Bullfrog Goldfield Railroad


The Bullfrog Goldfield Railroad was a former Class II railroad lying just inside and about midway of the southwestern State line of Nevada. It was incorporated in 1905 to provide an outlet from the mining section near Beatty to the north over the lines of the Tonopah and Goldfield Railroad and the Southern Pacific Railroad.

Track

The main line of the Bullfrog Goldfield Railroad Company extended from Beatty in a general north-northwesterly direction to Goldfield. A long branch line, ran westward from Beatty to Rhyolite. The total road mileage owned was thus 84.78 miles. Yard tracks and sidings to an aggregate of brought the total owned mileage to. The Bullfrog Goldfield Railroad Company owned no terminal facilities, as such, but used the station and yard facilities at Beatty belonging to the Las Vegas & Tonopah Railroad Company.

Corporate history

The Bullfrog Goldfield Railroad Company was incorporated September 1, 1905, under the general laws of Nevada, for a period of 50 years, by interests connected with the Tonopah and Goldfield Railroad Company and apparently connected with the Tonopah Mining Company. The purpose was to build a line from the southern terminus of the line of the Tonopah and Goldfield Railroad Company, at Goldfield, southward to the mining field in which Beatty and Rhyolite were the principal camps, thereby giving an outlet to this mining territory over the line of the Tonopah and Goldfield Railroad Company to the Central Pacific Railway Company at Tonopah in competition with the lines of the Las Vegas and Tonopah Railroad Company and the Tonopah and Tidewater Railroad Company, both of which had connections southward.
Construction was by the Amargosa Construction Company under contracts dated March 20, 1906, and December 27, 1907. The mileage shown above is that appearing in the records of the Bullfrog Goldfield Railroad Company. Construction commenced in the early part of 1906, and the line was completed, equipped, and opened for operation in May, 1907, from which date the Amargosa Construction Company operated the road until January 1, 1908.
Funds for construction were furnished by the construction company, called Amargosa Construction Company, which, in turn, appears to have been supplied by a syndicate, called the Bullfrog syndicate, in existence at the time of construction. It seems that the Bullfrog syndicate controlled the Amargosa Construction Company, but the records obtainable do not disclose that the officers or directors of the Bullfrog Goldfield Railroad Company had any interest in the Bullfrog syndicate or the Amargosa Construction Company.
Mining, the basic industry in this region, suffered a severe decline soon after the Bullfrog Goldfield Railroad Company was completed. The decline of the mining resources soon led, in 1908, to a joint operating arrangement with the Tonopah & Tidewater Railroad Company under a holding company incorporated in Delaware as the Tonopah & Tidewater Company. The failure of this arrangement to bring about the desired financial improvement led to a reorganization in June, 1914, whereby the parallel line of the Las Vegas & Tonopah Railroad Company was eliminated and the Bullfrog Goldfield Railroad Company passed under the control of the latter company, with which it has since been operated as a continuous road, but as a distinct corporation.
The traffic scarcity which ensued, coupled with the competition of the Las Vegas & Tonopah Railroad Company's line, which paralleled the Bullfrog Goldfield Railroad Company's line to Goldfield and also had a southern connection, induced the Bullfrog Goldfield Railroad Company to unite with the Tonopah and Tidewater Railroad Company, which had a southern connection in competition with the Las Vegas & Tonopah Railroad Company, in a traffic arrangement in which the principal feature was the operation of both roads as one system. The joint-operating plan became effective January 1, 1908. To insure to each an equitable participation in the advantages which it was hoped would accrue from this plan, a holding company, named Tonopah and Tidewater Company, was incorporated in Delaware and exchanged its own capital stock, share for share, for all of the capital stock, except directors' qualifying shares, of the two railroads.
However, owing to the constant shrinkage in traffic, this arrangement did not yield the anticipated results. Both companies continued to operate at a deficit, the Tonopah and Tidewater Railroad Company making advances to the Bullfrog Goldfield Railroad Company to assist it in meeting its charges and, in turn, being assisted by the interests behind it. The Bullfrog Goldfield Railroad Company finally became so involved that it could not pay its debts. To avert foreclosure, a reorganization agreement was concluded June 26, 1914, between the Bullfrog Goldfield Railroad Company, a committee representing its security holders, and the Las Vegas & Tonopah Railroad Company, whereby parallel portions of the lines of both the Bullfrog Goldfield Railroad Company and the Las Vegas & Tonopah Railroad Company were abandoned, changes were made in the capitalization of the Bullfrog Goldfield Railroad Company, and traffic arrangements were agreed upon. When this plan became effective, July 20, 1914, the joint agreement with the Tonopah and Tidewater Railroad Company was canceled and the Tonopah and Tidewater Company dissolved.
The Bullfrog Goldfield Railroad Company was controlled by the Las Vegas & Tonopah Railroad Company through the ownership of 51 per cent of its outstanding capital stock, acquired in the reorganization settlement of 1914. The two railroads have since been operated as a single road, although as distinct corporations, between Goldfield and Las Vegas.
In accordance with the reorganization agreement of June 26, 1914, the Bullfrog Goldfield Railroad Company conveyed to the Las Vegas & Tonopah Railroad Company the line from Rhyolite to Beatty, and from Bonne Claire to Goldfield, total. It acquired from the Las Vegas & Tonopah Railroad Company its line from Beatty to Rhyolite , and from Bonnie Claire to Goldfield, total. These transfers changed the Bullfrog Goldfield Railroad Company's mileage so that, at June 30, 1915, the line owned comprised, according to surveys by ICC engineers:

Locomotives

Closure

The Bullfrog Goldfield Railroad ceased to operate in January 1928. Before the closure, it had leased its tracks to either the Tonopah & Tidewater Railroad Company or to the Las Vegas & Tonopah Railroad Company. Management changed hands on 5 occasions over its 21 year long existence. The Bullfrog Goldfield freight depot and maintenance building stood at Fifth Avenue and Pearl Street of Goldfield opposite the Santa Fe Saloon and has been reconstructed in 2017.