is under provisions of the Roadmap of European Commission from 16, Octobar 2018.
On 6 June 2019, Giorgos Lakkotropis, the Minister of Energy, signed on behalf of the Cyprus government a 33-year land concession agreement for construction of HVDC converter station.
On July 3, 2019 EuroAsia Interconnector Ltd, project promoter, announced the final stage of tenders for construction of the Euroasia Interconnector.
On October 11, 2019 Minister of Environment and Energy Kostis Hatzidakis on behalf of Government of Greece and Prime Minister said that Greece provides strong political support to the work of Cyprus's electrical interconnection with Greece and Israel as PCI projects, in order to lift Cyprus's electrical isolation and link the island to the European Union's electricity grids.
The Republic of Cyprus has issued in July 2020 final building permit for the construction of the HVDC converter station in Cyprus.

Benefits of EuroAsia Interconnector

The interconnector is fully funded by EuroAsia Interconnector Ltd. and European Union. The company headquarters are in Nicosia, Cyprus.
EuroAsia Interconnector Ltd. is part of.