Boundary Dam Power Station


Boundary Dam Power Station is the largest coal fired station owned by SaskPower, located near Estevan, Saskatchewan, Canada.

Description

The Boundary Dam Power Station consists of two 62 net MW units ; two 139 net MW units, one of which—Unit 3—was decommissioned and replaced with a new 160 MW unit in 2013; one 139 net MW unit ; and one 273 net MW unit.
The boilers are supplied by Babcock & Wilcox and Combustion Engineering while the turbines/generator are supplied by General Electric and Hitachi.
There is also Boundary Dam located next to the station. It is an earth fill dam, which created the Boundary Reservoir on Long Creek a few kilometres west of the river's mouth on the Souris River. The station uses water from the reservoir for coolant, which is why Boundary Reservoir is the only body of water in Saskatchewan that doesn't freeze over during the winter months and supports largemouth bass.
The plant has five 300 ft tall smokestacks. SaskPower has advised that the project has a 30-year life.

Carbon capture and storage demonstration project

The Boundary Dam Integrated Carbon Capture and Storage Demonstration is a project to retrofit the lignite-fired Unit #3 with carbon capture and an enhanced oil recovery system. It consists of two distinct parts: Repowering of the existing Unit #3 and the installation of the carbon dioxide, sulfur dioxide and NOx capture facility. Its primary purpose is to provide a low-cost source of carbon dioxide, to the mature Weyburn Oil Field, for enhanced oil recovery. It is expected to result in a 90 percent reduction in CO2 emissions and will also reduce the output of Unit 3 from 139 MW to 110 MW. Critics point out that the 90% figure refers to the percentage of total CO2 emissions captured, and that only about a half of this CO2 will be actually be permanently stored. The remainder is released into the atmosphere during capturing and processing in the oil field. The retrofitted unit was officially opened in October 2014, and is the world's first commercial-scale, lignite-fired power plant equipped with carbon capture and storage technology
In 2015, internal documents from SaskPower revealed that there were "serious design issues" in the carbon capture system, resulting in regular breakdowns and maintenance problems that led the unit to only be operational 40% of the time. SNC-Lavalin had been contracted to engineer, procure, and build the facility, and the documents asserted that it "has neither the will or the ability to fix some of these fundamental flaws." The low productivity of the plant had in turn meant that SaskPower was only able to sell half of the 800,000 tonnes of captured carbon dioxide that it had contracted to sell to Cenovus Energy for use in enhanced oil recovery at a cost of $25 per tonne. In addition to the lost sales, this meant that SaskPower had been forced to pay Cenovus $12 million in penalties. In June 2016, and to avoid paying a $91-million penalty, SaskPower renegotiated its CO2 supply contract with Cenovus. That renegotiation means annual revenues are reduced from $25 million to "$16-17 million". Over the 30-year project life this represents reduced revenue of $240 million to $270 million and will further weaken the project economics. Cenovus sold its Saskatchewan interests in 2017 to Whitecap Resources.
Several major publications have noted what they deem poor economics of the project, among them The Economist, The Financial Times, The MIT Technology Review, and The New York Times. An April 2016 Parliamentary Budget Office report found that CCS at Boundary Dam doubles the price of electricity.
Financial concerns appear to fall into three main areas:
Among environmental concerns, critics note that while 90% of CO2 smokestack emissions are captured, only a portion is stored. Almost half of captured emissions end up being released in the atmosphere by processing in the oil field and the capturing process.
Among other concerns, critics point to the following:
All of these concerns are compounded by a lack of transparency: As of 2015 the project operators had not presented any financial or environmental performance numbers.
In July 2018, SaskPower announced that it would not retrofit Units 4 and 5 with CCS, with minister responsible Dustin Duncan saying that the units were approaching their mandated shut down in 2024 and that natural gas is a cheaper option.

Capital cost

In February 2008 the Saskatchewan government announced that it would proceed with a 7-year reconstruction and repowering of Boundary Dam's Unit 3. The initial project cost was $C 1.24 billion out of which $C 240-million was from the federal government. Budget over-runs have led to the plant having a total cost of some $C 1.5 billion.

Revenue

Other than the generation of electricity, the plant will have several by-products which will generate revenue.

Carbon dioxide

The facility will capture 90 percent of total carbon dioxide emissions from Unit 3 or one million tonnes annually.
Most of the total annual carbon dioxide capture volume, at least for the first ten years of the project, was sold to Alberta-based Cenovus Energy, the operator of the Weyburn Oil Field. SaskPower has not publicly disclosed the sale price but Minister Boyd has stated that it is "in the range of" $25 per tonne. Annual revenue from carbon dioxide sales is thus estimated at $25 million. Cenovus Energy used the carbon dioxide mainly for field injection work to increase crude oil production before its Saskatchewan operations were sold to Whitecap Resources.

Sulfuric acid

Most of the sulfur emissions from the power station will be captured, converted to sulfuric acid and sold. SaskPower sulphur dioxide emissions are approximately 5 tonnes per gigawatt hour of system generation. Given annual electricity generation of 1,010 gigawatt hours, it follows that total annual sulfur capture will be 5,050 tonnes.

Fly ash

, also known as flue ash, is one of the residues generated following the combustion of coal and lignite. In the past it was released into the atmosphere through the smoke stack but pollution control requirements have put an end to that practice. It is now captured by electrostatic precipitators and stored at the point of generation, placed in landfills or recycled - where it will typically replace Portland Cement in concrete production. Typical fly ash recovery rates, for Saskatchewan lignite-fired power stations, are 31 kilograms per megawatt hour. Fly ash, depending on its use, can attract a range of prices. The best arises from concrete-quality ash which fetches $22–$49 per tonne.

Expenses

There appear to be two main expense items: Operations and maintenance, and parasitic load. In the latter, carbon and sulfur dioxide amine-based capture units, such as the one at Boundary Dam, consume significant amounts of electricity and heat in operation and the largest single component is associated with solvent regeneration. Significant electrical load is also used to run additional emission control components as well as associated pumps and other equipment.