Clyde Arc


The Clyde Arc is a road bridge spanning the River Clyde in Glasgow, Scotland, connecting Finnieston near the Clyde Auditorium and SEC with Pacific Quay and Glasgow Science Centre in Govan. A prominent feature of the bridge is its innovative curved design and the way that it crosses the river at an angle. The Arc is the first city centre traffic crossing over the river built since the Kingston Bridge was opened to traffic in 1970.
The bridge was named the "Clyde Arc" upon its official opening on 18 September 2006. It has been previously known as the "Finnieston Bridge" or the "Squinty Bridge".

Design

The bridge was designed by the Halcrow Group and built by Kilsyth-based civil engineering company Edmund Nuttall. Glasgow City Council instigated the project in conjunction with Scottish Enterprise and the Scottish Government. Piling works for the bridge were carried out from a large floating barge on the Clyde, whilst the bridge superstructure was fabricated offsite. The bridge-deck concrete-slab units were cast at an onsite pre-casting yard. Planning permission was granted in 2003 and construction of the bridge began in May 2005. It was structurally completed in April 2006. The bridge project cost an estimated £20.3M. The Bridge is designed to last 120 years.
The bridge has a main span of with two end spans of, resulting in a total span of. The design of the main span features a steel arch. The supports for the main span are located within the river with the abutments located behind the existing quay walls. The central navigation height at mean water height is.
It was officially opened on 18 September 2006 by Glasgow City Council leader Steven Purcell, although pedestrians were allowed to walk across it the previous two days as part of Glasgow's annual "Doors Open" Weekend.
The bridge connects Finnieston Street on the north bank of the river to Govan Road on the southern bank. The bridge takes four lanes of traffic, two of which are dedicated to public transport and two for private and commercial traffic. There are also pedestrian and cycle paths. The new bridge was built to provide better access to Pacific Quay and allow better access to regeneration areas on both banks of the Clyde. The bridge has been designed to cope with a possible light rapid transit system or even a tram system.
The bridge is the first part of a massive development project planned to regenerate Glasgow. There are two more bridges planned – the £40M Tradeston Bridge and a further pedestrian bridge linking Springfield Quay with Lancefield Quay on the north bank. The canting basin and graving dock next to Pacific Quay are to be developed along with Tradeston and Laurieston. Plans are afoot to transform Rutherglen and Dalmarnock as the 'athletes' village' for the 2014 Commonwealth Games in Glasgow.

Support hanger failure

The bridge was closed between 14 January and 28 June 2008 due to the failure of one support hanger, and cracks found in a second.
On the night of 14 January 2008 the connecting fork on one of the bridge's 14 hangers snapped; Strathclyde Police quickly closed the bridge to traffic. Robert Booth, a spokesman for Glasgow City Council said:
A detailed inspection on 24 January found a stress fracture in a second support cable stay, like the one which had failed previously. Engineers determined that all of these connectors would have to be replaced; rather than a brief closure the bridge would have to remain closed for six months. In addition traffic on the river below was also halted. In March Nuttall began installing five temporary saddle frames atop the bridge's arch; these allowed the weight of the bridge to be supported without the hangers. This allowed them to replace defective fork connectors at the top and bottom of each hanger.
The bridge recommenced on 28 June 2008 with just two of its four lanes in use, having had all the cast steel connectors replaced with milled steel connectors. Once reopened, Glasgow City Council estimated that 6,500 crossings will be made every day using the bridge.
On 8 January 2009, New Civil Engineer reported that subcontractor Watson Steel was suing Macalloy, the supplier of the suspect connectors, for £1.8 million. According to reports, Watson alleges steel obtained from Macalloy did not meet British Standards or their own specifications; parts were inadequately manufactured, and did not tally with test certificates provided by the firm.